Cartis diligence evidence schedule

Microsoft Hebron Datacenter

PRJ-0428 · Site · 129 North High Street / Canyon Road, Hebron, Ohio, United States

Record last updated Oct 28, 2026

Scope and capacity

Microsoft's October 2026 Hebron update confirms that substation work is underway while site preparation continues. It does not establish that the substation is energized, that vertical data-center development is complete or that the campus has opened. Microsoft Hebron Datacenter is a physical data-center campus. Microsoft Hebron Datacenter is located in 129 North High Street / Canyon Road, Hebron, OH, US and is a data center campus in construction status.

Headline: Not established in published records

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Site context · West of Ohio 79 between North High Street and Canyon Road

Actual · Microsoft Hebron Datacenter (Project)

Claim 40833 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Microsoft gets approval for data center campus in Licking County, Ohio

    Data Center Dynamics · Document date: Jun 26, 2024 · Primary

    Source reference: SRC-2267 · Recorded authority: Secondary

    Source URL

    https://www.datacenterdynamics.com/en/news/microsoft-gets-approval-for-data-center-campus-in-licking-county-ohio/

Mass grading start · 2026-02

Actual · Microsoft Hebron Datacenter (Project)

Claim 40836 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Hebron datacenter construction update

    Microsoft · Document date: Jul 1, 2026 · Primary

    Source reference: SRC-2265 · Recorded authority: Party primary

    Source URL

    https://local.microsoft.com/blog/hebron-datacenter-construction-update/

Mass grading target completion · 2026-11

Actual · Microsoft Hebron Datacenter (Project)

Claim 40837 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Hebron datacenter construction update

    Microsoft · Document date: Jul 1, 2026 · Primary

    Source reference: SRC-2265 · Recorded authority: Party primary

    Source URL

    https://local.microsoft.com/blog/hebron-datacenter-construction-update/

Early site preparation target · 2026-12-31

Actual · Microsoft Hebron Datacenter (Project)

Claim 40838 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Hebron datacenter construction update

    Microsoft · Document date: Jul 1, 2026 · Primary

    Source reference: SRC-2265 · Recorded authority: Party primary

    Source URL

    https://local.microsoft.com/blog/hebron-datacenter-construction-update/

Vertical construction to follow · True

Actual · Microsoft Hebron Datacenter (Project)

Claim 40839 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Hebron datacenter construction update

    Microsoft · Document date: Jul 1, 2026 · Primary

    Source reference: SRC-2265 · Recorded authority: Party primary

    Source URL

    https://local.microsoft.com/blog/hebron-datacenter-construction-update/

Substation work expected · True

Actual · Microsoft Hebron Datacenter (Project)

Claim 40840 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Hebron datacenter construction update

    Microsoft · Document date: Jul 1, 2026 · Primary

    Source reference: SRC-2265 · Recorded authority: Party primary

    Source URL

    https://local.microsoft.com/blog/hebron-datacenter-construction-update/

Operating capacity disclosed · False

Actual · Microsoft Hebron Datacenter (Project)

Claim 40841 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Hebron datacenter construction update

    Microsoft · Document date: Jul 1, 2026 · Primary

    Source reference: SRC-2265 · Recorded authority: Party primary

    Source URL

    https://local.microsoft.com/blog/hebron-datacenter-construction-update/

Completion of grading equals operation · False

Actual · Microsoft Hebron Datacenter (Project)

Claim 40842 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Hebron datacenter construction update

    Microsoft · Document date: Jul 1, 2026 · Primary

    Source reference: SRC-2265 · Recorded authority: Party primary

    Source URL

    https://local.microsoft.com/blog/hebron-datacenter-construction-update/

Counterparties and capital

Ames Construction · Contractor · CMP-1049

Microsoft · Developer · CMP-0017

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.