Skip to content

NTT DATA Frankfurt 4 Data Center Campus

Hattersheim am Main, Hesse, GermanyPartially operational
Evidence
Planned critical IT
70.4 MW
Updated
Oct 28, 2026

NTT DATA Frankfurt 4 Data Center Campus, also known as NTT Frankfurt 4, is a data center project in Hattersheim am Main, HE, DE associated with NTT DATA. 34.4 MW current maximum critical IT load; 70.4 MW once fully built out; 28,400+ square metres at full build. Frankfurt-region campus with onsite 90 MVA substation, carrier-neutral DE-CIX connectivity and efficient cooling. 34.4 MW is NTT DATA’s current critical IT design; 70.4 MW is the separate full-build envelope.

Capacity

Reported capacity

Design

70.4 MW

Source

Reported capacity

Planned / design or future potential

34.4 MW

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Operating facility and documented expansionPartially operational

34.4 MW is NTT DATA’s current critical IT design; 70.4 MW is the separate full-build envelope.

Participants

NTT DATA

Developer

Sources by role
Developer (1)

Site & development

Location context

Actual

NTT Frankfurt 4 | Hattersheim am Main | HE | DE

Source

Location context

Actual

NTT Frankfurt 4 | Hattersheim am Main | HE | DE

Source

Onsite substation

Design

90 MVA

Source

Additional project facts

Lifecycle status

Actual

Partially operational

Source

Capacity basis

Actual

NTT DATA publishes 70.4 MW of critical IT capacity for this record boundary.

Source

Lifecycle status

Actual

Partially operational

Source

Capacity basis

Actual

34.4 MW is NTT DATA’s current critical IT design; 70.4 MW is the separate full build envelope.

Source

Current server space

Design

14,200 square metres

Source

Infrastructure & permits

Technical details (3)
Electric grid

Energized

Frankfurt-region campus with onsite 90 MVA substation, carrier-neutral DE-CIX connectivity and efficient cooling.

Cooling system

Operational

Cooling and efficiency claims remain limited to operator-described designs; no water use or delivered load is inferred.

Electric grid

Energized

90 MVA gross

Gross substation rating supports 34.4 MW current and 70.4 MW full-build critical IT.

Public-source research. Plans may change. See Evidence for sources and qualifications.

Related projects (2)
NTT DATA Frankfurt 1 Data Center Campus

Partially operational · Frankfurt, Hesse, Germany

Shared participant: NTT DATA · Same market: Hesse, Germany

Compare in a collection
NTT DATA Frankfurt 3 Data Center Campus

Partially operational · Rüsselsheim am Main, Hesse, Germany

Shared participant: NTT DATA · Same market: Hesse, Germany