Cartis diligence evidence schedule
NTT DATA Zurich 1 Data Center Campus
PRJ-0809 · Site · Rümlang, ZH, Switzerland
Record last updated Oct 28, 2026
Scope and capacity
NTT DATA Zurich 1 Data Center Campus, also known as NTT Zurich 1, is a data center project in Rümlang, ZH, CH associated with NTT DATA. 10,500+ square metres of server space and 20 MW maximum critical IT load. Carrier-neutral Zurich campus with two independent substation feeds and Swiss IX connectivity.
Headline: 20 MW Planned critical IT
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (13)
Location context · NTT Zurich 1 | Rümlang | ZH | CH
Actual · NTT DATA Zurich 1 Data Center Campus (Project)
Claim 61108 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- NTT DATA NTT Zurich 1 profile
NTT DATA · Document date: Aug 27, 2026 · Primary
Source reference: SRC-3377 · Fact sheet · Recorded authority: Official primary
Source URL
https://services.global.ntt/en-us/services-and-products/global-data-centers/global-locations/emea/zurich-1-data-center
https://services.global.ntt/en-us/services-and-products/global-data-centers/global-locations/emea/zurich-1-data-center
Lifecycle status · Partially operational
Actual · NTT DATA Zurich 1 Data Center Campus (Project)
Claim 61109 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- NTT DATA NTT Zurich 1 profile
NTT DATA · Document date: Aug 27, 2026 · Primary
Source reference: SRC-3377 · Fact sheet · Recorded authority: Official primary
Source URL
https://services.global.ntt/en-us/services-and-products/global-data-centers/global-locations/emea/zurich-1-data-center
https://services.global.ntt/en-us/services-and-products/global-data-centers/global-locations/emea/zurich-1-data-center
Reported capacity · 20 MW
Design · NTT DATA Zurich 1 Data Center Campus (Project)
Claim 61110 · Recorded claim type: Design · Review: Approved · Claim date: Not stated
Headline treatment: Selected headline
- NTT DATA NTT Zurich 1 profile
NTT DATA · Document date: Aug 27, 2026 · Primary
Source reference: SRC-3377 · Fact sheet · Recorded authority: Official primary
Source URL
https://services.global.ntt/en-us/services-and-products/global-data-centers/global-locations/emea/zurich-1-data-center
https://services.global.ntt/en-us/services-and-products/global-data-centers/global-locations/emea/zurich-1-data-center
Capacity basis · NTT DATA publishes 20 MW of critical IT capacity for this record boundary.
Actual · NTT DATA Zurich 1 Data Center Campus (Project)
Claim 61111 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- NTT DATA NTT Zurich 1 profile
NTT DATA · Document date: Aug 27, 2026 · Primary
Source reference: SRC-3377 · Fact sheet · Recorded authority: Official primary
Source URL
https://services.global.ntt/en-us/services-and-products/global-data-centers/global-locations/emea/zurich-1-data-center
https://services.global.ntt/en-us/services-and-products/global-data-centers/global-locations/emea/zurich-1-data-center
Location context · NTT Zurich 1 | Rümlang | ZH | CH
Actual · NTT DATA Zurich 1 Data Center Campus (Project)
Claim 101139 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- NTT DATA NTT Zurich 1 profile
NTT DATA · Document date: Aug 27, 2026 · Primary
Source reference: SRC-3377 · Fact sheet · Recorded authority: Official primary
Source URL
https://services.global.ntt/en-us/services-and-products/global-data-centers/global-locations/emea/zurich-1-data-center
https://services.global.ntt/en-us/services-and-products/global-data-centers/global-locations/emea/zurich-1-data-center
Lifecycle status · Partially operational
Actual · NTT DATA Zurich 1 Data Center Campus (Project)
Claim 101140 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- NTT DATA NTT Zurich 1 profile
NTT DATA · Document date: Aug 27, 2026 · Primary
Source reference: SRC-3377 · Fact sheet · Recorded authority: Official primary
Source URL
https://services.global.ntt/en-us/services-and-products/global-data-centers/global-locations/emea/zurich-1-data-center
https://services.global.ntt/en-us/services-and-products/global-data-centers/global-locations/emea/zurich-1-data-center
Reported capacity · 20 MW
Planned / design or future potential · NTT DATA Zurich 1 Data Center Campus (Project)
Claim 101141 · Recorded claim type: Design · Review: Approved · Claim date: Not stated
Headline treatment: Separate claim, not added to the headline
- NTT DATA NTT Zurich 1 profile
NTT DATA · Document date: Aug 27, 2026 · Primary
Source reference: SRC-3377 · Fact sheet · Recorded authority: Official primary
Source URL
https://services.global.ntt/en-us/services-and-products/global-data-centers/global-locations/emea/zurich-1-data-center
https://services.global.ntt/en-us/services-and-products/global-data-centers/global-locations/emea/zurich-1-data-center
Capacity basis · 20 MW facility or campus design capacity.
Actual · NTT DATA Zurich 1 Data Center Campus (Project)
Claim 101142 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- NTT DATA NTT Zurich 1 profile
NTT DATA · Document date: Aug 27, 2026 · Primary
Source reference: SRC-3377 · Fact sheet · Recorded authority: Official primary
Source URL
https://services.global.ntt/en-us/services-and-products/global-data-centers/global-locations/emea/zurich-1-data-center
https://services.global.ntt/en-us/services-and-products/global-data-centers/global-locations/emea/zurich-1-data-center
Project identity · NTT Zurich 1
Actual · NTT DATA Zurich 1 Data Center Campus (Project)
Claim 101144 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- NTT DATA current global data-center locations
NTT DATA · Document date: Aug 30, 2026 · Primary
Source reference: SRC-5643 · Fact sheet · Recorded authority: Official primary
Source URL
https://services.global.ntt/en-us/services-and-products/global-data-centers/global-locations
https://services.global.ntt/en-us/services-and-products/global-data-centers/global-locations
Location context · Rümlang, ZH, CH
Actual · NTT DATA Zurich 1 Data Center Campus (Project)
Claim 101145 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- NTT DATA current global data-center locations
NTT DATA · Document date: Aug 30, 2026 · Primary
Source reference: SRC-5643 · Fact sheet · Recorded authority: Official primary
Source URL
https://services.global.ntt/en-us/services-and-products/global-data-centers/global-locations
https://services.global.ntt/en-us/services-and-products/global-data-centers/global-locations
Lifecycle status · Partially operational
Actual · NTT DATA Zurich 1 Data Center Campus (Project)
Claim 101146 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- NTT DATA current global data-center locations
NTT DATA · Document date: Aug 30, 2026 · Primary
Source reference: SRC-5643 · Fact sheet · Recorded authority: Official primary
Source URL
https://services.global.ntt/en-us/services-and-products/global-data-centers/global-locations
https://services.global.ntt/en-us/services-and-products/global-data-centers/global-locations
Development detail · 10,500+ Square metres of server space and 20 MW maximum critical IT load.
Actual · NTT DATA Zurich 1 Data Center Campus (Project)
Claim 101147 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- NTT DATA current global data-center locations
NTT DATA · Document date: Aug 30, 2026 · Primary
Source reference: SRC-5643 · Fact sheet · Recorded authority: Official primary
Source URL
https://services.global.ntt/en-us/services-and-products/global-data-centers/global-locations
https://services.global.ntt/en-us/services-and-products/global-data-centers/global-locations
Capacity basis · 20 MW facility or campus design capacity.
Actual · NTT DATA Zurich 1 Data Center Campus (Project)
Claim 101148 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- NTT DATA current global data-center locations
NTT DATA · Document date: Aug 30, 2026 · Primary
Source reference: SRC-5643 · Fact sheet · Recorded authority: Official primary
Source URL
https://services.global.ntt/en-us/services-and-products/global-data-centers/global-locations
https://services.global.ntt/en-us/services-and-products/global-data-centers/global-locations
Counterparties and capital
NTT DATA · Developer · CMP-1100