Cartis diligence evidence schedule

Monarch Data Center Campus

PRJ-1133 · Site · Yerington, Nevada, United States

Record last updated Oct 28, 2026

Scope and capacity

Copia Power’s Monarch project in Lyon County, Nevada is a planned integrated power-and-data-center campus. Copia describes a 1,000 MW data-center envelope with 200 MW of solar, 500 MW of storage and 500 MW of thermal capacity; local planning materials show a multi-building campus still moving through land-use review.

Headline: 1,000 MW Planned / design

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Location context · Monarch Data Center Campus | Yerington | Nevada | US

Actual · Monarch Data Center Campus (Project)

Claim 71854 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Monarch Data Center Campus public-record research record

    US Data Center Map · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4116 · News report · Recorded authority: Secondary

    Source URL

    https://dcmap.us/states/nevada/

Lifecycle status · Proposed

Actual · Monarch Data Center Campus (Project)

Claim 71855 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Monarch Data Center Campus public-record research record

    US Data Center Map · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4116 · News report · Recorded authority: Secondary

    Source URL

    https://dcmap.us/states/nevada/

Reported capacity · 1,000 MW

Planned / design or future potential · Monarch Data Center Campus (Project)

Claim 71856 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Selected headline

  1. Monarch Data Center Campus public-record research record

    US Data Center Map · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4116 · News report · Recorded authority: Secondary

    Source URL

    https://dcmap.us/states/nevada/

Capacity basis · 1,000 MW future full build site capacity; not measured operating IT load.

Actual · Monarch Data Center Campus (Project)

Claim 71857 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Monarch Data Center Campus public-record research record

    US Data Center Map · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4116 · News report · Recorded authority: Secondary

    Source URL

    https://dcmap.us/states/nevada/

Solar capacity · 200 MW

Design · Monarch Data Center Campus (Project)

Claim 77720 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

  1. Monarch project

    Copia Power · Document date: Aug 28, 2026 · Primary

    Source reference: SRC-4413 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.copiapower.com/interactive-map-collection/ru9ht9lachmjgoqnn73bq8grhyfjei-mhprk-gd4f3-yf9ax-93my9-9ftc2-rf7hh-jg6rr-224sc-t23mt-h5xp6-zw5cj-a9x2y-6c978-tthy2-7a46w-ejjen-ln25x-2jarn-e98nn-7yg8p

Counterparties and capital

Copia Power · Developer · CMP-1523

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.