Cartis diligence evidence schedule

Keppel–DDSP Westwood Taiwan Data Center

PRJ-0044 · Site · A-Top Cloud Data Park, Taoyuan, TAO, Taiwan

Captured 2026-09-06T04:13:42.932Z · Record last updated 2026-08-22

SHA-256: ba87bf61a335e2ea77f9fa5625272498168f87a43f6b40f8c0b647e84b9aabaf

Save a diligence baseline

Download the public evidence as it appears now. Compare a previously saved snapshot to see added, removed and changed claims, counterparties, financing and milestones. Files are read in this browser and are not uploaded.

The fingerprint detects file changes; it is not a digital signature or a claim of independently verified authenticity. Keep your downloaded copy with the transaction file.

Scope and capacity

Keppel Data Centre Fund II and DDSP are developing Westwood, an 80 MW two-phase campus inside A-Top Cloud Data Park in Taoyuan. Phase 1 is about 30 MW, contracted to an undisclosed cloud provider and supported by a June 2026 Nomura financing.

Headline: 80 MW Planned / design

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Claims and exhibit sources

Project Status · Permitted, power secured, contracted and Phase 1 financed

transaction scope · Keppel–DDSP Westwood Taiwan Data Center (project)

Claim 6017 · Review: Approved · Claim date: 2026-06-08T00:00:00+00:00

  1. DDSP Announces Financing Transaction with Nomura for First Phase of 80MW Taiwan Hyperscale Data Centre Campus

    Digital Decarbonization Solutions Platform · Document date: 2026-06-08 · Primary

    https://ddsp.io/news/ddsp-nomura-financing

Total Capacity · 80 MW

Planned / design or future potential · Keppel–DDSP Westwood Taiwan Data Center (project)

Claim 6018 · Review: Approved · Claim date: 2024-10-21T00:00:00+00:00

Headline treatment: Selected headline

  1. A-Top Cloud Data Park Launches International AI R&D Cluster

    Central News Agency Taiwan · Document date: 2025-03-26 · Corroborating

    https://www.cna.com.tw/news/afe/202503260128.aspx
  2. Keppel Positions for AI and Semiconductor Boom with New 80MW Data Centre Campus Project in Taiwan

    Keppel · Document date: 2024-10-21 · Primary

    https://www.keppel.com/media/keppel-positions-for-ai-and-semiconductor-boom-with-new-80mw-data-centre-campus-project-in-taiwan-/
  3. Keppel Announces Partnership with DDSP and New 80MW Data Centre Campus Project in Taiwan

    Digital Decarbonization Solutions Platform · Document date: 2024-10-21 · Corroborating

    https://ddsp.io/news/keppel-ddsp
  4. Connectivity — Portfolio Highlights: Taiwan DC Campus

    Keppel · Document date: Not published · Corroborating

    https://www.keppel.com/fund-management-and-investment/connectivity/

Resilience Design · Tier III-equivalent

design · Keppel–DDSP Westwood Taiwan Data Center (project)

Claim 6019 · Review: Approved · Claim date: 2024-10-21T00:00:00+00:00

  1. Keppel Positions for AI and Semiconductor Boom with New 80MW Data Centre Campus Project in Taiwan

    Keppel · Document date: 2024-10-21 · Primary

    https://www.keppel.com/media/keppel-positions-for-ai-and-semiconductor-boom-with-new-80mw-data-centre-campus-project-in-taiwan-/
  2. Keppel Announces Partnership with DDSP and New 80MW Data Centre Campus Project in Taiwan

    Digital Decarbonization Solutions Platform · Document date: 2024-10-21 · Corroborating

    https://ddsp.io/news/keppel-ddsp

Phase Count · 2 phases

design · Keppel–DDSP Westwood Taiwan Data Center (project)

Claim 6020 · Review: Approved · Claim date: 2024-10-21T00:00:00+00:00

  1. Keppel Positions for AI and Semiconductor Boom with New 80MW Data Centre Campus Project in Taiwan

    Keppel · Document date: 2024-10-21 · Primary

    https://www.keppel.com/media/keppel-positions-for-ai-and-semiconductor-boom-with-new-80mw-data-centre-campus-project-in-taiwan-/
  2. Keppel Announces Partnership with DDSP and New 80MW Data Centre Campus Project in Taiwan

    Digital Decarbonization Solutions Platform · Document date: 2024-10-21 · Corroborating

    https://ddsp.io/news/keppel-ddsp

Phase Capacity · 30 MW

Planned / design or future potential · Phase 1 / first building (phase)

Claim 6021 · Review: Approved · Claim date: 2025-03-26T00:00:00+00:00

Headline treatment: Phase scope; not a whole-site figure

  1. A-Top Cloud Data Park Launches International AI R&D Cluster

    Central News Agency Taiwan · Document date: 2025-03-26 · Primary

    https://www.cna.com.tw/news/afe/202503260128.aspx

Anchor Contract · Long term contract with leading global cloud/hyperscale customer

actual · Phase 1 / first building (phase)

Claim 6022 · Review: Approved · Claim date: 2024-10-21T00:00:00+00:00

  1. DDSP Announces Financing Transaction with Nomura for First Phase of 80MW Taiwan Hyperscale Data Centre Campus

    Digital Decarbonization Solutions Platform · Document date: 2026-06-08 · Corroborating

    https://ddsp.io/news/ddsp-nomura-financing
  2. Keppel Positions for AI and Semiconductor Boom with New 80MW Data Centre Campus Project in Taiwan

    Keppel · Document date: 2024-10-21 · Primary

    https://www.keppel.com/media/keppel-positions-for-ai-and-semiconductor-boom-with-new-80mw-data-centre-campus-project-in-taiwan-/
  3. Keppel Announces Partnership with DDSP and New 80MW Data Centre Campus Project in Taiwan

    Digital Decarbonization Solutions Platform · Document date: 2024-10-21 · Corroborating

    https://ddsp.io/news/keppel-ddsp

Joint Venture Ownership · KDCF II 50%; DDSP 50%

actual · Keppel–DDSP Westwood Taiwan Data Center (project)

Claim 6023 · Review: Approved · Claim date: 2024-10-21T00:00:00+00:00

  1. Keppel Positions for AI and Semiconductor Boom with New 80MW Data Centre Campus Project in Taiwan

    Keppel · Document date: 2024-10-21 · Primary

    https://www.keppel.com/media/keppel-positions-for-ai-and-semiconductor-boom-with-new-80mw-data-centre-campus-project-in-taiwan-/
  2. Keppel Announces Partnership with DDSP and New 80MW Data Centre Campus Project in Taiwan

    Digital Decarbonization Solutions Platform · Document date: 2024-10-21 · Corroborating

    https://ddsp.io/news/keppel-ddsp

Municipality · Taoyuan

reported rounded · Keppel–DDSP Westwood Taiwan Data Center (project)

Claim 6026 · Review: Approved · Claim date: 2025-03-05T00:00:00+00:00

  1. A-Top Cloud Data Park Attracts Singaporean and U.S. Multinational IDC Operators

    Central News Agency Taiwan · Document date: 2025-03-05 · Primary

    https://www.cna.com.tw/news/afe/202503050324.aspx

Parent Data Park · A-Top Cloud Data Park

actual · Keppel–DDSP Westwood Taiwan Data Center (project)

Claim 6027 · Review: Approved · Claim date: 2025-03-26T00:00:00+00:00

  1. A-Top Cloud Data Park Launches International AI R&D Cluster

    Central News Agency Taiwan · Document date: 2025-03-26 · Primary

    https://www.cna.com.tw/news/afe/202503260128.aspx
  2. A-Top Cloud Data Park Attracts Singaporean and U.S. Multinational IDC Operators

    Central News Agency Taiwan · Document date: 2025-03-05 · Corroborating

    https://www.cna.com.tw/news/afe/202503050324.aspx

Financing Status · Nomura financing transaction completed; amount undisclosed

closed financing · Phase 1 / first building (phase)

Claim 6031 · Review: Approved · Claim date: 2026-06-08T00:00:00+00:00

  1. DDSP Announces Financing Transaction with Nomura for First Phase of 80MW Taiwan Hyperscale Data Centre Campus

    Digital Decarbonization Solutions Platform · Document date: 2026-06-08 · Primary

    https://ddsp.io/news/ddsp-nomura-financing

Counterparties and capital

AAM Ruiya Investment Group / A-Top Cloud Data Park · Developer · CMP-0212

Digital Decarbonization Solutions Platform · Developer · CMP-0211

Keppel Data Centre Fund II · Investor · CMP-0210

Keppel Ltd. · Operator · CMP-0209

Nomura · Lender · CMP-0213

Undisclosed Global Cloud Service Provider · Customer · CMP-0214

Debt Financing

Amount not disclosed · 2026-06-08

Nomura financing for Phase 1; amount, tenor, security and borrower undisclosed.

Digital Decarbonization Solutions Platform (Borrower) · Digital Decarbonization Solutions Platform (Developer Financing Recipient Role) · Nomura (Lender)

Financing record 35; claim-specific source links appear in the exhibit sources where published.

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed. Downloaded snapshots are retained by you; Cartis does not archive them automatically.