Cartis diligence evidence schedule

Prometheus WY-2

PRJ-1110 · Site · Casper, Wyoming, United States

Record last updated Oct 28, 2026

Scope and capacity

Prometheus WY-2 is Prometheus Hyperscale’s proposed Casper-area campus in Wyoming. Developer and state materials describe up to 1.5 GW of IT-ready capacity over multiple phases, backed by onsite natural-gas generation and a carbon-capture partnership, with at least $500 million of initial investment. Wyoming economic-development records also identify the Casper project as certified for the state data-center sales-tax exemption. The 1.5 GW figure is future phased capacity, not operating load, and first-power, permits, customer commitments and carbon performance remain prospective.

Headline: 1,500 MW Planned / design

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Location context · Prometheus WY-2 | Casper | Wyoming | US

Actual · Prometheus WY-2 (Project)

Claim 70412 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Prometheus WY-2 public-record research record

    US Data Center Map · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4038 · News report · Recorded authority: Secondary

    Source URL

    https://dcmap.us/states/wyoming/

Lifecycle status · Proposed

Actual · Prometheus WY-2 (Project)

Claim 70413 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Prometheus WY-2 public-record research record

    US Data Center Map · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4038 · News report · Recorded authority: Secondary

    Source URL

    https://dcmap.us/states/wyoming/

Reported capacity · 1,500 MW

Planned / design or future potential · Prometheus WY-2 (Project)

Claim 70414 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Selected headline

  1. Prometheus WY-2 public-record research record

    US Data Center Map · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4038 · News report · Recorded authority: Secondary

    Source URL

    https://dcmap.us/states/wyoming/

Capacity basis · 1,500 MW future full build site capacity; not measured operating IT load.

Actual · Prometheus WY-2 (Project)

Claim 70415 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Prometheus WY-2 public-record research record

    US Data Center Map · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4038 · News report · Recorded authority: Secondary

    Source URL

    https://dcmap.us/states/wyoming/

Location context · Prometheus WY-2 | Casper | Wyoming | US

Actual · Prometheus WY-2 (Project)

Claim 74678 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Prometheus WY-2 public-record research record

    US Data Center Map · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4038 · News report · Recorded authority: Secondary

    Source URL

    https://dcmap.us/states/wyoming/

Lifecycle status · Proposed

Actual · Prometheus WY-2 (Project)

Claim 74679 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Prometheus WY-2 public-record research record

    US Data Center Map · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4038 · News report · Recorded authority: Secondary

    Source URL

    https://dcmap.us/states/wyoming/

Reported capacity · 1,500 MW

Planned / design or future potential · Prometheus WY-2 (Project)

Claim 74680 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Separate claim, not added to the headline

  1. Prometheus WY-2 public-record research record

    US Data Center Map · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4038 · News report · Recorded authority: Secondary

    Source URL

    https://dcmap.us/states/wyoming/

Capacity basis · Up to 1,500 MW is future phased IT-ready capacity; no operating load is claimed.

Actual · Prometheus WY-2 (Project)

Claim 74681 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Prometheus WY-2 public-record research record

    US Data Center Map · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4038 · News report · Recorded authority: Secondary

    Source URL

    https://dcmap.us/states/wyoming/

Initial investment · $500,000,000

Reported rounded · Prometheus WY-2 (Project)

Claim 74682 · Recorded claim type: Reported rounded · Review: Approved · Claim date: Not stated

  1. Prometheus, Spiritus and Casper Carbon Capture announce Wyoming partnership

    Prometheus Hyperscale · Document date: Oct 7, 2025 · Primary

    Source reference: SRC-4276 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.prnewswire.com/news-releases/prometheus-hyperscale-spiritus-and-casper-carbon-capture-announce-strategic-partnership-to-build-carbon-negative-data-halls-and-energy-infrastructure-in-wyoming-302576579.html

Carbon partner · Spiritus / Casper Carbon Capture

Actual · Prometheus WY-2 (Project)

Claim 74684 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Prometheus, Spiritus and Casper Carbon Capture announce Wyoming partnership

    Prometheus Hyperscale · Document date: Oct 7, 2025 · Primary

    Source reference: SRC-4276 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.prnewswire.com/news-releases/prometheus-hyperscale-spiritus-and-casper-carbon-capture-announce-strategic-partnership-to-build-carbon-negative-data-halls-and-energy-infrastructure-in-wyoming-302576579.html

Tax exemption certification · Wyoming data center sales tax exemption

Actual · Prometheus WY-2 (Project)

Claim 74685 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Wyoming Business Council data-center materials

    Wyoming Legislature · Document date: Jun 5, 2026 · Primary

    Source reference: SRC-4277 · Government record · Recorded authority: Official primary

    Source URL

    https://wyoleg.gov/InterimCommittee/2026/09-202606049-05WBCMaterialsPreparedforJointMinerals06052026.pdf

Counterparties and capital

Prometheus Hyperscale · Developer · CMP-1415