Cartis diligence evidence schedule
Kasi Lekki Data Center Campus
PRJ-0385 · Site · Maiyegun, Lekki, LA, Nigeria
Record last updated Oct 28, 2026
Scope and capacity
Kasi is developing a carrier-neutral, AI-ready campus in Maiyegun, Lekki. Its first facility has reached commissioning, while the campus's 100 MW figure remains a long-term buildout envelope. Kasi Lekki Data Center Campus is located in Maiyegun, Lekki, LA, NG and is a data center campus in construction status.
Headline: 100 MW Planned / design
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (10)
Site area approximately · 4 hectares
Actual · Kasi Lekki Data Center Campus (Project)
Claim 35567 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Kasi Cloud commissions hyperscale-ready AI-capable campus in Lagos
Nigeria Sovereign Investment Authority · Document date: May 19, 2026 · Corroborating
Source reference: SRC-1981 · Recorded authority: Official primary
Source URL
https://nsia.com.ng/kasi-cloud-datacenters-commissions-west-africas-first-hyperscaleready-ai-capable-data-centre-campus-in-lagos/
https://nsia.com.ng/kasi-cloud-datacenters-commissions-west-africas-first-hyperscaleready-ai-capable-data-centre-campus-in-lagos/
- Kasi Cloud breaks ground in Lagos on new hyperscale data center
Nigeria Sovereign Investment Authority · Document date: Apr 19, 2022 · Primary
Source reference: SRC-1980 · Recorded authority: Official primary
Source URL
https://nsia.com.ng/kasi-cloud-ltd-breaks-ground-in-lagos-nigeria-on-new-hyperscale-data-center/
https://nsia.com.ng/kasi-cloud-ltd-breaks-ground-in-lagos-nigeria-on-new-hyperscale-data-center/
Planned campus capacity · 100 MW
Planned / design or future potential · Kasi Lekki Data Center Campus (Project)
Claim 35569 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
Headline treatment: Selected headline
- Kasi Cloud commissions hyperscale-ready AI-capable campus in Lagos
Nigeria Sovereign Investment Authority · Document date: May 19, 2026 · Primary
Source reference: SRC-1981 · Recorded authority: Official primary
Source URL
https://nsia.com.ng/kasi-cloud-datacenters-commissions-west-africas-first-hyperscaleready-ai-capable-data-centre-campus-in-lagos/
https://nsia.com.ng/kasi-cloud-datacenters-commissions-west-africas-first-hyperscaleready-ai-capable-data-centre-campus-in-lagos/
- Kasi Cloud Datacenters commissions West Africa hyperscale-ready campus
Kasi Cloud / GlobeNewswire · Document date: May 19, 2026 · Corroborating
Source reference: SRC-1982 · Company announcement · Recorded authority: Party primary
Source URL
https://www.globenewswire.com/news-release/2026/05/19/3297917/0/en/kasi-cloud-datacenters-commissions-west-africa-s-first-hyperscale-ready-ai-capable-data-centre-campus-in-lagos.html
https://www.globenewswire.com/news-release/2026/05/19/3297917/0/en/kasi-cloud-datacenters-commissions-west-africa-s-first-hyperscale-ready-ai-capable-data-centre-campus-in-lagos.html
Construction groundbreaking date · 2022-04-19
Actual · Kasi Lekki Data Center Campus (Project)
Claim 35571 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Kasi Cloud breaks ground in Lagos on new hyperscale data center
Nigeria Sovereign Investment Authority · Document date: Apr 19, 2022 · Primary
Source reference: SRC-1980 · Recorded authority: Official primary
Source URL
https://nsia.com.ng/kasi-cloud-ltd-breaks-ground-in-lagos-nigeria-on-new-hyperscale-data-center/
https://nsia.com.ng/kasi-cloud-ltd-breaks-ground-in-lagos-nigeria-on-new-hyperscale-data-center/
Commissioning flag off date · 2026-05-19
Actual · Kasi Lekki Data Center Campus (Project)
Claim 35572 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Kasi Cloud commissions hyperscale-ready AI-capable campus in Lagos
Nigeria Sovereign Investment Authority · Document date: May 19, 2026 · Primary
Source reference: SRC-1981 · Recorded authority: Official primary
Source URL
https://nsia.com.ng/kasi-cloud-datacenters-commissions-west-africas-first-hyperscaleready-ai-capable-data-centre-campus-in-lagos/
https://nsia.com.ng/kasi-cloud-datacenters-commissions-west-africas-first-hyperscaleready-ai-capable-data-centre-campus-in-lagos/
Carrier neutral design · True
Actual · Kasi Lekki Data Center Campus (Project)
Claim 35574 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Kasi Cloud commissions hyperscale-ready AI-capable campus in Lagos
Nigeria Sovereign Investment Authority · Document date: May 19, 2026 · Primary
Source reference: SRC-1981 · Recorded authority: Official primary
Source URL
https://nsia.com.ng/kasi-cloud-datacenters-commissions-west-africas-first-hyperscaleready-ai-capable-data-centre-campus-in-lagos/
https://nsia.com.ng/kasi-cloud-datacenters-commissions-west-africas-first-hyperscaleready-ai-capable-data-centre-campus-in-lagos/
Direct tcn connection voltage · 132 kV
Actual · Kasi Lekki Data Center Campus (Project)
Claim 35575 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Kasi Cloud commissions hyperscale-ready AI-capable campus in Lagos
Nigeria Sovereign Investment Authority · Document date: May 19, 2026 · Primary
Source reference: SRC-1981 · Recorded authority: Official primary
Source URL
https://nsia.com.ng/kasi-cloud-datacenters-commissions-west-africas-first-hyperscaleready-ai-capable-data-centre-campus-in-lagos/
https://nsia.com.ng/kasi-cloud-datacenters-commissions-west-africas-first-hyperscaleready-ai-capable-data-centre-campus-in-lagos/
Hybrid gas solar battery design · True
Actual · Kasi Lekki Data Center Campus (Project)
Claim 35576 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Kasi Cloud commissions hyperscale-ready AI-capable campus in Lagos
Nigeria Sovereign Investment Authority · Document date: May 19, 2026 · Primary
Source reference: SRC-1981 · Recorded authority: Official primary
Source URL
https://nsia.com.ng/kasi-cloud-datacenters-commissions-west-africas-first-hyperscaleready-ai-capable-data-centre-campus-in-lagos/
https://nsia.com.ng/kasi-cloud-datacenters-commissions-west-africas-first-hyperscaleready-ai-capable-data-centre-campus-in-lagos/
PUE target at most · 1.6
Actual · Kasi Lekki Data Center Campus (Project)
Claim 35577 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Nigerian data center operator Kasi opens first phase of 100MW facility
Data Center Dynamics · Document date: May 26, 2026 · Corroborating
Source reference: SRC-1983 · Recorded authority: Secondary
Source URL
https://www.datacenterdynamics.com/en/news/nigerian-data-center-operator-kasi-opens-first-phase-of-100mw-facility/
https://www.datacenterdynamics.com/en/news/nigerian-data-center-operator-kasi-opens-first-phase-of-100mw-facility/
- Kasi Cloud commissions hyperscale-ready AI-capable campus in Lagos
Nigeria Sovereign Investment Authority · Document date: May 19, 2026 · Primary
Source reference: SRC-1981 · Recorded authority: Official primary
Source URL
https://nsia.com.ng/kasi-cloud-datacenters-commissions-west-africas-first-hyperscaleready-ai-capable-data-centre-campus-in-lagos/
https://nsia.com.ng/kasi-cloud-datacenters-commissions-west-africas-first-hyperscaleready-ai-capable-data-centre-campus-in-lagos/
Subsea cable systems adjacent · 6 systems
Actual · Kasi Lekki Data Center Campus (Project)
Claim 35578 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Kasi Cloud commissions hyperscale-ready AI-capable campus in Lagos
Nigeria Sovereign Investment Authority · Document date: May 19, 2026 · Primary
Source reference: SRC-1981 · Recorded authority: Official primary
Source URL
https://nsia.com.ng/kasi-cloud-datacenters-commissions-west-africas-first-hyperscaleready-ai-capable-data-centre-campus-in-lagos/
https://nsia.com.ng/kasi-cloud-datacenters-commissions-west-africas-first-hyperscaleready-ai-capable-data-centre-campus-in-lagos/
Reported campus investment · $250 million
Actual · Kasi Lekki Data Center Campus (Project)
Claim 35579 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Nigerian data center operator Kasi opens first phase of 100MW facility
Data Center Dynamics · Document date: May 26, 2026 · Corroborating
Source reference: SRC-1983 · Recorded authority: Secondary
Source URL
https://www.datacenterdynamics.com/en/news/nigerian-data-center-operator-kasi-opens-first-phase-of-100mw-facility/
https://www.datacenterdynamics.com/en/news/nigerian-data-center-operator-kasi-opens-first-phase-of-100mw-facility/
- Kasi Cloud breaks ground in Lagos on new hyperscale data center
Nigeria Sovereign Investment Authority · Document date: Apr 19, 2022 · Primary
Source reference: SRC-1980 · Recorded authority: Official primary
Source URL
https://nsia.com.ng/kasi-cloud-ltd-breaks-ground-in-lagos-nigeria-on-new-hyperscale-data-center/
https://nsia.com.ng/kasi-cloud-ltd-breaks-ground-in-lagos-nigeria-on-new-hyperscale-data-center/
Counterparties and capital
Kasi Cloud Datacenters · Developer, Operator · CMP-0947
Lagos State Government · Government authority · CMP-0949
Nigeria Sovereign Investment Authority · Investor · CMP-0948
Transmission Company of Nigeria · Utility provider · CMP-0950
$250,000,000 · Apr 19, 2022
Groundbreaking release described a USD 250 million campus; capital structure, draw schedule and current spend remain undisclosed.
Kasi Cloud Datacenters (Developer / investment recipient) · Nigeria Sovereign Investment Authority (Foundational investor)
Sources (2)
Financing record 110; claim-specific source links appear in the exhibit sources where published.
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.