Cartis diligence evidence schedule
Joliet Technology Center
PRJ-1099 · Site · Joliet, Illinois, United States
Record last updated Oct 28, 2026
Scope and capacity
Joliet Technology Center is Hillwood’s proposed 795-acre data-center campus in Joliet, Illinois. Project materials describe a $20 billion, 1.8 GW full-build program over roughly five to seven years, with closed-loop cooling, ComEd service and no planned onsite generation. The city conditionally approved annexation in March 2026, but building permits, utility delivery and construction remain phased. The 1.8 GW figure is a future design objective, not operating capacity.
Headline: 1,800 MW Planned / design
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (12)
Location context · Joliet Technology Center | Joliet | Illinois | US
Actual · Joliet Technology Center (Project)
Claim 70368 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Joliet Technology Center public-record research record
US Data Center Map · Document date: Aug 28, 2026 · Primary
Source reference: SRC-4025 · News report · Recorded authority: Secondary
Source URL
https://dcmap.us/states/illinois/
https://dcmap.us/states/illinois/
Lifecycle status · Proposed
Actual · Joliet Technology Center (Project)
Claim 70369 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Joliet Technology Center public-record research record
US Data Center Map · Document date: Aug 28, 2026 · Primary
Source reference: SRC-4025 · News report · Recorded authority: Secondary
Source URL
https://dcmap.us/states/illinois/
https://dcmap.us/states/illinois/
Reported capacity · 1,800 MW
Planned / design or future potential · Joliet Technology Center (Project)
Claim 70370 · Recorded claim type: Design · Review: Approved · Claim date: Not stated
Headline treatment: Selected headline
- Joliet Technology Center public-record research record
US Data Center Map · Document date: Aug 28, 2026 · Primary
Source reference: SRC-4025 · News report · Recorded authority: Secondary
Source URL
https://dcmap.us/states/illinois/
https://dcmap.us/states/illinois/
Capacity basis · 1,800 MW future full build site capacity; not measured operating IT load.
Actual · Joliet Technology Center (Project)
Claim 70371 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Joliet Technology Center public-record research record
US Data Center Map · Document date: Aug 28, 2026 · Primary
Source reference: SRC-4025 · News report · Recorded authority: Secondary
Source URL
https://dcmap.us/states/illinois/
https://dcmap.us/states/illinois/
Location context · Joliet Technology Center | Joliet | Illinois | US
Actual · Joliet Technology Center (Project)
Claim 74597 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Joliet Technology Center public-record research record
US Data Center Map · Document date: Aug 28, 2026 · Primary
Source reference: SRC-4025 · News report · Recorded authority: Secondary
Source URL
https://dcmap.us/states/illinois/
https://dcmap.us/states/illinois/
Lifecycle status · Proposed
Actual · Joliet Technology Center (Project)
Claim 74598 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Joliet Technology Center public-record research record
US Data Center Map · Document date: Aug 28, 2026 · Primary
Source reference: SRC-4025 · News report · Recorded authority: Secondary
Source URL
https://dcmap.us/states/illinois/
https://dcmap.us/states/illinois/
Reported capacity · 1,800 MW
Planned / design or future potential · Joliet Technology Center (Project)
Claim 74599 · Recorded claim type: Design · Review: Approved · Claim date: Not stated
Headline treatment: Separate claim, not added to the headline
- Joliet Technology Center public-record research record
US Data Center Map · Document date: Aug 28, 2026 · Primary
Source reference: SRC-4025 · News report · Recorded authority: Secondary
Source URL
https://dcmap.us/states/illinois/
https://dcmap.us/states/illinois/
Capacity basis · 1,800 MW is the proposed full build campus design over a multi year development period.
Actual · Joliet Technology Center (Project)
Claim 74600 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Joliet Technology Center public-record research record
US Data Center Map · Document date: Aug 28, 2026 · Primary
Source reference: SRC-4025 · News report · Recorded authority: Secondary
Source URL
https://dcmap.us/states/illinois/
https://dcmap.us/states/illinois/
Site area · 795 acres
Actual · Joliet Technology Center (Project)
Claim 74601 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Joliet Technology Center at a glance
Hillwood · Document date: Aug 28, 2026 · Primary
Source reference: SRC-4259 · Company announcement · Recorded authority: Party primary
Source URL
https://joliettechnologycenter.com/at-a-glance/
https://joliettechnologycenter.com/at-a-glance/
Reported investment · $20,000,000,000
Reported rounded · Joliet Technology Center (Project)
Claim 74602 · Recorded claim type: Reported rounded · Review: Approved · Claim date: Not stated
- Joliet Technology Center at a glance
Hillwood · Document date: Aug 28, 2026 · Primary
Source reference: SRC-4259 · Company announcement · Recorded authority: Party primary
Source URL
https://joliettechnologycenter.com/at-a-glance/
https://joliettechnologycenter.com/at-a-glance/
Buildout duration · 5–7 Years
Actual · Joliet Technology Center (Project)
Claim 74603 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Joliet Technology Center at a glance
Hillwood · Document date: Aug 28, 2026 · Primary
Source reference: SRC-4259 · Company announcement · Recorded authority: Party primary
Source URL
https://joliettechnologycenter.com/at-a-glance/
https://joliettechnologycenter.com/at-a-glance/
Permanent jobs · 700 jobs
Reported rounded · Joliet Technology Center (Project)
Claim 74604 · Recorded claim type: Reported rounded · Review: Approved · Claim date: Not stated
- Joliet Technology Center at a glance
Hillwood · Document date: Aug 28, 2026 · Primary
Source reference: SRC-4259 · Company announcement · Recorded authority: Party primary
Source URL
https://joliettechnologycenter.com/at-a-glance/
https://joliettechnologycenter.com/at-a-glance/
Counterparties and capital
Hillwood Development Company · Developer · CMP-1509