Scope and capacity

Novva’s West Jordan campus is a 100-acre, multi-building data-center development launched with a 300,000-square-foot first phase and corporate headquarters. The operator plans up to 1.5 million square feet across four phases, supported by a dedicated transmission connection and an onsite substation designed for future capacity up to 200 MW. A $2 billion expansion is adding two buildings and new backup-generation infrastructure while the original campus remains in operation.

Headline: Not established in published records

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Site area · 100 acre

Actual · Novva West Jordan Data Center Campus (Project)

Claim 154753 · Recorded claim type: Actual · Review: Approved · Claim date: Aug 31, 2026

  1. Novva Utah data-center campus

    Novva Data Centers · Document date: Aug 31, 2026 · Primary

    Source reference: SRC-7454 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.novva.com/data-center-facilities/utah/

  2. West Jordan’s $2B data boost

    City of West Jordan · Document date: Mar 1, 2025 · Corroborating

    Source reference: SRC-7456 · Government record · Recorded authority: Official primary

    Source URL

    https://www.westjordan.utah.gov/newsroom/2025/03/west-jordans-2b-data-boost-how-novvas-expansion-benefits-you/

  3. Novva expansion notice

    Utah Division of Air Quality · Document date: Jan 1, 2025 · Corroborating

    Source reference: SRC-7457 · Regulatory record · Recorded authority: Official primary

    Source URL

    https://daqpermitting.utah.gov/DocViewer?IntDocID=150302&contentType=application%2Fpdf

  4. Novva launches Utah data center

    Novva Data Centers · Document date: Jun 1, 2021 · Corroborating

    Source reference: SRC-7455 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.novva.com/media-center/utah-data-center/

Planned building area · 1,500,000 sq. ft.

Forecast · Novva West Jordan Data Center Campus (Project)

Claim 154754 · Recorded claim type: Forecast · Review: Approved · Claim date: Aug 31, 2026

  1. Novva Utah data-center campus

    Novva Data Centers · Document date: Aug 31, 2026 · Primary

    Source reference: SRC-7454 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.novva.com/data-center-facilities/utah/

  2. West Jordan’s $2B data boost

    City of West Jordan · Document date: Mar 1, 2025 · Corroborating

    Source reference: SRC-7456 · Government record · Recorded authority: Official primary

    Source URL

    https://www.westjordan.utah.gov/newsroom/2025/03/west-jordans-2b-data-boost-how-novvas-expansion-benefits-you/

  3. Novva expansion notice

    Utah Division of Air Quality · Document date: Jan 1, 2025 · Corroborating

    Source reference: SRC-7457 · Regulatory record · Recorded authority: Official primary

    Source URL

    https://daqpermitting.utah.gov/DocViewer?IntDocID=150302&contentType=application%2Fpdf

  4. Novva launches Utah data center

    Novva Data Centers · Document date: Jun 1, 2021 · Corroborating

    Source reference: SRC-7455 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.novva.com/media-center/utah-data-center/

Phase count · 4 phases

Actual · Novva West Jordan Data Center Campus (Project)

Claim 154755 · Recorded claim type: Actual · Review: Approved · Claim date: Aug 31, 2026

  1. Novva Utah data-center campus

    Novva Data Centers · Document date: Aug 31, 2026 · Primary

    Source reference: SRC-7454 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.novva.com/data-center-facilities/utah/

  2. West Jordan’s $2B data boost

    City of West Jordan · Document date: Mar 1, 2025 · Corroborating

    Source reference: SRC-7456 · Government record · Recorded authority: Official primary

    Source URL

    https://www.westjordan.utah.gov/newsroom/2025/03/west-jordans-2b-data-boost-how-novvas-expansion-benefits-you/

  3. Novva expansion notice

    Utah Division of Air Quality · Document date: Jan 1, 2025 · Corroborating

    Source reference: SRC-7457 · Regulatory record · Recorded authority: Official primary

    Source URL

    https://daqpermitting.utah.gov/DocViewer?IntDocID=150302&contentType=application%2Fpdf

  4. Novva launches Utah data center

    Novva Data Centers · Document date: Jun 1, 2021 · Corroborating

    Source reference: SRC-7455 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.novva.com/media-center/utah-data-center/

Counterparties and capital

City of West Jordan · Government authority · CMP-1650

Novva Data Centers · Operator · CMP-1663

Investment commitment

$2,000,000,000 · Mar 1, 2025

Expansion investment announced by West Jordan; Source amount stated in millions.

Counterparties not specified.

Sources (4)

Financing record 349; claim-specific source links appear in the exhibit sources where published.