Meta Lebanon Data Center Campus

Lebanon; LEAP Lebanon Innovation District, Indiana, United StatesUnder construction
Evidence
Headline capacity
Not established in published records
Updated
Oct 28, 2026
Utility
Arable

Meta broke ground in February 2026 on a multi-phase data center campus in Lebanon, Indiana. The operator and state describe a roughly 1,500-acre, 13-building plan designed to deliver 1 GW once operational, with investment above USD 10 billion.

Capacity

Designed full campus capacity

Planned / design or future potential

1,000 MW

Full campus · Phase

Phase scope; not a whole-site figure

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Historical Project Domino initial planChanged or cancelled

Earlier IEDC framing retained for lineage; not added to current USD 10B-plus total.

Current first construction phaseUnder construction

No phase MW or building allocation disclosed.

Later phasesPlanned

Five later phase slots are not created as records because their individual scopes are undisclosed.

Full campusPlanned

13 buildings

Ten data center buildings plus three support buildings across all phases.

Milestones (3)
IEDC records historical initial plan

Jan 10, 2025 · Recorded actual event

Completed · Announced

Source not linked
Meta announces Lebanon groundbreaking

Feb 11, 2026 · Recorded actual event

Public groundbreaking ceremony documented February 11, 2026. The cited announcements do not establish the exact first earthworks day or operating acceptance.

Completed · Construction started

Source not linked
First capacity online target

2028 · Forecast / planned record

Forecast · Forecast completion

Source not linked

Participants

Meta Platforms, Inc.

Owner

Sources by role
Owner (1)
Owner (1)
Owner (1)
Other participants (3)
Arable

Utility provider

Sources by role
City of Lebanon

Government authority

Sources by role
Government authority (1)
Indiana Economic Development Corporation

Government authority

Sources by role
Government authority (1)

Capital & incentives

Capital claims and financing records may overlap. Their amounts are not added together.

Capital claims

Capital investment

Transaction scope

$>10000000000

Source

Public and utility infrastructure

Transaction scope

$>120000000

Source

Financing records

Investment commitment

$10bn

Feb 11, 2026

Minimum current campus investment; operator wording is over USD 10B and Reuters reports Meta covering the full investment at outset.

Parties & sources

Meta Platforms, Inc. (Sponsor)

Incentives

Sales tax exemption

for 35 years

Approved · Indiana Economic Development Corporation

Minimum USD 1B eligible capital in six years supports 35 years; additional investment milestones can extend by five-year increments up to 50 years.

Site & development

Site area

Reported rounded

1,500 acre

Source

Total building count

Actual

13 building

Full campus · Phase

Source

Data center building count

Actual

10 building

Full campus · Phase

Source

Support building count

Actual

3 building

Full campus · Phase

Source

Gross floor area

Reported rounded

4,000,000 sqft

Source

Construction jobs

Reported rounded

>4000 job

Source

Technical specifications

Cooling design

Design

Closed loop liquid cooling

Source

Clean energy matching

Forecast

100 percent

Source

Water restoration commitment

Forecast

100 percent consumed

Source

Additional project facts

Project status

Actual

Under construction

Source

First online target

Forecast

Late 2027 to early 2028

Current first construction phase · Phase

Source

Operational jobs

Reported rounded

300 job

Source

Arable restoration program

Actual

200,000,000 gallon per year

Source

Leed target

Forecast

LEED Gold

Source

Infrastructure & permits

Technical details (5)
Electric grid

Potential or planned

1,000 MW

full campus power design — 1000 MW; future.

Closed loop cooling

Under construction

closed loop liquid cooling; under construction design.

Utility service

Under construction

public utility upgrades; planned and under development.

Renewable energy supply

Planned or represented

100 percent

clean energy matching — 100 percent; future operational commitment.

Water supply

Planned or represented

200,000,000 gallon per year

offsite water restoration — 200000000 gallon_per_year; program announced.

Public-source research. Plans may change. See Evidence for sources and qualifications.

Related projects (1)
AWS Project Rainier — St. Joseph County Site

Partially operational · New Carlisle area, Indiana, United States

Shared participant: Indiana Economic Development Corporation · Same market: Indiana, United States

Compare in a collection