Cartis diligence evidence schedule
Northeast Creek Technology Campus
PRJ-1086 · Site · Louisa, Virginia, United States
Record last updated Oct 28, 2026
Scope and capacity
Northeast Creek Technology Campus is an Amazon Web Services data-center development in Louisa County, Virginia, also described publicly as the Lake Anna Technology Campus. County and federal permit records support a multi-phase campus whose site construction began in 2025, but they do not establish the tracked 2.7 GW figure as operating or contracted IT capacity. The headline is withheld while the existing identity is preserved. Wetlands impacts, building phases, Dominion transmission, water, air permits and final energization remain active development matters.
Headline: Not established in published records
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (8)
Location context · Northeast Creek Technology Campus | Louisa | Virginia | US
Actual · Northeast Creek Technology Campus (Project)
Claim 70316 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Northeast Creek Technology Campus public-record research record
US Data Center Map · Document date: Aug 28, 2026 · Primary
Source reference: SRC-4009 · News report · Recorded authority: Secondary
Source URL
https://dcmap.us/states/virginia/
https://dcmap.us/states/virginia/
Lifecycle status · Preconstruction
Actual · Northeast Creek Technology Campus (Project)
Claim 70317 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Northeast Creek Technology Campus public-record research record
US Data Center Map · Document date: Aug 28, 2026 · Primary
Source reference: SRC-4009 · News report · Recorded authority: Secondary
Source URL
https://dcmap.us/states/virginia/
https://dcmap.us/states/virginia/
Capacity basis · 2,700 MW future full build site capacity; not measured operating IT load.
Actual · Northeast Creek Technology Campus (Project)
Claim 70319 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Northeast Creek Technology Campus public-record research record
US Data Center Map · Document date: Aug 28, 2026 · Primary
Source reference: SRC-4009 · News report · Recorded authority: Secondary
Source URL
https://dcmap.us/states/virginia/
https://dcmap.us/states/virginia/
Location context · Northeast Creek Technology Campus | Louisa | Virginia | US
Actual · Northeast Creek Technology Campus (Project)
Claim 74500 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Northeast Creek Technology Campus public-record research record
US Data Center Map · Document date: Aug 28, 2026 · Primary
Source reference: SRC-4009 · News report · Recorded authority: Secondary
Source URL
https://dcmap.us/states/virginia/
https://dcmap.us/states/virginia/
Lifecycle status · Preconstruction
Actual · Northeast Creek Technology Campus (Project)
Claim 74501 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Northeast Creek Technology Campus public-record research record
US Data Center Map · Document date: Aug 28, 2026 · Primary
Source reference: SRC-4009 · News report · Recorded authority: Secondary
Source URL
https://dcmap.us/states/virginia/
https://dcmap.us/states/virginia/
Operator confirmed · Amazon Web Services
Actual · Northeast Creek Technology Campus (Project)
Claim 74504 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Lake Anna Technology Campus construction updates
Amazon Web Services · Document date: Aug 28, 2026 · Primary
Source reference: SRC-4236 · Company announcement · Recorded authority: Party primary
Source URL
https://www.lakeannatechcampus.com/
https://www.lakeannatechcampus.com/
Construction start · 2025
Actual · Northeast Creek Technology Campus (Project)
Claim 74505 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Lake Anna Technology Campus construction updates
Amazon Web Services · Document date: Aug 28, 2026 · Primary
Source reference: SRC-4236 · Company announcement · Recorded authority: Party primary
Source URL
https://www.lakeannatechcampus.com/
https://www.lakeannatechcampus.com/
Capacity status · 2.7 GW is not established by permits
Actual · Northeast Creek Technology Campus (Project)
Claim 74506 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Northeast Creek permit record
Commonwealth of Virginia · Document date: Aug 28, 2026 · Primary
Source reference: SRC-4234 · Government record · Recorded authority: Official primary
Source URL
https://permits.virginia.gov/Permit/Details/109962
https://permits.virginia.gov/Permit/Details/109962
Counterparties and capital
Amazon Web Services · Developer · CMP-0152
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.