MSB Global Matrix Data Center Campus

Sulphur Springs, Texas, United StatesPreconstruction
Evidence
Planned / design
3,000 MW
Updated
Oct 28, 2026

MSB Global Services’ Matrix campus in Sulphur Springs, Texas is planned as a 3 GW, 30-building development on roughly 1,677 acres. The company announced a June 2025 groundbreaking and described an initial eight-building, 800 MW phase, but its published delivery dates conflict across materials. The 3 GW value is therefore a full-build design target, not operating capacity, and the phase schedule needs reconciliation. Local legal, utility, permitting, customer and financing details remain open.

Capacity

Reported capacity

Planned / design or future potential

3,000 MW

Source

Reported capacity

Planned / design or future potential

3,000 MW

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Site work and phased campus developmentUnder construction

30 buildings

MSB Global Services’ Matrix campus in Sulphur Springs, Texas is planned as a 3 GW, 30-building development on roughly 1,677 acres. The company announced a June 2025 groundbreaking and described an initial eight-building, 800 MW phase, but its published delivery dates conflict across materials. The 3 GW value is therefore a full-build design target, not operating capacity, and the phase schedule needs reconciliation. Local legal, utility, permitting, customer and financing details remain open.

Milestones (1)
Groundbreaking announced

Jun 13, 2025 · Recorded actual event

Completed · Construction started

Source not linked

Participants

MSB Global Services

Developer

Sources by role

Site & development

Location context

Actual

MSB Global Matrix Data Center Campus | Sulphur Springs | Texas | US

Source

Location context

Actual

MSB Global Matrix Data Center Campus | Sulphur Springs | Texas | US

Source

Site area

Actual

1,677 acres

Source

Building count

Actual

30 buildings

Source

Additional project facts

Lifecycle status

Actual

Preconstruction

Source

Capacity basis

Actual

3,000 MW future full build site capacity; not measured operating IT load.

Source

Lifecycle status

Actual

Preconstruction

Source

Capacity basis

Actual

3,000 MW is the 30-building full build design; Phase 1 is described as 800 MW and delivery dates conflict.

Source

Schedule status

Actual

Published delivery dates conflict

Source

Infrastructure & permits

Technical details (1)
Electric grid

Planned or represented

3,000 MW

Full-build design objective; not operating load.

Public-source research. Plans may change. See Evidence for sources and qualifications.