Monarch Data Center Campus
- Planned / design
- 1,000 MW
- Updated
- Oct 28, 2026
Copia Power’s Monarch project in Lyon County, Nevada is a planned integrated power-and-data center campus. Copia describes a 1,000 MW data center envelope with 200 MW of solar, 500 MW of storage and 500 MW of thermal capacity; local planning materials show a multi-building campus still moving through land-use review.
Capacity
Operating IT capacity: Not established in published records
A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.
Development
Copia Power’s Monarch project in Lyon County, Nevada is a planned integrated power-and-data center campus. Copia describes a 1,000 MW data center envelope with 200 MW of solar, 500 MW of storage and 500 MW of thermal capacity; local planning materials show a multi-building campus still moving through land-use review.
Milestones (1)
Aug 2026 · Event timing type not established
In progress · Permit filed
Source not linkedParticipants
Developer
Sources by role
Developer (1)
- Monarch Data Center Campus public-record research record · Aug 28, 2026 · Primary
Site & development
Additional project facts
Infrastructure & permits
Technical details (3)
Planned or represented
500 MW
Thermal generation component.
Planned or represented
500 MW
Planned storage component.
Planned or represented
200 MW
Planned photovoltaic component.
Project map