Pure DC Amsterdam Westpoort AMS01

Amsterdam Westpoort, NH, NetherlandsUnder construction
Evidence
Planned critical IT
78 MW
Updated
Oct 28, 2026

On May 28, 2026, Pure DC announced a $2.15 billion financing facility supporting its Dublin and Amsterdam developments. This is shared financing, not $2.15 billion assigned solely to AMS01, and does not establish a new commissioning date. The substation is operational and data-hall construction is underway. The 78 MW campus is fully leased, with phased delivery anticipated from 2028. Pure DC Amsterdam Westpoort AMS01 is in Amsterdam Westpoort, NH, NL and is a data center campus with under construction status.

Capacity

Planned IT capacity

Planned / design or future potential

78 MW

Source

Per tower IT capacity

Planned / design or future potential

26 MW

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

AMS01 Tower 1Planned

1 building

Each tower is designed for 26 MW.

AMS01 Tower 2Planned

1 building

Each tower is designed for 26 MW.

AMS01 Tower 3Planned

1 building

Each tower is designed for 26 MW.

Milestones (4)
Pure DC disclosed fully leased AMS01 with power and permits

Dec 15, 2025 · Recorded actual event

Completed · Event type not stated

Source not linked
Data-hall construction began

Jan 2026 · Recorded actual event

Completed · Construction started

Source not linked
Pure DC confirmed Amsterdam construction underway

Jul 21, 2026 · Recorded actual event

Completed · Event type not stated

Source not linked
Phased delivery anticipated from 2028

2028 · Forecast / planned record

Forecast · Event type not stated

Source not linked

Participants

Brookfield Asset Management

Owner

Sources by role
Oaktree Capital Management

Owner

Sources by role
Owner (1)
Owner (1)
Pure Data Centres Group

Developer · Operator

Sources by role
Developer (1)
Developer (1)
Operator (1)
Other participants (1)
Port of Amsterdam

Government authority

Sources by role

Capital & incentives

Capital claims and financing records may overlap. Their amounts are not added together.

Capital claims

Expected investment

Actual

€1 billion

Source

Financing records

Long leasehold acquisition

Amount not disclosed

Dec 15, 2025

Long leasehold over 5.68-acre Amsterdam Westpoort site; consideration and term undisclosed.

Parties & sources

Port of Amsterdam (Lessor) · Pure Data Centres Group (Lessee)

Site & development

Planned building count

Actual

3 towers

Source

Planned floor area

Actual

94,660 square metres

Source

Site area

Actual

5.68 acres

Source

Technical specifications

Grid connection voltage

Actual

50 kV

Source

Additional project facts

Utility service capacity

Actual

100 MVA

Source

Private substation operational

Source report

True

Source

Fully leased

Source report

True

Source

Customer disclosed

Source report

False

Source

Tower height

Actual

85 metres

Source

Target PUE

Actual

1.2 ratio

Source

Phased delivery from year

Actual

2028

Source

Infrastructure & permits

Technical details (2)
Electric grid

Operational

100 MVA

Live private substation; operator and transformer configuration not disclosed.

Electric grid

Secured or contracted

50 kV

Firm grid connection serving the private substation.

Public-source research. Plans may change. See Evidence for sources and qualifications.