Scope and capacity

NSA’s Fort Meade computing-center program includes the High Performance Computing Center 2 and supporting utility, generator and cooling infrastructure on the installation’s east campus. NSA broke ground on HPCC-2 in 2013 with completion scheduled for 2016, and the Army Corps of Engineers continues environmental review for related campus infrastructure. Published generator figures describe backup power, not operating IT capacity.

Headline: Not established in published records

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Project program · High Performance Computing Center 2

Actual · NSA Fort Meade High Performance Computing Center (Project)

Claim 155042 · Recorded claim type: Actual · Review: Approved · Claim date: May 3, 2013

  1. Central Campus Development

    U.S. Army Corps of Engineers, Baltimore District · Document date: Aug 31, 2026 · Corroborating

    Source reference: SRC-7459 · Government record · Recorded authority: Official primary

    Source URL

    https://www.nab.usace.army.mil/Central-Campus-Development-CCD/

  2. Fort Meade campus environmental assessment

    U.S. Army Corps of Engineers · Document date: Sep 1, 2024 · Corroborating

    Source reference: SRC-7460 · Government record · Recorded authority: Official primary

    Source URL

    https://www.nab.usace.army.mil/Portals/63/CNMF%20EA_Draft%20EA_Sep24.pdf

  3. Groundbreaking ceremony held for computing center

    National Security Agency · Document date: May 3, 2013 · Primary

    Source reference: SRC-7458 · Government record · Recorded authority: Official primary

    Source URL

    https://www.nsa.gov/Press-Room/Press-Releases-Statements/Press-Release-View/Article/1631098/groundbreaking-ceremony-held-for-computing-center/

Counterparties and capital

National Security Agency · Operator · CMP-1662

U.S. Army Corps of Engineers · Government authority · CMP-0909