Cartis diligence evidence schedule

NTT DATA Johannesburg 1 Data Center Campus

PRJ-0814 · Site · Centurion, Gauteng, South Africa

Record last updated Oct 28, 2026

Scope and capacity

NTT DATA Johannesburg 1 Data Center Campus, also known as NTT Johannesburg 1, is a data center project in Centurion, Gauteng, ZA associated with NTT DATA. 6,200 square metres of server space and 12 MW critical IT load. Carrier-neutral Gauteng campus with onsite 20 MVA substation and N+1 free-cooling chiller systems.

Headline: 12 MW Planned critical IT

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Location context · NTT Johannesburg 1 | Centurion | Gauteng | ZA

Actual · NTT DATA Johannesburg 1 Data Center Campus (Project)

Claim 61128 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. NTT DATA NTT Johannesburg 1 profile

    NTT DATA · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-3383 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://services.global.ntt/en-us/services-and-products/global-data-centers/global-locations/emea/johannesburg-1-data-center

Lifecycle status · Partially operational

Actual · NTT DATA Johannesburg 1 Data Center Campus (Project)

Claim 61129 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. NTT DATA NTT Johannesburg 1 profile

    NTT DATA · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-3383 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://services.global.ntt/en-us/services-and-products/global-data-centers/global-locations/emea/johannesburg-1-data-center

Reported capacity · 12 MW

Design · NTT DATA Johannesburg 1 Data Center Campus (Project)

Claim 61130 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Selected headline

  1. NTT DATA NTT Johannesburg 1 profile

    NTT DATA · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-3383 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://services.global.ntt/en-us/services-and-products/global-data-centers/global-locations/emea/johannesburg-1-data-center

Capacity basis · NTT DATA publishes 12 MW of critical IT capacity for this record boundary.

Actual · NTT DATA Johannesburg 1 Data Center Campus (Project)

Claim 61131 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. NTT DATA NTT Johannesburg 1 profile

    NTT DATA · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-3383 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://services.global.ntt/en-us/services-and-products/global-data-centers/global-locations/emea/johannesburg-1-data-center

Location context · NTT Johannesburg 1 | Centurion | Gauteng | ZA

Actual · NTT DATA Johannesburg 1 Data Center Campus (Project)

Claim 101189 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. NTT DATA NTT Johannesburg 1 profile

    NTT DATA · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-3383 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://services.global.ntt/en-us/services-and-products/global-data-centers/global-locations/emea/johannesburg-1-data-center

Lifecycle status · Partially operational

Actual · NTT DATA Johannesburg 1 Data Center Campus (Project)

Claim 101190 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. NTT DATA NTT Johannesburg 1 profile

    NTT DATA · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-3383 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://services.global.ntt/en-us/services-and-products/global-data-centers/global-locations/emea/johannesburg-1-data-center

Reported capacity · 12 MW

Planned / design or future potential · NTT DATA Johannesburg 1 Data Center Campus (Project)

Claim 101191 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Separate claim, not added to the headline

  1. NTT DATA NTT Johannesburg 1 profile

    NTT DATA · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-3383 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://services.global.ntt/en-us/services-and-products/global-data-centers/global-locations/emea/johannesburg-1-data-center

Capacity basis · 12 MW facility or campus design capacity.

Actual · NTT DATA Johannesburg 1 Data Center Campus (Project)

Claim 101192 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. NTT DATA NTT Johannesburg 1 profile

    NTT DATA · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-3383 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://services.global.ntt/en-us/services-and-products/global-data-centers/global-locations/emea/johannesburg-1-data-center

Project identity · NTT Johannesburg 1

Actual · NTT DATA Johannesburg 1 Data Center Campus (Project)

Claim 101194 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. NTT DATA current global data-center locations

    NTT DATA · Document date: Aug 30, 2026 · Primary

    Source reference: SRC-5655 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://services.global.ntt/en-us/services-and-products/global-data-centers/global-locations

Location context · Centurion, Gauteng, ZA

Actual · NTT DATA Johannesburg 1 Data Center Campus (Project)

Claim 101195 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. NTT DATA current global data-center locations

    NTT DATA · Document date: Aug 30, 2026 · Primary

    Source reference: SRC-5655 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://services.global.ntt/en-us/services-and-products/global-data-centers/global-locations

Lifecycle status · Partially operational

Actual · NTT DATA Johannesburg 1 Data Center Campus (Project)

Claim 101196 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. NTT DATA current global data-center locations

    NTT DATA · Document date: Aug 30, 2026 · Primary

    Source reference: SRC-5655 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://services.global.ntt/en-us/services-and-products/global-data-centers/global-locations

Development detail · 6,200 Square metres of server space and 12 MW critical IT load.

Actual · NTT DATA Johannesburg 1 Data Center Campus (Project)

Claim 101197 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. NTT DATA current global data-center locations

    NTT DATA · Document date: Aug 30, 2026 · Primary

    Source reference: SRC-5655 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://services.global.ntt/en-us/services-and-products/global-data-centers/global-locations

Capacity basis · 12 MW facility or campus design capacity.

Actual · NTT DATA Johannesburg 1 Data Center Campus (Project)

Claim 101198 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. NTT DATA current global data-center locations

    NTT DATA · Document date: Aug 30, 2026 · Primary

    Source reference: SRC-5655 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://services.global.ntt/en-us/services-and-products/global-data-centers/global-locations

Counterparties and capital

NTT DATA · Developer · CMP-1100

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.