New Hill Digital Campus

southwest Wake County near Apex and New Hill, North Carolina, United StatesCancelled
Capacity
300 MW
Planned / design
Lead participant
Natelli Holdings
Developer
Last updated
Aug 26, 2026
Most recent public record update

About New Hill Digital Campus

Natelli Holdings proposed a four-building, approximately 190-acre campus near New Hill with a 300 MW design, but withdrew the annexation and rezoning applications in March 2026.

Capacity

Planned / design
Operating capacityAn operating IT-capacity figure has not been publicly disclosed.
Design300 MWProposal · New Hill Digital Campus

Development

1 phases · 2 milestones
Annexation and rezoning filingChanged Or Cancelled

Four-building developer concept. No construction phase exists.

4 buildings

Sep 2, 2025
Developer files Apex land-use applications
Completed
Mar 5, 2026
Annexation and rezoning requests withdrawn
Completed

Infrastructure

Utility ServiceCancelled Or Not Proceeding

300 MW

Developer says it applied for 300 MW; no executed interconnection or service agreement verified.

Electric GridPotential Or Planned

Developer-funded substation anticipated to connect to Duke transmission rather than Apex distribution.

Water SupplyPlanned Or Represented

1 million gallons per day

Developer says near-zero on cold days and up to 1 MGD on peak summer days, with about two-thirds returned; no current use.

Project map

0 of 1 project point mapped
Infrastructure facts
3
Mapped records
1
Capacity figures
2

No map point available

Power & interconnection: 2Cooling & water: 1

Facts & sources

Published claims and their source links.

11 facts
Proposal Status
Withdrawn
Actual
Site Area
190 acres
Reported Rounded
Building Count
4
Proposal
Building Area Each
200,000 square feet
Proposal
Design Power
300 MW
Proposal
Site Location
Between US-1 and Old US-1, west of Shearon Harris Road
Actual
Adjacent Generation Asset
Shearon Harris Nuclear Plant
Actual
Peak Reclaimed Water Demand
1 million gallons per day
Reported Rounded
Tenant Status
No customer selected
Actual
Applications Withdrawn Date
2026-03-05
Actual
Townwide Moratorium
Year long data center moratorium
Actual