Cartis diligence evidence schedule
Meta Tulsa AI Data Center
PRJ-0384 · Site · Tulsa, Oklahoma, United States
Captured 2026-09-06T04:12:19.971Z · Record last updated 2026-08-25
SHA-256: ccdf88adf65bd6ce8b6cfeb08948ebda9cf5fffcc60953d086ec069f646ee132
Save a diligence baseline
Download the public evidence as it appears now. Compare a previously saved snapshot to see added, removed and changed claims, counterparties, financing and milestones. Files are read in this browser and are not uploaded.
The fingerprint detects file changes; it is not a digital signature or a claim of independently verified authenticity. Keep your downloaded copy with the transaction file.
Scope and capacity
Meta's first Oklahoma data center is under construction at Fair Oaks in east Tulsa; the adjacent Phase 2 rezoning was withdrawn and remains outside the active campus footprint. Meta Tulsa AI Data Center is located in Tulsa, OK, US and is a data center campus in construction status.
Headline: —
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Planned Investment Over · $1 billion
Planned / design or future potential · Meta Tulsa AI Data Center (project)
Claim 34714 · Review: Approved · Claim date: Not published
- Breaking ground on a new AI-optimized data center in Tulsa, Oklahoma
Meta · Document date: 2026-04-21 · Primary
https://about.fb.com/news/2026/04/breaking-ground-new-ai-optimized-data-center-tulsa-oklahoma/ - Meta breaks ground on new USD 1 billion data center in Tulsa
Oklahoma Department of Commerce · Document date: 2026-04-21 · Corroborating
https://www.okcommerce.gov/meta-breaks-ground-on-data-center-in-tulsa/ - Meta breaks ground on over USD 1 billion data center in Oklahoma's Tulsa
Reuters · Document date: 2026-04-21 · Corroborating
https://www.reuters.com/technology/meta-breaks-ground-over-1-billion-data-center-oklahomas-tulsa-2026-04-21/
Reported Floor Area Over · 2,000,000 square feet
actual · Meta Tulsa AI Data Center (project)
Claim 34715 · Review: Approved · Claim date: Not published
- Meta breaks ground on new USD 1 billion data center in Tulsa
Oklahoma Department of Commerce · Document date: 2026-04-21 · Primary
https://www.okcommerce.gov/meta-breaks-ground-on-data-center-in-tulsa/
Phase 1 Site Area Approximately · 340 acres
actual · Meta Tulsa AI Data Center (project)
Claim 34716 · Review: Approved · Claim date: Not published
- Meta's east Tulsa data center earns praise and protests
Tulsa Flyer / Oklahoma Eagle · Document date: 2026-04-22 · Corroborating
https://tulsaflyer.org/2026/04/22/news/post/meta-east-tulsa-data-center/ - Developer withdraws plans to build second phase of Tulsa data center
Data Center Dynamics · Document date: 2026-04-01 · Primary
https://www.datacenterdynamics.com/en/news/developer-withdraws-plans-to-build-second-phase-of-500-acre-data-center-in-tulsa-oklahoma/
Physical Construction Started · True
actual · Meta Tulsa AI Data Center (project)
Claim 34718 · Review: Approved · Claim date: 2026-04-21T00:00:00+00:00
- Breaking ground on a new AI-optimized data center in Tulsa, Oklahoma
Meta · Document date: 2026-04-21 · Primary
https://about.fb.com/news/2026/04/breaking-ground-new-ai-optimized-data-center-tulsa-oklahoma/ - Meta breaks ground on new USD 1 billion data center in Tulsa
Oklahoma Department of Commerce · Document date: 2026-04-21 · Corroborating
https://www.okcommerce.gov/meta-breaks-ground-on-data-center-in-tulsa/ - Meta breaks ground on over USD 1 billion data center in Oklahoma's Tulsa
Reuters · Document date: 2026-04-21 · Corroborating
https://www.reuters.com/technology/meta-breaks-ground-over-1-billion-data-center-oklahomas-tulsa-2026-04-21/
Planned Peak Construction Jobs · 1,000 jobs approximately
Planned / design or future potential · Meta Tulsa AI Data Center (project)
Claim 34721 · Review: Approved · Claim date: Not published
- Breaking ground on a new AI-optimized data center in Tulsa, Oklahoma
Meta · Document date: 2026-04-21 · Primary
https://about.fb.com/news/2026/04/breaking-ground-new-ai-optimized-data-center-tulsa-oklahoma/ - Meta breaks ground on new USD 1 billion data center in Tulsa
Oklahoma Department of Commerce · Document date: 2026-04-21 · Corroborating
https://www.okcommerce.gov/meta-breaks-ground-on-data-center-in-tulsa/
Planned Operational Jobs · 100 jobs approximately
Planned / design or future potential · Meta Tulsa AI Data Center (project)
Claim 34722 · Review: Approved · Claim date: Not published
- Breaking ground on a new AI-optimized data center in Tulsa, Oklahoma
Meta · Document date: 2026-04-21 · Primary
https://about.fb.com/news/2026/04/breaking-ground-new-ai-optimized-data-center-tulsa-oklahoma/ - Meta breaks ground on new USD 1 billion data center in Tulsa
Oklahoma Department of Commerce · Document date: 2026-04-21 · Corroborating
https://www.okcommerce.gov/meta-breaks-ground-on-data-center-in-tulsa/
Local Infrastructure Investment Over · $25 million
actual · Meta Tulsa AI Data Center (project)
Claim 34723 · Review: Approved · Claim date: Not published
- Breaking ground on a new AI-optimized data center in Tulsa, Oklahoma
Meta · Document date: 2026-04-21 · Primary
https://about.fb.com/news/2026/04/breaking-ground-new-ai-optimized-data-center-tulsa-oklahoma/ - Meta breaks ground on new USD 1 billion data center in Tulsa
PartnerTulsa · Document date: 2026-04-21 · Corroborating
https://partnertulsa.org/meta-breaks-ground-on-new-1-billion-data-center-in-tulsa/
Closed Loop Liquid Cooling Planned · True
Planned / design or future potential · Meta Tulsa AI Data Center (project)
Claim 34725 · Review: Approved · Claim date: Not published
- Breaking ground on a new AI-optimized data center in Tulsa, Oklahoma
Meta · Document date: 2026-04-21 · Primary
https://about.fb.com/news/2026/04/breaking-ground-new-ai-optimized-data-center-tulsa-oklahoma/
Zero Water Majority Of Year Planned · True
Planned / design or future potential · Meta Tulsa AI Data Center (project)
Claim 34726 · Review: Approved · Claim date: Not published
- Breaking ground on a new AI-optimized data center in Tulsa, Oklahoma
Meta · Document date: 2026-04-21 · Primary
https://about.fb.com/news/2026/04/breaking-ground-new-ai-optimized-data-center-tulsa-oklahoma/
Water Restoration Term · 10 years
actual · Meta Tulsa AI Data Center (project)
Claim 34727 · Review: Approved · Claim date: Not published
- Hello, Tulsa!
Meta Data Centers · Document date: 2026-04-21 · Primary
https://datacenters.atmeta.com/2026/04/hello-tulsa/
Water Restoration Crop Area · 1,500 acres
actual · Meta Tulsa AI Data Center (project)
Claim 34728 · Review: Approved · Claim date: Not published
- Hello, Tulsa!
Meta Data Centers · Document date: 2026-04-21 · Primary
https://datacenters.atmeta.com/2026/04/hello-tulsa/
Water Savings Target Over · 50 million gallons per year
Planned / design or future potential · Meta Tulsa AI Data Center (project)
Claim 34729 · Review: Approved · Claim date: Not published
- Hello, Tulsa!
Meta Data Centers · Document date: 2026-04-21 · Primary
https://datacenters.atmeta.com/2026/04/hello-tulsa/
Electricity Use Clean Energy Match Target · 100 percent
Planned / design or future potential · Meta Tulsa AI Data Center (project)
Claim 34731 · Review: Approved · Claim date: Not published
- Breaking ground on a new AI-optimized data center in Tulsa, Oklahoma
Meta · Document date: 2026-04-21 · Primary
https://about.fb.com/news/2026/04/breaking-ground-new-ai-optimized-data-center-tulsa-oklahoma/ - Hello, Tulsa!
Meta Data Centers · Document date: 2026-04-21 · Corroborating
https://datacenters.atmeta.com/2026/04/hello-tulsa/
Utility Cost Pass Through To Consumers Planned · False
Planned / design or future potential · Meta Tulsa AI Data Center (project)
Claim 34732 · Review: Approved · Claim date: Not published
- Breaking ground on a new AI-optimized data center in Tulsa, Oklahoma
Meta · Document date: 2026-04-21 · Primary
https://about.fb.com/news/2026/04/breaking-ground-new-ai-optimized-data-center-tulsa-oklahoma/ - Hello, Tulsa!
Meta Data Centers · Document date: 2026-04-21 · Corroborating
https://datacenters.atmeta.com/2026/04/hello-tulsa/
Phase 2 Rezoning Withdrawn · True
actual · Meta Tulsa AI Data Center (project)
Claim 34734 · Review: Approved · Claim date: 2026-03-30T00:00:00+00:00
- Developer withdraws plans to build second phase of Tulsa data center
Data Center Dynamics · Document date: 2026-04-01 · Primary
https://www.datacenterdynamics.com/en/news/developer-withdraws-plans-to-build-second-phase-of-500-acre-data-center-in-tulsa-oklahoma/
Citywide Moratorium Exception · True
actual · Meta Tulsa AI Data Center (project)
Claim 34736 · Review: Approved · Claim date: Not published
- Meta's east Tulsa data center earns praise and protests
Tulsa Flyer / Oklahoma Eagle · Document date: 2026-04-22 · Corroborating
https://tulsaflyer.org/2026/04/22/news/post/meta-east-tulsa-data-center/ - Tulsa City Council data-center moratorium supporting documentation
City of Tulsa · Document date: 2026-03-25 · Primary
https://www.cityoftulsa.org/apps/CouncilDocuments?item=49527
Reported Completion Target · 2028
Planned / design or future potential · Meta Tulsa AI Data Center (project)
Claim 34737 · Review: Approved · Claim date: Not published
- Meta's east Tulsa data center earns praise and protests
Tulsa Flyer / Oklahoma Eagle · Document date: 2026-04-22 · Primary
https://tulsaflyer.org/2026/04/22/news/post/meta-east-tulsa-data-center/
First Oklahoma Meta Data Center · True
actual · Meta Tulsa AI Data Center (project)
Claim 34738 · Review: Approved · Claim date: Not published
- Breaking ground on a new AI-optimized data center in Tulsa, Oklahoma
Meta · Document date: 2026-04-21 · Primary
https://about.fb.com/news/2026/04/breaking-ground-new-ai-optimized-data-center-tulsa-oklahoma/ - Meta breaks ground on new USD 1 billion data center in Tulsa
Oklahoma Department of Commerce · Document date: 2026-04-21 · Corroborating
https://www.okcommerce.gov/meta-breaks-ground-on-data-center-in-tulsa/
Counterparties and capital
Atmoss, LLC · Developer · CMP-0934
City of Tulsa · Government Authority · CMP-0935
Fortis Construction · Contractor · CMP-0938
Meta Platforms, Inc. · Operator, Owner · CMP-0083
PartnerTulsa / Tulsa Authority for Economic Opportunity · Government Authority · CMP-0937
Public Service Company of Oklahoma · Utility Provider · CMP-0939
Tulsa Metropolitan Utility Authority · Utility Provider · CMP-0940
$1,000,000,000 · 2026-04-21
Meta-announced campus investment; exact total and spend schedule undisclosed.
Meta Platforms, Inc. (Owner / Sponsor)
Financing record 108; claim-specific source links appear in the exhibit sources where published.
$25,000,000 · 2026-04-21
Road and water improvements. 5 million project fund until overlap is reconciled.
Meta Platforms, Inc. (Funder)
Financing record 109; claim-specific source links appear in the exhibit sources where published.
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed. Downloaded snapshots are retained by you; Cartis does not archive them automatically.