Cartis diligence evidence schedule

MSB Global Matrix Data Center Campus

PRJ-1081 · Site · Sulphur Springs, Texas, United States

Record last updated Oct 28, 2026

Scope and capacity

MSB Global Services’ Matrix campus in Sulphur Springs, Texas is planned as a 3 GW, 30-building development on roughly 1,677 acres. The company announced a June 2025 groundbreaking and described an initial eight-building, 800 MW phase, but its published delivery dates conflict across materials. The 3 GW value is therefore a full-build design target, not operating capacity, and the phase schedule needs reconciliation. Local legal, utility, permitting, customer and financing details remain open.

Headline: 3,000 MW Planned / design

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Location context · MSB Global Matrix Data Center Campus | Sulphur Springs | Texas | US

Actual · MSB Global Matrix Data Center Campus (Project)

Claim 70296 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. MSB Global Matrix Data Center Campus public-record research record

    PoweredByWho · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4003 · News report · Recorded authority: Secondary

    Source URL

    https://poweredbywho.com/rankings/largest-data-centers-under-construction

Lifecycle status · Preconstruction

Actual · MSB Global Matrix Data Center Campus (Project)

Claim 70297 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. MSB Global Matrix Data Center Campus public-record research record

    PoweredByWho · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4003 · News report · Recorded authority: Secondary

    Source URL

    https://poweredbywho.com/rankings/largest-data-centers-under-construction

Reported capacity · 3,000 MW

Planned / design or future potential · MSB Global Matrix Data Center Campus (Project)

Claim 70298 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Selected headline

  1. MSB Global Matrix Data Center Campus public-record research record

    PoweredByWho · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4003 · News report · Recorded authority: Secondary

    Source URL

    https://poweredbywho.com/rankings/largest-data-centers-under-construction

Capacity basis · 3,000 MW future full build site capacity; not measured operating IT load.

Actual · MSB Global Matrix Data Center Campus (Project)

Claim 70299 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. MSB Global Matrix Data Center Campus public-record research record

    PoweredByWho · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4003 · News report · Recorded authority: Secondary

    Source URL

    https://poweredbywho.com/rankings/largest-data-centers-under-construction

Location context · MSB Global Matrix Data Center Campus | Sulphur Springs | Texas | US

Actual · MSB Global Matrix Data Center Campus (Project)

Claim 74463 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. MSB Global Matrix Data Center Campus public-record research record

    PoweredByWho · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4003 · News report · Recorded authority: Secondary

    Source URL

    https://poweredbywho.com/rankings/largest-data-centers-under-construction

Lifecycle status · Preconstruction

Actual · MSB Global Matrix Data Center Campus (Project)

Claim 74464 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. MSB Global Matrix Data Center Campus public-record research record

    PoweredByWho · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4003 · News report · Recorded authority: Secondary

    Source URL

    https://poweredbywho.com/rankings/largest-data-centers-under-construction

Reported capacity · 3,000 MW

Planned / design or future potential · MSB Global Matrix Data Center Campus (Project)

Claim 74465 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Separate claim, not added to the headline

  1. MSB Global Matrix Data Center Campus public-record research record

    PoweredByWho · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4003 · News report · Recorded authority: Secondary

    Source URL

    https://poweredbywho.com/rankings/largest-data-centers-under-construction

Capacity basis · 3,000 MW is the 30-building full build design; Phase 1 is described as 800 MW and delivery dates conflict.

Actual · MSB Global Matrix Data Center Campus (Project)

Claim 74466 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. MSB Global Matrix Data Center Campus public-record research record

    PoweredByWho · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4003 · News report · Recorded authority: Secondary

    Source URL

    https://poweredbywho.com/rankings/largest-data-centers-under-construction

Site area · 1,677 acres

Actual · MSB Global Matrix Data Center Campus (Project)

Claim 74467 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Matrix Sulphur Springs campus

    MSB Global Services · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4223 · Company announcement · Recorded authority: Party primary

    Source URL

    https://msbglobalservices.com/sulphur-springs/

Building count · 30 buildings

Actual · MSB Global Matrix Data Center Campus (Project)

Claim 74468 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Matrix Sulphur Springs campus

    MSB Global Services · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4223 · Company announcement · Recorded authority: Party primary

    Source URL

    https://msbglobalservices.com/sulphur-springs/

Schedule status · Published delivery dates conflict

Actual · MSB Global Matrix Data Center Campus (Project)

Claim 74470 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Matrix campus breaks ground

    MSB Global Services · Document date: Jun 13, 2025 · Primary

    Source reference: SRC-4224 · Company announcement · Recorded authority: Party primary

    Source URL

    https://msbglobalservices.com/matrix-data-center-campus-breaks-ground-in-sulphur-springs-tx-a-new-era-for-net-zero-ai-infrastructure/

Counterparties and capital

MSB Global Services · Developer · CMP-1498

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.