MSB Global Matrix Data Center Campus
- Planned / design
- 3,000 MW
- Updated
- Oct 28, 2026
MSB Global Services’ Matrix campus in Sulphur Springs, Texas is planned as a 3 GW, 30-building development on roughly 1,677 acres. The company announced a June 2025 groundbreaking and described an initial eight-building, 800 MW phase, but its published delivery dates conflict across materials. The 3 GW value is therefore a full-build design target, not operating capacity, and the phase schedule needs reconciliation. Local legal, utility, permitting, customer and financing details remain open.
Capacity
Operating IT capacity: Not established in published records
A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.
Development
30 buildings
MSB Global Services’ Matrix campus in Sulphur Springs, Texas is planned as a 3 GW, 30-building development on roughly 1,677 acres. The company announced a June 2025 groundbreaking and described an initial eight-building, 800 MW phase, but its published delivery dates conflict across materials. The 3 GW value is therefore a full-build design target, not operating capacity, and the phase schedule needs reconciliation. Local legal, utility, permitting, customer and financing details remain open.
Milestones (1)
Jun 13, 2025 · Recorded actual event
Completed · Construction started
Source not linkedParticipants
Developer
Sources by role
Developer (1)
- MSB Global Matrix Data Center Campus public-record research record · Aug 28, 2026 · Primary
Site & development
Additional project facts
Capacity basis
Actual3,000 MW is the 30-building full build design; Phase 1 is described as 800 MW and delivery dates conflict.
SourceInfrastructure & permits
Technical details (1)
Planned or represented
3,000 MW
Full-build design objective; not operating load.
Project map
Public-source research. Plans may change. See Evidence for sources and qualifications.