Cartis diligence evidence schedule

Meta Lebanon Data Center Campus

PRJ-0032 · Site · Lebanon; LEAP Lebanon Innovation District, Indiana, United States

Record last updated Oct 28, 2026

Scope and capacity

Meta broke ground in February 2026 on a multi-phase data-center campus in Lebanon, Indiana. The operator and state describe a roughly 1,500-acre, 13-building plan designed to deliver 1 GW once operational, with investment above USD 10 billion.

Headline: Not established in published records

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Project status · Under construction

Actual · Meta Lebanon Data Center Campus (Project)

Claim 4548 · Recorded claim type: Actual · Review: Approved · Claim date: Feb 11, 2026

  1. Meta's new data center in Lebanon, Indiana marks milestone AI investment

    Meta · Document date: Feb 11, 2026 · Primary

    Source reference: SRC-0245 · Company announcement · Recorded authority: Party primary

    Source URL

    https://about.fb.com/news/2026/02/metas-new-data-center-lebanon-indiana-marks-milestone-ai-investment/amp/

  2. Gov. Braun breaks ground on $10B Meta data center campus at LEAP District

    Indiana Economic Development Corporation · Document date: Feb 11, 2026 · Corroborating

    Source reference: SRC-0247 · Government record · Recorded authority: Official primary

    Source URL

    https://iedc.in.gov/events/news/details/2026/02/11/gov.-braun-breaks-ground-on-10b-meta-data-center-campus-at-leap-district

  3. Meta begins construction on $10 billion Indiana data center to boost AI capabilities

    Reuters · Document date: Feb 11, 2026 · Corroborating

    Source reference: SRC-0249 · News report · Recorded authority: Secondary

    Source URL

    https://www.reuters.com/business/meta-begins-construction-10-billion-indiana-data-center-boost-ai-capabilities-2026-02-11/

Designed full campus capacity · 1,000 MW

Planned / design or future potential · Full campus (Phase)

Claim 4549 · Recorded claim type: Forecast · Review: Approved · Claim date: Feb 11, 2026

Headline treatment: Phase scope; not a whole-site figure

  1. Meta breaks ground on 1-GW data center campus in Indiana

    American Public Power Association · Document date: Feb 12, 2026 · Corroborating

    Source reference: SRC-0250 · News report · Recorded authority: Secondary

    Source URL

    https://www.publicpower.org/periodical/article/meta-breaks-ground-1-gw-data-center-campus-indiana

  2. Meta's new data center in Lebanon, Indiana marks milestone AI investment

    Meta · Document date: Feb 11, 2026 · Primary

    Source reference: SRC-0245 · Company announcement · Recorded authority: Party primary

    Source URL

    https://about.fb.com/news/2026/02/metas-new-data-center-lebanon-indiana-marks-milestone-ai-investment/amp/

Capital investment · $>10000000000

Transaction scope · Meta Lebanon Data Center Campus (Project)

Claim 4550 · Recorded claim type: Transaction scope · Review: Approved · Claim date: Feb 11, 2026

  1. Meta's new data center in Lebanon, Indiana marks milestone AI investment

    Meta · Document date: Feb 11, 2026 · Primary

    Source reference: SRC-0245 · Company announcement · Recorded authority: Party primary

    Source URL

    https://about.fb.com/news/2026/02/metas-new-data-center-lebanon-indiana-marks-milestone-ai-investment/amp/

  2. Hello, Lebanon

    Meta Data Centers · Document date: Feb 11, 2026 · Corroborating

    Source reference: SRC-0246 · Fact sheet · Recorded authority: Party primary

    Source URL

    https://datacenters.atmeta.com/2026/02/hello-lebanon/

  3. Gov. Braun breaks ground on $10B Meta data center campus at LEAP District

    Indiana Economic Development Corporation · Document date: Feb 11, 2026 · Corroborating

    Source reference: SRC-0247 · Government record · Recorded authority: Official primary

    Source URL

    https://iedc.in.gov/events/news/details/2026/02/11/gov.-braun-breaks-ground-on-10b-meta-data-center-campus-at-leap-district

Site area · 1,500 acre

Reported rounded · Meta Lebanon Data Center Campus (Project)

Claim 4551 · Recorded claim type: Reported rounded · Review: Approved · Claim date: Feb 11, 2026

  1. Gov. Braun breaks ground on $10B Meta data center campus at LEAP District

    Indiana Economic Development Corporation · Document date: Feb 11, 2026 · Primary

    Source reference: SRC-0247 · Government record · Recorded authority: Official primary

    Source URL

    https://iedc.in.gov/events/news/details/2026/02/11/gov.-braun-breaks-ground-on-10b-meta-data-center-campus-at-leap-district

Total building count · 13 building

Actual · Full campus (Phase)

Claim 4552 · Recorded claim type: Actual · Review: Approved · Claim date: Feb 11, 2026

  1. Gov. Braun breaks ground on $10B Meta data center campus at LEAP District

    Indiana Economic Development Corporation · Document date: Feb 11, 2026 · Primary

    Source reference: SRC-0247 · Government record · Recorded authority: Official primary

    Source URL

    https://iedc.in.gov/events/news/details/2026/02/11/gov.-braun-breaks-ground-on-10b-meta-data-center-campus-at-leap-district

Data center building count · 10 building

Actual · Full campus (Phase)

Claim 4553 · Recorded claim type: Actual · Review: Approved · Claim date: Feb 11, 2026

  1. Gov. Braun breaks ground on $10B Meta data center campus at LEAP District

    Indiana Economic Development Corporation · Document date: Feb 11, 2026 · Primary

    Source reference: SRC-0247 · Government record · Recorded authority: Official primary

    Source URL

    https://iedc.in.gov/events/news/details/2026/02/11/gov.-braun-breaks-ground-on-10b-meta-data-center-campus-at-leap-district

Support building count · 3 building

Actual · Full campus (Phase)

Claim 4554 · Recorded claim type: Actual · Review: Approved · Claim date: Feb 11, 2026

  1. Gov. Braun breaks ground on $10B Meta data center campus at LEAP District

    Indiana Economic Development Corporation · Document date: Feb 11, 2026 · Primary

    Source reference: SRC-0247 · Government record · Recorded authority: Official primary

    Source URL

    https://iedc.in.gov/events/news/details/2026/02/11/gov.-braun-breaks-ground-on-10b-meta-data-center-campus-at-leap-district

Gross floor area · 4,000,000 sqft

Reported rounded · Meta Lebanon Data Center Campus (Project)

Claim 4555 · Recorded claim type: Reported rounded · Review: Approved · Claim date: Feb 11, 2026

  1. Hello, Lebanon

    Meta Data Centers · Document date: Feb 11, 2026 · Primary

    Source reference: SRC-0246 · Fact sheet · Recorded authority: Party primary

    Source URL

    https://datacenters.atmeta.com/2026/02/hello-lebanon/

First online target · Late 2027 to early 2028

Forecast · Current first construction phase (Phase)

Claim 4556 · Recorded claim type: Forecast · Review: Approved · Claim date: Feb 11, 2026

  1. Meta begins construction on $10 billion Indiana data center to boost AI capabilities

    Reuters · Document date: Feb 11, 2026 · Primary

    Source reference: SRC-0249 · News report · Recorded authority: Secondary

    Source URL

    https://www.reuters.com/business/meta-begins-construction-10-billion-indiana-data-center-boost-ai-capabilities-2026-02-11/

Construction jobs · >4000 job

Reported rounded · Meta Lebanon Data Center Campus (Project)

Claim 4557 · Recorded claim type: Reported rounded · Review: Approved · Claim date: Feb 11, 2026

  1. Meta's new data center in Lebanon, Indiana marks milestone AI investment

    Meta · Document date: Feb 11, 2026 · Primary

    Source reference: SRC-0245 · Company announcement · Recorded authority: Party primary

    Source URL

    https://about.fb.com/news/2026/02/metas-new-data-center-lebanon-indiana-marks-milestone-ai-investment/amp/

  2. Hello, Lebanon

    Meta Data Centers · Document date: Feb 11, 2026 · Corroborating

    Source reference: SRC-0246 · Fact sheet · Recorded authority: Party primary

    Source URL

    https://datacenters.atmeta.com/2026/02/hello-lebanon/

Operational jobs · 300 job

Reported rounded · Meta Lebanon Data Center Campus (Project)

Claim 4558 · Recorded claim type: Reported rounded · Review: Approved · Claim date: Feb 11, 2026

  1. Meta's new data center in Lebanon, Indiana marks milestone AI investment

    Meta · Document date: Feb 11, 2026 · Primary

    Source reference: SRC-0245 · Company announcement · Recorded authority: Party primary

    Source URL

    https://about.fb.com/news/2026/02/metas-new-data-center-lebanon-indiana-marks-milestone-ai-investment/amp/

  2. Hello, Lebanon

    Meta Data Centers · Document date: Feb 11, 2026 · Corroborating

    Source reference: SRC-0246 · Fact sheet · Recorded authority: Party primary

    Source URL

    https://datacenters.atmeta.com/2026/02/hello-lebanon/

Public and utility infrastructure · $>120000000

Transaction scope · Meta Lebanon Data Center Campus (Project)

Claim 4559 · Recorded claim type: Transaction scope · Review: Approved · Claim date: Feb 11, 2026

  1. Meta's new data center in Lebanon, Indiana marks milestone AI investment

    Meta · Document date: Feb 11, 2026 · Primary

    Source reference: SRC-0245 · Company announcement · Recorded authority: Party primary

    Source URL

    https://about.fb.com/news/2026/02/metas-new-data-center-lebanon-indiana-marks-milestone-ai-investment/amp/

Cooling design · Closed loop liquid cooling

Design · Meta Lebanon Data Center Campus (Project)

Claim 4560 · Recorded claim type: Design · Review: Approved · Claim date: Feb 11, 2026

  1. Meta's new data center in Lebanon, Indiana marks milestone AI investment

    Meta · Document date: Feb 11, 2026 · Primary

    Source reference: SRC-0245 · Company announcement · Recorded authority: Party primary

    Source URL

    https://about.fb.com/news/2026/02/metas-new-data-center-lebanon-indiana-marks-milestone-ai-investment/amp/

Clean energy matching · 100 percent

Forecast · Meta Lebanon Data Center Campus (Project)

Claim 4561 · Recorded claim type: Forecast · Review: Approved · Claim date: Feb 11, 2026

  1. Meta's new data center in Lebanon, Indiana marks milestone AI investment

    Meta · Document date: Feb 11, 2026 · Primary

    Source reference: SRC-0245 · Company announcement · Recorded authority: Party primary

    Source URL

    https://about.fb.com/news/2026/02/metas-new-data-center-lebanon-indiana-marks-milestone-ai-investment/amp/

Water restoration commitment · 100 percent consumed

Forecast · Meta Lebanon Data Center Campus (Project)

Claim 4562 · Recorded claim type: Forecast · Review: Approved · Claim date: Feb 11, 2026

  1. Meta's new data center in Lebanon, Indiana marks milestone AI investment

    Meta · Document date: Feb 11, 2026 · Primary

    Source reference: SRC-0245 · Company announcement · Recorded authority: Party primary

    Source URL

    https://about.fb.com/news/2026/02/metas-new-data-center-lebanon-indiana-marks-milestone-ai-investment/amp/

Arable restoration program · 200,000,000 gallon per year

Actual · Meta Lebanon Data Center Campus (Project)

Claim 4563 · Recorded claim type: Actual · Review: Approved · Claim date: Feb 11, 2026

  1. Meta's new data center in Lebanon, Indiana marks milestone AI investment

    Meta · Document date: Feb 11, 2026 · Primary

    Source reference: SRC-0245 · Company announcement · Recorded authority: Party primary

    Source URL

    https://about.fb.com/news/2026/02/metas-new-data-center-lebanon-indiana-marks-milestone-ai-investment/amp/

Leed target · LEED Gold

Forecast · Meta Lebanon Data Center Campus (Project)

Claim 4564 · Recorded claim type: Forecast · Review: Approved · Claim date: Feb 11, 2026

  1. Meta's new data center in Lebanon, Indiana marks milestone AI investment

    Meta · Document date: Feb 11, 2026 · Primary

    Source reference: SRC-0245 · Company announcement · Recorded authority: Party primary

    Source URL

    https://about.fb.com/news/2026/02/metas-new-data-center-lebanon-indiana-marks-milestone-ai-investment/amp/

Counterparties and capital

Arable · Utility provider · CMP-0151

City of Lebanon · Government authority · CMP-0148

Indiana Economic Development Corporation · Government authority · CMP-0149

Meta Platforms, Inc. · Owner · CMP-0083

Investment commitment

$10,000,000,000 · Feb 11, 2026

Minimum current campus investment; operator wording is over USD 10B and Reuters reports Meta covering the full investment at outset.

Meta Platforms, Inc. (Sponsor)

Financing record 27; claim-specific source links appear in the exhibit sources where published.

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.