Microsoft Hebron Datacenter

129 North High Street / Canyon Road, Hebron, Ohio, United StatesUnder construction
Capacity
No public figure
Lead participant
Microsoft
Developer
Last updated
Aug 25, 2026
Most recent public record update

About Microsoft Hebron Datacenter

Microsoft Hebron Datacenter is a physical data center campus. Microsoft Hebron Datacenter is located in 129 North High Street / Canyon Road, Hebron, OH, US and is a data center campus in construction status. Participants include Microsoft as developer, Ames Construction as contractor. Development comprises Mass grading and site preparation (construction), Future vertical development (planned). Key milestones include Hebron groundbreaking ceremony (2026-02-24) and Mass grading target completion (2026-11-30). electric substation: First-party July 2026 update anticipates substation work; utility and capacity undisclosed. Permitting includes development approval for Hebron campus (approved).

Program relationships

1 linked

Projects sharing a market, utility, or organization.

2 related

Capacity

Operating capacityAn operating IT-capacity figure has not been publicly disclosed.

No additional capacity claims are published.

Development

2 phases · 3 milestones
Mass grading and site preparationUnder Construction

Early site work, stormwater and anticipated substation work.

Future vertical developmentPlanned

Historical six-building approval is not assumed to be current design.

Jun 1, 2024
Hebron approved the campus development plan
Completed
Feb 24, 2026
Hebron groundbreaking ceremony
Completed
Nov 30, 2026
Mass grading target completion
Forecast

Infrastructure

Electric GridPlanned Or Represented

First-party July 2026 update anticipates substation work; utility and capacity undisclosed.

Project map

0 of 1 project point mapped
Infrastructure facts
1
Mapped records
1
Capacity figures
0

No map point available

Power & interconnection: 1

Facts & sources

Published claims and their source links.

8 facts
Site Context
West of Ohio 79 between North High Street and Canyon Road
Actual
Mass Grading Start
2026-02
Actual
Mass Grading Target Completion
2026-11
Actual
Early Site Preparation Target
2026-12-31
Actual
Vertical Construction To Follow
True
Actual
Substation Work Expected
True
Actual
Operating Capacity Disclosed
False
Actual
Completion Of Grading Equals Operation
False
Actual