PowerHouse Louisville Campus
- Contracted
- 402 MW
- Updated
- Oct 28, 2026
- Utility
- Louisville Gas and Electric Company
PowerHouse and Poe are developing a 154-acre hyperscale campus on Camp Ground Road in Louisville. A revised development plan was approved in March 2026, while PowerHouse continues to market Q4 2026 delivery and a 525 MW maximum utility envelope.
Capacity
Operating IT capacity: Not established in published records
A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.
Development
1 building
Targeted first building and power tranche; an operating start has not been publicly announced.
Capacity and building-program bases conflict and must not be collapsed.
Milestones (3)
Jan 16, 2025 · Recorded actual event
Completed · Announced
Source not linkedMar 5, 2026 · Recorded actual event
Completed · Permit approved
Source not linkedQ4 2026 · Forecast / planned record
Forecast · Forecast completion
Source not linkedParticipants
Investor
Sources by role
Investor (1)
- West Louisville data center approved despite opposition · Mar 5, 2026 · Corroborating
Investor (1)
Developer
Sources by role
Other participants (2)
Utility provider
Sources by role
Utility provider (1)
Utility provider (1)
Government authority
Sources by role
Government authority (1)
- West Louisville data center approved despite opposition · Mar 5, 2026 · Primary
Site & development
Additional project facts
Infrastructure & permits
Technical details (6)
Planned or represented
130 MW
First tranche targeted for October/Q4 2026; not live capacity.
Secured or contracted
335 MW
Operator says the collaboration secured this initial supply level; contract record remains queued.
Planned or represented
402 MW
Near-term expansion statement and current homepage market figure.
Potential or planned
525 MW
Current project-page maximum; not operating IT load or current draw.
Planned or represented
lg and e switch station; target completion.
Planned or represented
On-site substation shown in development/approval sources; capacity and delivery remain unresolved.
Project map
Other · Issued
PowerHouse Louisville revised development plan
Louisville Metro Planning Commission
Mar 5, 2026
Sources (1)
- West Louisville data center approved despite opposition · Mar 5, 2026 · Primary
Public-source research. Plans may change. See Evidence for sources and qualifications.