Cartis diligence evidence schedule
Meta Lebanon Data Center Campus
PRJ-0032 · Site · Lebanon; LEAP Lebanon Innovation District, Indiana, United States
Captured 2026-09-06T04:13:12.901Z · Record last updated 2026-08-22
SHA-256: dc20deaa2392b98590c7cc6a579441ae2c5dedbe8d910dbb0cf871694ae8a2e0
Save a diligence baseline
Download the public evidence as it appears now. Compare a previously saved snapshot to see added, removed and changed claims, counterparties, financing and milestones. Files are read in this browser and are not uploaded.
The fingerprint detects file changes; it is not a digital signature or a claim of independently verified authenticity. Keep your downloaded copy with the transaction file.
Scope and capacity
Meta broke ground in February 2026 on a multi-phase data-center campus in Lebanon, Indiana. The operator and state describe a roughly 1,500-acre, 13-building plan designed to deliver 1 GW once operational, with investment above USD 10 billion.
Headline: —
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Project Status · Under construction
actual · Meta Lebanon Data Center Campus (project)
Claim 4548 · Review: Approved · Claim date: 2026-02-11T00:00:00+00:00
- Meta's new data center in Lebanon, Indiana marks milestone AI investment
Meta · Document date: 2026-02-11 · Primary
https://about.fb.com/news/2026/02/metas-new-data-center-lebanon-indiana-marks-milestone-ai-investment/amp/ - Gov. Braun breaks ground on $10B Meta data center campus at LEAP District
Indiana Economic Development Corporation · Document date: 2026-02-11 · Corroborating
https://iedc.in.gov/events/news/details/2026/02/11/gov.-braun-breaks-ground-on-10b-meta-data-center-campus-at-leap-district - Meta begins construction on $10 billion Indiana data center to boost AI capabilities
Reuters · Document date: 2026-02-11 · Corroborating
https://www.reuters.com/business/meta-begins-construction-10-billion-indiana-data-center-boost-ai-capabilities-2026-02-11/
Designed Full Campus Capacity · 1,000 MW
Planned / design or future potential · Full campus (phase)
Claim 4549 · Review: Approved · Claim date: 2026-02-11T00:00:00+00:00
Headline treatment: Phase scope; not a whole-site figure
- Meta breaks ground on 1-GW data center campus in Indiana
American Public Power Association · Document date: 2026-02-12 · Corroborating
https://www.publicpower.org/periodical/article/meta-breaks-ground-1-gw-data-center-campus-indiana - Meta's new data center in Lebanon, Indiana marks milestone AI investment
Meta · Document date: 2026-02-11 · Primary
https://about.fb.com/news/2026/02/metas-new-data-center-lebanon-indiana-marks-milestone-ai-investment/amp/
Capital Investment · $>10000000000
transaction scope · Meta Lebanon Data Center Campus (project)
Claim 4550 · Review: Approved · Claim date: 2026-02-11T00:00:00+00:00
- Meta's new data center in Lebanon, Indiana marks milestone AI investment
Meta · Document date: 2026-02-11 · Primary
https://about.fb.com/news/2026/02/metas-new-data-center-lebanon-indiana-marks-milestone-ai-investment/amp/ - Hello, Lebanon
Meta Data Centers · Document date: 2026-02-11 · Corroborating
https://datacenters.atmeta.com/2026/02/hello-lebanon/ - Gov. Braun breaks ground on $10B Meta data center campus at LEAP District
Indiana Economic Development Corporation · Document date: 2026-02-11 · Corroborating
https://iedc.in.gov/events/news/details/2026/02/11/gov.-braun-breaks-ground-on-10b-meta-data-center-campus-at-leap-district
Site Area · 1,500 acre
reported rounded · Meta Lebanon Data Center Campus (project)
Claim 4551 · Review: Approved · Claim date: 2026-02-11T00:00:00+00:00
- Gov. Braun breaks ground on $10B Meta data center campus at LEAP District
Indiana Economic Development Corporation · Document date: 2026-02-11 · Primary
https://iedc.in.gov/events/news/details/2026/02/11/gov.-braun-breaks-ground-on-10b-meta-data-center-campus-at-leap-district
Total Building Count · 13 building
actual · Full campus (phase)
Claim 4552 · Review: Approved · Claim date: 2026-02-11T00:00:00+00:00
- Gov. Braun breaks ground on $10B Meta data center campus at LEAP District
Indiana Economic Development Corporation · Document date: 2026-02-11 · Primary
https://iedc.in.gov/events/news/details/2026/02/11/gov.-braun-breaks-ground-on-10b-meta-data-center-campus-at-leap-district
Data Center Building Count · 10 building
actual · Full campus (phase)
Claim 4553 · Review: Approved · Claim date: 2026-02-11T00:00:00+00:00
- Gov. Braun breaks ground on $10B Meta data center campus at LEAP District
Indiana Economic Development Corporation · Document date: 2026-02-11 · Primary
https://iedc.in.gov/events/news/details/2026/02/11/gov.-braun-breaks-ground-on-10b-meta-data-center-campus-at-leap-district
Support Building Count · 3 building
actual · Full campus (phase)
Claim 4554 · Review: Approved · Claim date: 2026-02-11T00:00:00+00:00
- Gov. Braun breaks ground on $10B Meta data center campus at LEAP District
Indiana Economic Development Corporation · Document date: 2026-02-11 · Primary
https://iedc.in.gov/events/news/details/2026/02/11/gov.-braun-breaks-ground-on-10b-meta-data-center-campus-at-leap-district
Gross Floor Area · 4,000,000 sqft
reported rounded · Meta Lebanon Data Center Campus (project)
Claim 4555 · Review: Approved · Claim date: 2026-02-11T00:00:00+00:00
- Hello, Lebanon
Meta Data Centers · Document date: 2026-02-11 · Primary
https://datacenters.atmeta.com/2026/02/hello-lebanon/
First Online Target · Late 2027 to early 2028
Planned / design or future potential · Current first construction phase (phase)
Claim 4556 · Review: Approved · Claim date: 2026-02-11T00:00:00+00:00
- Meta begins construction on $10 billion Indiana data center to boost AI capabilities
Reuters · Document date: 2026-02-11 · Primary
https://www.reuters.com/business/meta-begins-construction-10-billion-indiana-data-center-boost-ai-capabilities-2026-02-11/
Construction Jobs · >4000 job
reported rounded · Meta Lebanon Data Center Campus (project)
Claim 4557 · Review: Approved · Claim date: 2026-02-11T00:00:00+00:00
- Meta's new data center in Lebanon, Indiana marks milestone AI investment
Meta · Document date: 2026-02-11 · Primary
https://about.fb.com/news/2026/02/metas-new-data-center-lebanon-indiana-marks-milestone-ai-investment/amp/ - Hello, Lebanon
Meta Data Centers · Document date: 2026-02-11 · Corroborating
https://datacenters.atmeta.com/2026/02/hello-lebanon/
Operational Jobs · 300 job
reported rounded · Meta Lebanon Data Center Campus (project)
Claim 4558 · Review: Approved · Claim date: 2026-02-11T00:00:00+00:00
- Meta's new data center in Lebanon, Indiana marks milestone AI investment
Meta · Document date: 2026-02-11 · Primary
https://about.fb.com/news/2026/02/metas-new-data-center-lebanon-indiana-marks-milestone-ai-investment/amp/ - Hello, Lebanon
Meta Data Centers · Document date: 2026-02-11 · Corroborating
https://datacenters.atmeta.com/2026/02/hello-lebanon/
Public And Utility Infrastructure · $>120000000
transaction scope · Meta Lebanon Data Center Campus (project)
Claim 4559 · Review: Approved · Claim date: 2026-02-11T00:00:00+00:00
- Meta's new data center in Lebanon, Indiana marks milestone AI investment
Meta · Document date: 2026-02-11 · Primary
https://about.fb.com/news/2026/02/metas-new-data-center-lebanon-indiana-marks-milestone-ai-investment/amp/
Cooling Design · Closed loop liquid cooling
design · Meta Lebanon Data Center Campus (project)
Claim 4560 · Review: Approved · Claim date: 2026-02-11T00:00:00+00:00
- Meta's new data center in Lebanon, Indiana marks milestone AI investment
Meta · Document date: 2026-02-11 · Primary
https://about.fb.com/news/2026/02/metas-new-data-center-lebanon-indiana-marks-milestone-ai-investment/amp/
Clean Energy Matching · 100 percent
forecast · Meta Lebanon Data Center Campus (project)
Claim 4561 · Review: Approved · Claim date: 2026-02-11T00:00:00+00:00
- Meta's new data center in Lebanon, Indiana marks milestone AI investment
Meta · Document date: 2026-02-11 · Primary
https://about.fb.com/news/2026/02/metas-new-data-center-lebanon-indiana-marks-milestone-ai-investment/amp/
Water Restoration Commitment · 100 percent consumed
forecast · Meta Lebanon Data Center Campus (project)
Claim 4562 · Review: Approved · Claim date: 2026-02-11T00:00:00+00:00
- Meta's new data center in Lebanon, Indiana marks milestone AI investment
Meta · Document date: 2026-02-11 · Primary
https://about.fb.com/news/2026/02/metas-new-data-center-lebanon-indiana-marks-milestone-ai-investment/amp/
Arable Restoration Program · 200,000,000 gallon per year
actual · Meta Lebanon Data Center Campus (project)
Claim 4563 · Review: Approved · Claim date: 2026-02-11T00:00:00+00:00
- Meta's new data center in Lebanon, Indiana marks milestone AI investment
Meta · Document date: 2026-02-11 · Primary
https://about.fb.com/news/2026/02/metas-new-data-center-lebanon-indiana-marks-milestone-ai-investment/amp/
Leed Target · LEED Gold
Planned / design or future potential · Meta Lebanon Data Center Campus (project)
Claim 4564 · Review: Approved · Claim date: 2026-02-11T00:00:00+00:00
- Meta's new data center in Lebanon, Indiana marks milestone AI investment
Meta · Document date: 2026-02-11 · Primary
https://about.fb.com/news/2026/02/metas-new-data-center-lebanon-indiana-marks-milestone-ai-investment/amp/
Counterparties and capital
Arable · Utility Provider · CMP-0151
City of Lebanon · Government Authority · CMP-0148
Indiana Economic Development Corporation · Government Authority · CMP-0149
Meta Platforms, Inc. · Owner · CMP-0083
$10,000,000,000 · 2026-02-11
Minimum current campus investment; operator wording is over USD 10B and Reuters reports Meta covering the full investment at outset.
Meta Platforms, Inc. (Sponsor)
Financing record 27; claim-specific source links appear in the exhibit sources where published.
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed. Downloaded snapshots are retained by you; Cartis does not archive them automatically.