Cartis diligence evidence schedule

NTT DATA Sacramento Data Center Campus

PRJ-0780 · Site · Sacramento, California, United States

Record last updated Oct 28, 2026

Scope and capacity

NTT DATA Sacramento Data Center Campus, also known as NTT Sacramento Campus, is a data center project in Sacramento, CA, US associated with NTT DATA. Three-building Sacramento campus; 52.7 MW published campus critical IT load; CA3 provides 14 MW. Northern California campus with multiple 69 kV feeds, renewable-energy options and carrier-neutral connectivity.

Headline: 52.7 MW Planned critical IT

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Location context · NTT Sacramento Campus | Sacramento | CA | US

Actual · NTT DATA Sacramento Data Center Campus (Project)

Claim 60992 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. NTT DATA Sacramento CA3 Data Center Fact Sheet

    NTT DATA · Document date: Jan 1, 2023 · Primary

    Source reference: SRC-3342 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://services.global.ntt/en-us/campaigns/-/media/54f9d01c89b3473fa24b5e046266791f.ashx

Lifecycle status · Partially operational

Actual · NTT DATA Sacramento Data Center Campus (Project)

Claim 60993 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. NTT DATA Sacramento CA3 Data Center Fact Sheet

    NTT DATA · Document date: Jan 1, 2023 · Primary

    Source reference: SRC-3342 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://services.global.ntt/en-us/campaigns/-/media/54f9d01c89b3473fa24b5e046266791f.ashx

Reported capacity · 52.7 MW

Design · NTT DATA Sacramento Data Center Campus (Project)

Claim 60994 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Selected headline

  1. NTT DATA Sacramento CA3 Data Center Fact Sheet

    NTT DATA · Document date: Jan 1, 2023 · Primary

    Source reference: SRC-3342 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://services.global.ntt/en-us/campaigns/-/media/54f9d01c89b3473fa24b5e046266791f.ashx

Capacity basis · NTT DATA publishes 52.7 MW of critical IT capacity for this record boundary.

Actual · NTT DATA Sacramento Data Center Campus (Project)

Claim 60995 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. NTT DATA Sacramento CA3 Data Center Fact Sheet

    NTT DATA · Document date: Jan 1, 2023 · Primary

    Source reference: SRC-3342 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://services.global.ntt/en-us/campaigns/-/media/54f9d01c89b3473fa24b5e046266791f.ashx

Location context · NTT Sacramento Campus | Sacramento | CA | US

Actual · NTT DATA Sacramento Data Center Campus (Project)

Claim 100866 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. NTT DATA Sacramento CA3 Data Center Fact Sheet

    NTT DATA · Document date: Jan 1, 2023 · Primary

    Source reference: SRC-3342 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://services.global.ntt/en-us/campaigns/-/media/54f9d01c89b3473fa24b5e046266791f.ashx

Lifecycle status · Partially operational

Actual · NTT DATA Sacramento Data Center Campus (Project)

Claim 100867 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. NTT DATA Sacramento CA3 Data Center Fact Sheet

    NTT DATA · Document date: Jan 1, 2023 · Primary

    Source reference: SRC-3342 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://services.global.ntt/en-us/campaigns/-/media/54f9d01c89b3473fa24b5e046266791f.ashx

Reported capacity · 52.7 MW

Planned / design or future potential · NTT DATA Sacramento Data Center Campus (Project)

Claim 100868 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Separate claim, not added to the headline

  1. NTT DATA Sacramento CA3 Data Center Fact Sheet

    NTT DATA · Document date: Jan 1, 2023 · Primary

    Source reference: SRC-3342 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://services.global.ntt/en-us/campaigns/-/media/54f9d01c89b3473fa24b5e046266791f.ashx

Capacity basis · 52.7 MW facility or campus design capacity.

Actual · NTT DATA Sacramento Data Center Campus (Project)

Claim 100869 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. NTT DATA Sacramento CA3 Data Center Fact Sheet

    NTT DATA · Document date: Jan 1, 2023 · Primary

    Source reference: SRC-3342 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://services.global.ntt/en-us/campaigns/-/media/54f9d01c89b3473fa24b5e046266791f.ashx

Project identity · NTT Sacramento Campus

Actual · NTT DATA Sacramento Data Center Campus (Project)

Claim 100871 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. NTT DATA Sacramento CA3 Data Center Fact Sheet

    NTT DATA · Document date: Jan 1, 2023 · Primary

    Source reference: SRC-3342 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://services.global.ntt/en-us/campaigns/-/media/54f9d01c89b3473fa24b5e046266791f.ashx

Location context · Sacramento, CA, US

Actual · NTT DATA Sacramento Data Center Campus (Project)

Claim 100872 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. NTT DATA Sacramento CA3 Data Center Fact Sheet

    NTT DATA · Document date: Jan 1, 2023 · Primary

    Source reference: SRC-3342 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://services.global.ntt/en-us/campaigns/-/media/54f9d01c89b3473fa24b5e046266791f.ashx

Lifecycle status · Partially operational

Actual · NTT DATA Sacramento Data Center Campus (Project)

Claim 100873 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. NTT DATA Sacramento CA3 Data Center Fact Sheet

    NTT DATA · Document date: Jan 1, 2023 · Primary

    Source reference: SRC-3342 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://services.global.ntt/en-us/campaigns/-/media/54f9d01c89b3473fa24b5e046266791f.ashx

Development detail · Three building Sacramento campus; 52.7 MW published campus critical IT load; CA3 provides 14 MW.

Actual · NTT DATA Sacramento Data Center Campus (Project)

Claim 100874 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. NTT DATA Sacramento CA3 Data Center Fact Sheet

    NTT DATA · Document date: Jan 1, 2023 · Primary

    Source reference: SRC-3342 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://services.global.ntt/en-us/campaigns/-/media/54f9d01c89b3473fa24b5e046266791f.ashx

Capacity basis · 52.7 MW facility or campus design capacity.

Actual · NTT DATA Sacramento Data Center Campus (Project)

Claim 100875 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. NTT DATA Sacramento CA3 Data Center Fact Sheet

    NTT DATA · Document date: Jan 1, 2023 · Primary

    Source reference: SRC-3342 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://services.global.ntt/en-us/campaigns/-/media/54f9d01c89b3473fa24b5e046266791f.ashx

Counterparties and capital

NTT DATA · Developer · CMP-1100

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.