Cartis diligence evidence schedule
Project Blue
PRJ-1159 · Site · Tucson, Arizona, United States
Record last updated Oct 28, 2026
Scope and capacity
Project Blue is Beale Infrastructure’s data-center campus on approximately 290 acres north of the Pima County Fairgrounds in unincorporated Pima County, Arizona. The developer acquired the County land on December 24, 2025. County materials describe approximately ten buildings and up to $3.6 billion in planned capital investment. The Arizona Corporation Commission approved Tucson Electric Power’s electric-service agreement in December 2025 for an initial 286 MW of utility service. Beale’s current project timeline records a first-quarter 2026 construction start and targets phase-one completion in 2028. The developer describes an air-cooled, closed-loop design and estimates average water use of 15,000–20,000 gallons per day, primarily for domestic building needs and fire protection. Beale’s current project listing describes an expected capacity of 600 MW; the listing does not specify whether this is IT or gross facility capacity. This is separate from the initial 286 MW electric-service agreement.
Headline: Not established in published records
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (15)
Location context · Unincorporated Pima County, north of the Pima County Fairgrounds, Arizona
Actual · Project Blue (Project)
Claim 71958 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Project Blue FAQ
Pima County · Document date: Not stated · Primary
Source reference: SRC-4466 · Government record · Recorded authority: Official primary
Source URL
https://www.pima.gov/3552/Project-Blue-FAQ
https://www.pima.gov/3552/Project-Blue-FAQ
Lifecycle status · Construction
Actual · Project Blue (Project)
Claim 71959 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Pima County data center project
Beale Infrastructure · Document date: Not stated · Primary
Source reference: SRC-4467 · Company announcement · Recorded authority: Party primary
Source URL
https://bealeinfra.com/location/pima-county/
https://bealeinfra.com/location/pima-county/
Site area · 290 acres
Actual · Project Blue (Project)
Claim 77925 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Project Blue FAQ
Pima County · Document date: Not stated · Primary
Source reference: SRC-4466 · Government record · Recorded authority: Official primary
Source URL
https://www.pima.gov/3552/Project-Blue-FAQ
https://www.pima.gov/3552/Project-Blue-FAQ
Building count · 10 buildings
Design · Project Blue (Project)
Claim 77926 · Recorded claim type: Design · Review: Approved · Claim date: Not stated
- Progress Update on Project Blue Development
Pima County · Document date: Apr 23, 2026 · Primary
Source reference: SRC-8022 · Government record · Recorded authority: Official primary
Source URL
https://content.civicplus.com/api/assets/32428b1b-4a81-444a-92a4-72b1fa039655
https://content.civicplus.com/api/assets/32428b1b-4a81-444a-92a4-72b1fa039655
Reported investment · $3,600,000,000
Forecast · Project Blue (Project)
Claim 77927 · Recorded claim type: Forecast · Review: Approved · Claim date: Not stated
- Progress Update on Project Blue Development
Pima County · Document date: Apr 23, 2026 · Primary
Source reference: SRC-8022 · Government record · Recorded authority: Official primary
Source URL
https://content.civicplus.com/api/assets/32428b1b-4a81-444a-92a4-72b1fa039655
https://content.civicplus.com/api/assets/32428b1b-4a81-444a-92a4-72b1fa039655
Phase one completion target · 2028
Forecast · Project Blue (Project)
Claim 159219 · Recorded claim type: Forecast · Review: Approved · Claim date: Not stated
- Pima County data center project
Beale Infrastructure · Document date: Not stated · Primary
Source reference: SRC-4467 · Company announcement · Recorded authority: Party primary
Source URL
https://bealeinfra.com/location/pima-county/
https://bealeinfra.com/location/pima-county/
Capital investment · $3,600,000,000
Proposed · Project Blue Tucson (Project)
Claim AST-B4-001 · Recorded claim type: Proposed · Review: Approved · Claim date: May 21, 2025
- Project Blue FAQ
Pima County · Document date: Not stated · Supports
Source reference: BLU-01 · Government primary
Source URL
https://www.pima.gov/3552/Project-Blue-FAQ
https://www.pima.gov/3552/Project-Blue-FAQ
Site area · 290 acres
Parcel area · Project Blue Tucson (Project)
Claim AST-B4-002 · Recorded claim type: Parcel area · Review: Approved · Claim date: May 21, 2025
- Project Blue FAQ
Pima County · Document date: Not stated · Supports
Source reference: BLU-01 · Government primary
Source URL
https://www.pima.gov/3552/Project-Blue-FAQ
https://www.pima.gov/3552/Project-Blue-FAQ
Initial buildings · 4 buildings
Potential initial phase · Project Blue Tucson (Project)
Claim AST-B4-003 · Recorded claim type: Potential initial phase · Review: Approved · Claim date: May 21, 2025
- Project Blue FAQ
Pima County · Document date: Not stated · Supports
Source reference: BLU-01 · Government primary
Source URL
https://www.pima.gov/3552/Project-Blue-FAQ
https://www.pima.gov/3552/Project-Blue-FAQ
Maximum buildings · 10 buildings
Site potential · Project Blue Tucson (Project)
Claim AST-B4-004 · Recorded claim type: Site potential · Review: Approved · Claim date: May 21, 2025
- Project Blue FAQ
Pima County · Document date: Not stated · Supports
Source reference: BLU-01 · Government primary
Source URL
https://www.pima.gov/3552/Project-Blue-FAQ
https://www.pima.gov/3552/Project-Blue-FAQ
Original first operation · 2027
Forecast · Project Blue Tucson (Project)
Claim AST-B4-005 · Recorded claim type: Forecast · Review: Approved · Claim date: May 21, 2025
- Project Blue FAQ
Pima County · Document date: Not stated · Supports
Source reference: BLU-01 · Government primary
Source URL
https://www.pima.gov/3552/Project-Blue-FAQ
https://www.pima.gov/3552/Project-Blue-FAQ
Construction jobs · 3,000+ jobs
Forecast · Project Blue Tucson (Project)
Claim AST-B4-006 · Recorded claim type: Forecast · Review: Approved · Claim date: May 21, 2025
- Project Blue FAQ
Pima County · Document date: Not stated · Supports
Source reference: BLU-01 · Government primary
Source URL
https://www.pima.gov/3552/Project-Blue-FAQ
https://www.pima.gov/3552/Project-Blue-FAQ
Permanent jobs · 180 jobs
Forecast by 2029 · Project Blue Tucson (Project)
Claim AST-B4-007 · Recorded claim type: Forecast by 2029 · Review: Approved · Claim date: May 21, 2025
- Project Blue FAQ
Pima County · Document date: Not stated · Supports
Source reference: BLU-01 · Government primary
Source URL
https://www.pima.gov/3552/Project-Blue-FAQ
https://www.pima.gov/3552/Project-Blue-FAQ
Amazon participation · No
Reported withdrawal · Project Blue Tucson (Project)
Claim AST-B4-009 · Recorded claim type: Reported withdrawal · Review: Approved · Claim date: Oct 15, 2025
- The Arizona community fight against Project Blue
The Guardian · Document date: Oct 15, 2025 · Supports
Source reference: BLU-04 · Press secondary
Source URL
https://www.theguardian.com/us-news/2025/oct/15/tucson-arizona-ai-data-center-project-blue
https://www.theguardian.com/us-news/2025/oct/15/tucson-arizona-ai-data-center-project-blue
Developer intent to proceed · Yes
Reported · Project Blue Tucson (Project)
Claim AST-B4-010 · Recorded claim type: Reported · Review: Approved · Claim date: Sep 17, 2025
- Project Blue developer tells county they are still building
Tucson Sentinel · Document date: Sep 17, 2025 · Supports
Source reference: BLU-03 · Press secondary
Source URL
https://www.tucsonsentinel.com/local/report/091725_pima_project_blue/
https://www.tucsonsentinel.com/local/report/091725_pima_project_blue/
Counterparties and capital
Beale Infrastructure · Developer · CMP-1536
Tucson Electric Power · Utility provider, Utility · CMP-1719
Humphrey’s Peak Properties LLC · Project land entity
Pima County · Host jurisdiction and land seller
City of Tucson · Rejected annexation and water counterparty
$3,600,000,000 · May 21, 2025
Financing record legacy-financing-AST-B4-001; claim-specific source links appear in the exhibit sources where published.
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.