Hut 8 Beacon Point AI Data Center Campus

Texas, United StatesUnder construction
Capacity
704 MW
Contracted
Lead participant
Hut 8
Developer
Last updated
Aug 27, 2026
Most recent public record update

About Hut 8 Beacon Point AI Data Center Campus

Hut 8 is developing Beacon Point in Nueces County as a two-phase AI campus. Two 15-year leases now cover a combined 704 MW of critical IT load within approximately 1,000 MW of utility capacity. Hut 8, American Electric Power, Jacobs is associated with the development in Nueces County, TX, US. The disclosed development scope includes 704 MW contracted critical IT across two phases; approximately 1,000 MW utility capacity; Phase 1 financed with $4.25 billion of secured notes; Phase 2 initial delivery expected Q2 2028. Power and physical infrastructure include aEP Texas interconnection supports two approximately 500 MW utility phases and purpose-built AI factories. Two executed tenant leases cover a combined 704 MW of critical IT capacity at Beacon Point. Beacon Point Phase 1 is financed with $4.25 billion of senior secured notes; the two leases have an aggregate stated base-term value of about $19.6 billion.

Capacity

Contracted
Operating capacityAn operating IT-capacity figure has not been publicly disclosed.
Contracted Supply352 MWActual · Hut 8 Beacon Point AI Data Center Campus
Contracted Supply704 MWActual · Hut 8 Beacon Point AI Data Center Campus

Development

1 phases · 2 milestones
Construction programUnder Construction

Project-wide phase for Hut 8 Beacon Point AI Data Center Campus; capacity class is contracted supply.

May 6, 2026
Beacon Point Nueces County development disclosed
Completed
Two 352 MW phases fully contracted; Phase 1 under construction and Phase 2 scheduled for delivery from Q2 2028
Forecast

Infrastructure

Electric GridPlanned Or Represented

704 MW

Two executed tenant leases cover a combined 704 MW of critical IT capacity at Beacon Point.

Site FacilityPlanned Or Represented

AEP Texas interconnection supports two approximately 500 MW utility phases and purpose-built AI factories.

Project map

0 of 1 project point mapped
Infrastructure facts
2
Mapped records
1
Capacity figures
1

No map point available

Power & interconnection: 1Site systems: 1

Facts & sources

Published claims and their source links.

12 facts
Location Context
Beacon Point campus | Nueces County | Texas
Actual
Lifecycle Status
Construction
Actual
Reported Capacity
352 MW
Actual
Capacity Basis
A 15-year tenant lease covers 352 MW of critical IT capacity.
Actual
Location Context
Beacon Point campus | Nueces County | Texas
Actual
Lifecycle Status
Construction
Actual
Reported Capacity
704 MW
Actual
Capacity Basis
Two executed tenant leases cover a combined 704 MW of critical IT capacity at Beacon Point.
Actual
Development Scale
704 MW contracted critical IT across two phases
Actual
Development Milestone
Approximately 1,000 MW utility capacity
Actual
Power Arrangement
Phase 1 financed with $4.25 billion of secured notes
Actual
Site Configuration
Phase 2 initial delivery expected Q2 2028.
Actual