Skip to content

Iron Mountain HYD-1 Hyderabad Data Center

Hyderabad, Telangana, IndiaOperating
Evidence
Planned critical IT
5.7 MW
Updated
Oct 28, 2026

HYD-1 is the existing Hyderabad facility operated within Iron Mountain’s fully acquired Web Werks platform. Current Iron Mountain portfolio material reports 5.6 MW, correcting the prior 5.7 MW value; actual tenant utilization and project-specific financing remain undisclosed. Customer utilization, private contract terms and unreported project financing remain outside the verified public record.

Capacity

Reported capacity

Design

5.7 MW

Source

Reported capacity

Planned / design or future potential

5.6 MW

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Operating facility and documented expansionOperational

HYD-1 is the existing Hyderabad facility operated within Iron Mountain’s fully acquired Web Werks platform. Current Iron Mountain portfolio material reports 5.6 MW, correcting the prior 5.7 MW value; actual tenant utilization and project-specific financing remain undisclosed. Customer utilization, private contract terms and unreported project financing remain outside the verified public record.

Milestones (1)
Project-specific evidence refreshed and reconciled

Aug 29, 2026 · Recorded actual event

Completed · Status changed

Source not linked

Participants

Iron Mountain Data Centers

Developer

Sources by role
Developer (1)

Site & development

Location context

Actual

HYD-1 | Hyderabad | Telangana | IN

Source

Location context

Actual

HYD-1 | Hyderabad | Telangana | IN

Source

Project location

Actual

Hyderabad, Telangana, IN

Source

Technical specifications

Renewable energy matching

Actual

Operator states 100% matched renewable energy where applicable

Source

Additional project facts

Lifecycle status

Actual

Operating

Source

Capacity basis

Actual

Iron Mountain publishes 5.7 MW for the HYD-1 facility record boundary.

Source

Lifecycle status

Actual

Operating

Source

Capacity basis

Actual

Iron Mountain currently reports 5.6 MW for HYD-1, superseding the prior 5.7 MW figure; live utilization is not disclosed.

Source

Operator or developer

Actual

Iron Mountain Data Centers

Source

Current lifecycle

Actual

Operating or in phased operation

Source

Capacity classification

Actual

Design

Source

Capacity basis

Actual

Iron Mountain currently reports 5.6 MW for HYD-1, superseding the prior 5.7 MW figure; live utilization is not disclosed.

Source

Customer utilization

Actual

Not publicly disclosed

Source

Source refresh date

Actual

2026-08-29

Source

Sec capacity comparison

Actual

Q2 2026 leaseable and development schedules reviewed

Source

Infrastructure & permits

Technical details (3)
Electric grid

Operational

5.6 MW

Iron Mountain currently reports 5.6 MW for HYD-1, superseding the prior 5.7 MW figure; live utilization is not disclosed.

Fiber

Operational

Tier III facility with diverse feeds, N+1 power, N+2 cooling, on-site substation infrastructure and carrier-neutral connectivity.

Cooling system

Operational

Cooling and resilience architecture is described at facility or campus level; instantaneous draw and tenant utilization remain undisclosed.

Public-source research. Plans may change. See Evidence for sources and qualifications.

Related projects (2)
AirTrunk HYD1 Campus

Proposed · Hyderabad, Telangana, India

Same locality: Hyderabad

Compare in a collection
Microsoft India South Central Cloud Region

Status under review · Hyderabad, Telangana, India

Same locality: Hyderabad

Compare in a collection