Scope and capacity
Nabiax Alcalá ADC1 is the first built and operating facility at the Alcalá campus. A current building-specific IT-capacity figure has not been publicly disclosed.
Headline: Not established in published records
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (5)
Operational since · 2,013
Source report · Nabiax Alcalá ADC1 (Project)
Claim 44909 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated
- Asterion agrees sale of Nabiax to Aermont
Asterion Industrial Partners · Document date: Nov 11, 2024 · Primary
Source reference: SRC-6939 · Company announcement · Recorded authority: Party primary
Source URL
https://www.asterionindustrial.com/asterion-industrial-partners-agrees-sale-of-data-center-group-nabiax-to-aermont/
https://www.asterionindustrial.com/asterion-industrial-partners-agrees-sale-of-data-center-group-nabiax-to-aermont/
- Alcalá Data Center
Nabiax · Document date: Not stated · Primary
Source reference: SRC-2477 · Recorded authority: Party primary
Source URL
https://nabiax.com/en/our-data-centers/spain/alcala-data-center/
https://nabiax.com/en/our-data-centers/spain/alcala-data-center/
Technical space · 4,800 square meters
Source report · Nabiax Alcalá ADC1 (Project)
Claim 44910 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated
- Alcalá Data Center
Nabiax · Document date: Not stated · Primary
Source reference: SRC-2477 · Recorded authority: Party primary
Source URL
https://nabiax.com/en/our-data-centers/spain/alcala-data-center/
https://nabiax.com/en/our-data-centers/spain/alcala-data-center/
IT room count · 7 IT rooms
Source report · Nabiax Alcalá ADC1 (Project)
Claim 44911 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated
- Alcalá Data Center
Nabiax · Document date: Not stated · Primary
Source reference: SRC-2477 · Recorded authority: Party primary
Source URL
https://nabiax.com/en/our-data-centers/spain/alcala-data-center/
https://nabiax.com/en/our-data-centers/spain/alcala-data-center/
Electrical redundancy · 2N
Actual · Nabiax Alcalá ADC1 (Project)
Claim 44912 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Alcalá Data Center
Nabiax · Document date: Not stated · Primary
Source reference: SRC-2477 · Recorded authority: Party primary
Source URL
https://nabiax.com/en/our-data-centers/spain/alcala-data-center/
https://nabiax.com/en/our-data-centers/spain/alcala-data-center/
Tier certification · Uptime Institute Tier IV
Actual · Nabiax Alcalá ADC1 (Project)
Claim 44913 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Alcalá Data Center
Nabiax · Document date: Not stated · Primary
Source reference: SRC-2477 · Recorded authority: Party primary
Source URL
https://nabiax.com/en/our-data-centers/spain/alcala-data-center/
https://nabiax.com/en/our-data-centers/spain/alcala-data-center/
Counterparties and capital
Nabiax · Operator · CMP-1144