Prime Austin AUS01 Lockhart Data Center Campus

Lockhart, Texas, United StatesPreconstruction
Evidence
Planned critical IT
384 MW
Updated
Oct 28, 2026
Utility
Bluebonnet Electric Cooperative

Prime Austin AUS01 Lockhart Data Center Campus, also known as Prime Austin AUS01, is a data center project in Lockhart, TX, US associated with Prime Data Centers. 205-acre campus; eight planned hyperscale buildings; 2 million square feet; 384 MW total critical IT load. On-site substation, closed-loop air and liquid cooling, and ten carriers in proximity. 384 MW is the source-defined future IT or site design envelope. Disclosed investment or financing context is recorded with its transaction scope and is not treated as delivered project cost or proof of capacity.

Capacity

Reported capacity

Design

384 MW

Source

Reported capacity

Planned / design or future potential

384 MW

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Development, permitting and phased deliveryAnnounced or preconstruction

384 MW is the source-defined future IT or site design envelope. It is not operating IT load.

Milestones (1)
No operating status inferred from development evidence

Aug 30, 2026 · Recorded actual event

Completed · Status changed

Source not linked

Participants

Prime Data Centers

Developer

Sources by role
Developer (1)
Other participants (1)
Bluebonnet Electric Cooperative

Utility provider

Sources by role
Utility provider (1)

Capital & incentives

Financing records

Investment commitment

$5bn

Jan 25, 2021

Prime/Macquarie ten-year platform target; no amount is allocated to Austin.

Parties & sources

Prime Data Centers (Borrower)

Site & development

Location context

Actual

Prime Austin AUS01 | Lockhart | TX | US

Source

Location context

Actual

Prime Austin AUS01 | Lockhart | TX | US

Source

Location context

Actual

Lockhart, TX, US

Source

Development detail

Actual

205-Acre campus; eight planned hyperscale buildings; 2 million square feet; 384 MW total critical IT load.

Source

Additional project facts

Lifecycle status

Actual

Preconstruction

Source

Capacity basis

Actual

Prime Data Centers publishes 384 MW of critical IT capacity for this record boundary.

Source

Lifecycle status

Actual

Preconstruction

Source

Capacity basis

Actual

384 MW is the source defined future IT or site design envelope.

Source

Project identity

Actual

Prime Austin AUS01

Source

Lifecycle status

Actual

Preconstruction

Source

Capacity basis

Actual

384 MW is the source defined future IT or site design envelope.

Source

Infrastructure & permits

Technical details (3)
Electric grid

Planned or represented

On-site substation, closed-loop air and liquid cooling, and ten carriers in proximity.

Cooling system

Planned or represented

Cooling and efficiency claims remain limited to operator-described designs; no water use or delivered load is inferred.

Electric grid

Planned or represented

384 MW IT future

Bluebonnet supply and onsite substation support eight planned buildings; no operating load is asserted.

Public-source research. Plans may change. See Evidence for sources and qualifications.

Related projects (1)
Prime Dallas DFW01 Data Center Campus

Partially operational · Dallas, Texas, United States

Shared participant: Prime Data Centers · Same market: Texas, United States