PowerHouse Louisville Campus

PRJ-0574 · Site · Louisville, Kentucky, United States

Record last updated Oct 28, 2026

Scope and capacity

PowerHouse and Poe are developing a 154-acre hyperscale campus on Camp Ground Road in Louisville. A revised development plan was approved in March 2026, while PowerHouse continues to market Q4 2026 delivery and a 525 MW maximum utility envelope.

Headline: 402 MW Contracted

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Current status · Approved development plan; site clearing reported; pre delivery

Actual · PowerHouse Louisville Campus (Project)

Claim 53117 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. West Louisville data center approved despite opposition

    Louisville Public Media · Document date: Mar 5, 2026 · Corroborating

    Source reference: SRC-2819 · News report · Recorded authority: Secondary

    Source URL

    https://www.lpm.org/news/2026-03-05/west-louisville-data-center-approved-despite-opposition

  2. PowerHouse Louisville

    PowerHouse Data Centers · Document date: Not stated · Primary

    Source reference: SRC-2816 · Fact sheet · Recorded authority: Party primary

    Source URL

    https://www.powerhousedata.com/data-center/ph-louisville

Announcement date · 2025-01-16

Actual · PowerHouse Louisville Campus (Project)

Claim 53118 · Recorded claim type: Actual · Review: Approved · Claim date: Jan 16, 2025

  1. PowerHouse Data Centers and Poe Companies Partner to Develop Kentucky's First Hyperscale Data Center Campus

    PowerHouse Data Centers · Document date: Jan 16, 2025 · Primary

    Source reference: SRC-2815 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.powerhousedata.com/news/powerhouse-data-centers-and-poe-companies-partner-to-develop-kentuckys-first-hyperscale-data-center-campus

Site area · 154 acres

Actual · PowerHouse Louisville Campus (Project)

Claim 53119 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. PowerHouse Louisville

    PowerHouse Data Centers · Document date: Not stated · Primary

    Source reference: SRC-2816 · Fact sheet · Recorded authority: Party primary

    Source URL

    https://www.powerhousedata.com/data-center/ph-louisville

Developable floor area · 1,800,000 square feet

Design · PowerHouse Louisville Campus (Project)

Claim 53120 · Recorded claim type: Design · Review: Approved with conflict · Claim date: Not stated

  1. PowerHouse Louisville

    PowerHouse Data Centers · Document date: Not stated · Primary

    Source reference: SRC-2816 · Fact sheet · Recorded authority: Party primary

    Source URL

    https://www.powerhousedata.com/data-center/ph-louisville

Building count · Up to 6 buildings

Design · PowerHouse Louisville Campus (Project)

Claim 53121 · Recorded claim type: Design · Review: Approved with conflict · Claim date: Not stated

Conflicting public evidence is preserved.

  1. PowerHouse Louisville

    PowerHouse Data Centers · Document date: Not stated · Primary

    Source reference: SRC-2816 · Fact sheet · Recorded authority: Party primary

    Source URL

    https://www.powerhousedata.com/data-center/ph-louisville

Building count · 7 buildings

Actual · PowerHouse Louisville Campus (Project)

Claim 53122 · Recorded claim type: Actual · Review: Approved with conflict · Claim date: Mar 5, 2026

Conflicting public evidence is preserved.

  1. West Louisville data center approved despite opposition

    Louisville Public Media · Document date: Mar 5, 2026 · Primary

    Source reference: SRC-2819 · News report · Recorded authority: Secondary

    Source URL

    https://www.lpm.org/news/2026-03-05/west-louisville-data-center-approved-despite-opposition

Approved plan floor area · 1,600,000 square feet

Actual · PowerHouse Louisville Campus (Project)

Claim 53123 · Recorded claim type: Actual · Review: Approved with conflict · Claim date: Mar 5, 2026

  1. West Louisville data center approved despite opposition

    Louisville Public Media · Document date: Mar 5, 2026 · Primary

    Source reference: SRC-2819 · News report · Recorded authority: Secondary

    Source URL

    https://www.lpm.org/news/2026-03-05/west-louisville-data-center-approved-despite-opposition

Initial delivery capacity · 130 MW

Forecast · PowerHouse Louisville Campus (Project)

Claim 53124 · Recorded claim type: Forecast · Review: Approved · Claim date: Jan 16, 2025

Headline treatment: Separate claim, not added to the headline

  1. PowerHouse Data Centers and Poe Companies Partner to Develop Kentucky's First Hyperscale Data Center Campus

    PowerHouse Data Centers · Document date: Jan 16, 2025 · Primary

    Source reference: SRC-2815 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.powerhousedata.com/news/powerhouse-data-centers-and-poe-companies-partner-to-develop-kentuckys-first-hyperscale-data-center-campus

  2. Let's Go Build Some Data Centers: PowerHouse Drives Hyperscale and AI Infrastructure Across North America

    PowerHouse Data Centers · Document date: Not stated · Corroborating

    Source reference: SRC-2817 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.powerhousedata.com/news/lets-go-build-some-data-centers-powerhouse-drives-hyperscale-and-ai-infrastructure-across-north-america

Initial delivery target · October/Q4 2026

Forecast · PowerHouse Louisville Campus (Project)

Claim 53125 · Recorded claim type: Forecast · Review: Approved · Claim date: Jan 16, 2025

  1. PowerHouse Data Centers and Poe Companies Partner to Develop Kentucky's First Hyperscale Data Center Campus

    PowerHouse Data Centers · Document date: Jan 16, 2025 · Primary

    Source reference: SRC-2815 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.powerhousedata.com/news/powerhouse-data-centers-and-poe-companies-partner-to-develop-kentuckys-first-hyperscale-data-center-campus

  2. PowerHouse Louisville

    PowerHouse Data Centers · Document date: Not stated · Corroborating

    Source reference: SRC-2816 · Fact sheet · Recorded authority: Party primary

    Source URL

    https://www.powerhousedata.com/data-center/ph-louisville

  3. Let's Go Build Some Data Centers: PowerHouse Drives Hyperscale and AI Infrastructure Across North America

    PowerHouse Data Centers · Document date: Not stated · Corroborating

    Source reference: SRC-2817 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.powerhousedata.com/news/lets-go-build-some-data-centers-powerhouse-drives-hyperscale-and-ai-infrastructure-across-north-america

Campus design power · 400 MW

Planned / design or future potential · PowerHouse Louisville Campus (Project)

Claim 53126 · Recorded claim type: Design · Review: Approved · Claim date: Jan 16, 2025

Headline treatment: Separate claim, not added to the headline

  1. PowerHouse Data Centers and Poe Companies Partner to Develop Kentucky's First Hyperscale Data Center Campus

    PowerHouse Data Centers · Document date: Jan 16, 2025 · Primary

    Source reference: SRC-2815 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.powerhousedata.com/news/powerhouse-data-centers-and-poe-companies-partner-to-develop-kentuckys-first-hyperscale-data-center-campus

Secured power capacity · 335 MW

Actual · PowerHouse Louisville Campus (Project)

Claim 53127 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

Headline treatment: Separate claim, not added to the headline

  1. Let's Go Build Some Data Centers: PowerHouse Drives Hyperscale and AI Infrastructure Across North America

    PowerHouse Data Centers · Document date: Not stated · Primary

    Source reference: SRC-2817 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.powerhousedata.com/news/lets-go-build-some-data-centers-powerhouse-drives-hyperscale-and-ai-infrastructure-across-north-america

Near term power capacity · 402 MW

Actual · PowerHouse Louisville Campus (Project)

Claim 53128 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

Headline treatment: Selected headline

  1. Let's Go Build Some Data Centers: PowerHouse Drives Hyperscale and AI Infrastructure Across North America

    PowerHouse Data Centers · Document date: Not stated · Primary

    Source reference: SRC-2817 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.powerhousedata.com/news/lets-go-build-some-data-centers-powerhouse-drives-hyperscale-and-ai-infrastructure-across-north-america

Maximum utility power · 525 MW

Actual · PowerHouse Louisville Campus (Project)

Claim 53130 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

Headline treatment: Separate claim, not added to the headline

  1. PowerHouse Louisville

    PowerHouse Data Centers · Document date: Not stated · Primary

    Source reference: SRC-2816 · Fact sheet · Recorded authority: Party primary

    Source URL

    https://www.powerhousedata.com/data-center/ph-louisville

Utility switch station target · September 2026

Forecast · PowerHouse Louisville Campus (Project)

Claim 53131 · Recorded claim type: Forecast · Review: Approved · Claim date: Jan 16, 2025

  1. PowerHouse Data Centers and Poe Companies Partner to Develop Kentucky's First Hyperscale Data Center Campus

    PowerHouse Data Centers · Document date: Jan 16, 2025 · Primary

    Source reference: SRC-2815 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.powerhousedata.com/news/powerhouse-data-centers-and-poe-companies-partner-to-develop-kentuckys-first-hyperscale-data-center-campus

On site substation · Planned dedicated substation

Design · PowerHouse Louisville Campus (Project)

Claim 53132 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

  1. West Louisville data center approved despite opposition

    Louisville Public Media · Document date: Mar 5, 2026 · Corroborating

    Source reference: SRC-2819 · News report · Recorded authority: Secondary

    Source URL

    https://www.lpm.org/news/2026-03-05/west-louisville-data-center-approved-despite-opposition

  2. PowerHouse Data Centers and Poe Companies Partner to Develop Kentucky's First Hyperscale Data Center Campus

    PowerHouse Data Centers · Document date: Jan 16, 2025 · Primary

    Source reference: SRC-2815 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.powerhousedata.com/news/powerhouse-data-centers-and-poe-companies-partner-to-develop-kentuckys-first-hyperscale-data-center-campus

Counterparties and capital

American Real Estate Partners · Owner · CMP-1072

Louisville Gas and Electric Company · Utility provider · CMP-1332

Louisville Metro Planning Commission · Government authority · CMP-1333

Poe Companies · Investor · CMP-1331

PowerHouse Data Centers · Developer · CMP-1069