Cartis diligence evidence schedule

New Hill Digital Campus

PRJ-0568 · Site · southwest Wake County near Apex and New Hill, North Carolina, United States

Record last updated Oct 28, 2026

Scope and capacity

Natelli Holdings proposed a four-building, approximately 190-acre campus near New Hill with a 300 MW design, but withdrew the annexation and rezoning applications in March 2026.

Headline: 300 MW Planned / design

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Proposal status · Withdrawn

Actual · New Hill Digital Campus (Project)

Claim 50776 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Proposed data center in Wake County withdrawn

    WUNC · Document date: Mar 5, 2026 · Primary

    Source reference: SRC-2735 · News report · Recorded authority: Secondary

    Source URL

    https://www.wunc.org/environment/2026-03-05/proposed-data-center-new-hill-digital-campus-wake-county-apex

  2. Natelli withdraws Apex data center project near Shearon Harris

    WRAL · Document date: Not stated · Corroborating

    Source reference: SRC-2736 · News report · Recorded authority: Secondary

    Source URL

    https://www.wral.com/news/local/natelli-withdraws-apex-data-center-project-shearon-harris-march-2026/

Site area · 190 acres

Reported rounded · New Hill Digital Campus (Project)

Claim 50777 · Recorded claim type: Reported rounded · Review: Approved · Claim date: Not stated

  1. Frequently Asked Questions

    New Hill Digital Campus / Natelli Holdings · Document date: Not stated · Primary

    Source reference: SRC-2734 · Fact sheet · Recorded authority: Party primary

    Source URL

    https://newhilldigitalcampus.com/faqs/

Building count · 4 buildings

Proposal · New Hill Digital Campus (Project)

Claim 50778 · Recorded claim type: Proposal · Review: Approved with conflict · Claim date: Not stated

  1. New Hill Digital Campus

    New Hill Digital Campus / Natelli Holdings · Document date: Not stated · Primary

    Source reference: SRC-2733 · Fact sheet · Recorded authority: Party primary

    Source URL

    https://newhilldigitalcampus.com/

  2. Frequently Asked Questions

    New Hill Digital Campus / Natelli Holdings · Document date: Not stated · Corroborating

    Source reference: SRC-2734 · Fact sheet · Recorded authority: Party primary

    Source URL

    https://newhilldigitalcampus.com/faqs/

Building area each · 200,000 square feet

Proposal · New Hill Digital Campus (Project)

Claim 50780 · Recorded claim type: Proposal · Review: Approved · Claim date: Not stated

  1. New Hill Digital Campus

    New Hill Digital Campus / Natelli Holdings · Document date: Not stated · Primary

    Source reference: SRC-2733 · Fact sheet · Recorded authority: Party primary

    Source URL

    https://newhilldigitalcampus.com/

  2. Frequently Asked Questions

    New Hill Digital Campus / Natelli Holdings · Document date: Not stated · Corroborating

    Source reference: SRC-2734 · Fact sheet · Recorded authority: Party primary

    Source URL

    https://newhilldigitalcampus.com/faqs/

Design power · 300 MW

Planned / design or future potential · New Hill Digital Campus (Project)

Claim 50781 · Recorded claim type: Proposal · Review: Approved · Claim date: Not stated

Headline treatment: Selected headline

  1. New Hill Digital Campus

    New Hill Digital Campus / Natelli Holdings · Document date: Not stated · Primary

    Source reference: SRC-2733 · Fact sheet · Recorded authority: Party primary

    Source URL

    https://newhilldigitalcampus.com/

  2. Frequently Asked Questions

    New Hill Digital Campus / Natelli Holdings · Document date: Not stated · Corroborating

    Source reference: SRC-2734 · Fact sheet · Recorded authority: Party primary

    Source URL

    https://newhilldigitalcampus.com/faqs/

Site location · Between US-1 and Old US-1, west of Shearon Harris Road

Actual · New Hill Digital Campus (Project)

Claim 50783 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. New Hill Digital Campus

    New Hill Digital Campus / Natelli Holdings · Document date: Not stated · Primary

    Source reference: SRC-2733 · Fact sheet · Recorded authority: Party primary

    Source URL

    https://newhilldigitalcampus.com/

  2. Frequently Asked Questions

    New Hill Digital Campus / Natelli Holdings · Document date: Not stated · Corroborating

    Source reference: SRC-2734 · Fact sheet · Recorded authority: Party primary

    Source URL

    https://newhilldigitalcampus.com/faqs/

Adjacent generation asset · Shearon Harris Nuclear Plant

Actual · New Hill Digital Campus (Project)

Claim 50784 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. New Hill Digital Campus

    New Hill Digital Campus / Natelli Holdings · Document date: Not stated · Primary

    Source reference: SRC-2733 · Fact sheet · Recorded authority: Party primary

    Source URL

    https://newhilldigitalcampus.com/

  2. Frequently Asked Questions

    New Hill Digital Campus / Natelli Holdings · Document date: Not stated · Corroborating

    Source reference: SRC-2734 · Fact sheet · Recorded authority: Party primary

    Source URL

    https://newhilldigitalcampus.com/faqs/

Peak reclaimed water demand · 1 million gallons per day

Reported rounded · New Hill Digital Campus (Project)

Claim 50786 · Recorded claim type: Reported rounded · Review: Approved · Claim date: Not stated

  1. New Hill Digital Campus

    New Hill Digital Campus / Natelli Holdings · Document date: Not stated · Primary

    Source reference: SRC-2733 · Fact sheet · Recorded authority: Party primary

    Source URL

    https://newhilldigitalcampus.com/

  2. Frequently Asked Questions

    New Hill Digital Campus / Natelli Holdings · Document date: Not stated · Corroborating

    Source reference: SRC-2734 · Fact sheet · Recorded authority: Party primary

    Source URL

    https://newhilldigitalcampus.com/faqs/

Tenant status · No customer selected

Actual · New Hill Digital Campus (Project)

Claim 50788 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Frequently Asked Questions

    New Hill Digital Campus / Natelli Holdings · Document date: Not stated · Primary

    Source reference: SRC-2734 · Fact sheet · Recorded authority: Party primary

    Source URL

    https://newhilldigitalcampus.com/faqs/

Applications withdrawn date · 2026-03-05

Actual · New Hill Digital Campus (Project)

Claim 50790 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Proposed data center in Wake County withdrawn

    WUNC · Document date: Mar 5, 2026 · Primary

    Source reference: SRC-2735 · News report · Recorded authority: Secondary

    Source URL

    https://www.wunc.org/environment/2026-03-05/proposed-data-center-new-hill-digital-campus-wake-county-apex

Townwide moratorium · Year long data center moratorium

Actual · New Hill Digital Campus (Project)

Claim 50792 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Environmental Advisory Board — Data Center Subcommittee

    Town of Apex · Document date: Not stated · Primary

    Source reference: SRC-2737 · Government record · Recorded authority: Official primary

    Source URL

    https://www.apexnc.org/1348/Environmental-Advisory-Board-EAB

Counterparties and capital

Duke Energy · Utility provider · CMP-1320

Natelli Holdings · Developer · CMP-1318

Town of Apex · Government authority · CMP-1319

Western Wake Regional Water Reclamation Facility · Utility provider · CMP-1321

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.