Data center siteSite record

Meta Tulsa AI Data Center

Tulsa, Oklahoma, United StatesUnder construction
Capacity
No public figure
Lead participant
Atmoss, LLC
Developer
Last updated
Aug 25, 2026
Most recent public record update

About Meta Tulsa AI Data Center

Meta's first Oklahoma data center is under construction at Fair Oaks in east Tulsa; the adjacent Phase 2 rezoning was withdrawn and remains outside the active campus footprint. Meta Tulsa AI Data Center is located in Tulsa, OK, US and is a data center campus in construction status. Participants include Meta Platforms as owner, Meta Platforms as operator, Atmoss, LLC as developer, Fortis Construction as contractor. Development comprises Phase 1 / disclosed Meta Tulsa campus (construction), Adjacent Phase 2 rezoning (cancelled). Key milestones include Meta identifies Project Anthem and announces construction (2026-04-21) and Secondary local reporting targets completion in 2028 (2028-01-01). electricity service: PSO is a named partner; campus load and service agreement are not public. water and wastewater: Closed-loop design and local road/water improvements are planned; actual demand and service terms remain unresolved. Permitting includes rezoning Z-7851 for Project Anthem Phase 2 (withdrawn) and data center moratorium exception for Meta Tulsa Phase 1 (exempted). Capital records include planned campus investment of 1 USD billion plus for Meta-announced campus investment; exact total and spend schedule undisclosed. and local infrastructure improvements commitment of 25 USD million plus for Road and water improvements. 5 million project fund until overlap is reconciled. Incentives include Local Development Act ad valorem exemption (approved) for 85% exemption of specified ad valorem taxes and special assessments for up to 25 fiscal years under the Project Anthem Tax Incentive District agreement; multiple taxing entities are parties.

Capacity

Operating capacityAn operating IT-capacity figure has not been publicly disclosed.

No additional capacity claims are published.

Development

2 phases · 5 milestones
Phase 1 / disclosed Meta Tulsa campusUnder Construction

Approximately 340-acre disclosed campus; no public MW figure.

Adjacent Phase 2 rezoningChanged Or Cancelled

Approximately 375-acre adjacent expansion; not active campus area or capacity.

May 1, 2024
City approves Project Anthem ad valorem exemption agreement
Completed
Mar 25, 2026
Tulsa adopts temporary moratorium with Project Anthem exception
Completed
Mar 30, 2026
Atmoss withdraws adjacent Phase 2 rezoning
Completed
Apr 21, 2026
Meta identifies Project Anthem and announces construction
Completed
Jan 1, 2028
Secondary local reporting targets completion in 2028
Forecast

Infrastructure

Utility ServiceUnder Construction

PSO is a named partner; campus load and service agreement are not public.

Water SupplyUnder Construction

Closed-loop design and local road/water improvements are planned; actual demand and service terms remain unresolved.

Water SupplyPlanned Or Represented

50 million gallons per year

Ten-year irrigation-technology project target; not an offset already delivered or a measure of campus water use.

Renewable Energy SupplyReported Context

1,500 MW

Oklahoma-wide Meta clean-energy contracts; not dedicated Tulsa capacity.

Project map

0 of 1 project point mapped
Infrastructure facts
4
Mapped records
1
Capacity figures
2

No map point available

Power & interconnection: 2Cooling & water: 2

Facts & sources

Published claims and their source links.

18 facts
Planned Investment Over
$1 billion
Actual
Reported Floor Area Over
2,000,000 square feet
Actual
Phase 1 Site Area Approximately
340 acres
Actual
Physical Construction Started
True
Actual
Planned Peak Construction Jobs
1,000 jobs approximately
Actual
Planned Operational Jobs
100 jobs approximately
Actual
Local Infrastructure Investment Over
$25 million
Actual
Closed Loop Liquid Cooling Planned
True
Actual
Zero Water Majority Of Year Planned
True
Actual
Water Restoration Term
10 years
Actual
Water Restoration Crop Area
1,500 acres
Actual
Water Savings Target Over
50 million gallons per year
Actual
Electricity Use Clean Energy Match Target
100 percent
Actual
Utility Cost Pass Through To Consumers Planned
False
Actual
Phase 2 Rezoning Withdrawn
True
Actual
Citywide Moratorium Exception
True
Actual
Reported Completion Target
2028
Actual
First Oklahoma Meta Data Center
True
Actual