Green Mountain SVG-Undheim Data Center Campus

PRJ-0797 · Site · Undheim, Rogaland, Norway

Record last updated Oct 28, 2026

Scope and capacity

Green Mountain SVG-Undheim Data Center Campus, also known as Green Mountain SVG-Undheim, is a data center project in Undheim, Rogaland, NO associated with Green Mountain. Two interconnected buildings; 80 MW total IT capacity; 100 MW maximum site capacity; completion scheduled for 2028. Single-tenant AI and HPC campus with renewable hydropower, air and liquid cooling, and heat-reuse design. 80 MW is the source-defined future IT or site design envelope.

Headline: 80 MW Planned critical IT

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Location context · Green Mountain SVG-Undheim | Undheim | Rogaland | NO

Actual · Green Mountain SVG-Undheim Data Center Campus (Project)

Claim 61060 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Green Mountain Green Mountain SVG-Undheim profile

    Green Mountain · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-3362 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://greenmountain.no/data-center/svg-undheim/

Lifecycle status · Construction

Actual · Green Mountain SVG-Undheim Data Center Campus (Project)

Claim 61061 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Green Mountain Green Mountain SVG-Undheim profile

    Green Mountain · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-3362 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://greenmountain.no/data-center/svg-undheim/

Reported capacity · 80 MW

Design · Green Mountain SVG-Undheim Data Center Campus (Project)

Claim 61062 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Selected headline

  1. Green Mountain Green Mountain SVG-Undheim profile

    Green Mountain · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-3362 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://greenmountain.no/data-center/svg-undheim/

Capacity basis · Green Mountain publishes 80 MW of critical IT capacity for this record boundary.

Actual · Green Mountain SVG-Undheim Data Center Campus (Project)

Claim 61063 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Green Mountain Green Mountain SVG-Undheim profile

    Green Mountain · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-3362 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://greenmountain.no/data-center/svg-undheim/

Location context · Green Mountain SVG-Undheim | Undheim | Rogaland | NO

Actual · Green Mountain SVG-Undheim Data Center Campus (Project)

Claim 101032 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Green Mountain Green Mountain SVG-Undheim profile

    Green Mountain · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-3362 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://greenmountain.no/data-center/svg-undheim/

Lifecycle status · Construction

Actual · Green Mountain SVG-Undheim Data Center Campus (Project)

Claim 101033 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Green Mountain Green Mountain SVG-Undheim profile

    Green Mountain · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-3362 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://greenmountain.no/data-center/svg-undheim/

Reported capacity · 80 MW

Planned / design or future potential · Green Mountain SVG-Undheim Data Center Campus (Project)

Claim 101034 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

Headline treatment: Separate claim, not added to the headline

  1. Green Mountain Green Mountain SVG-Undheim profile

    Green Mountain · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-3362 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://greenmountain.no/data-center/svg-undheim/

Capacity basis · 80 MW is the source defined future IT or site design envelope.

Actual · Green Mountain SVG-Undheim Data Center Campus (Project)

Claim 101035 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Green Mountain Green Mountain SVG-Undheim profile

    Green Mountain · Document date: Aug 27, 2026 · Primary

    Source reference: SRC-3362 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://greenmountain.no/data-center/svg-undheim/

Building count · 2 buildings

Design · Green Mountain SVG-Undheim Data Center Campus (Project)

Claim 101038 · Recorded claim type: Design · Review: Approved · Claim date: Not stated

  1. Undheim data-center project information

    Green Mountain · Document date: Aug 30, 2026 · Primary

    Source reference: SRC-5608 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://info.greenmountain.no/datasenter-pa-undheim/

Scheduled completion · 2028

Forecast · Green Mountain SVG-Undheim Data Center Campus (Project)

Claim 101039 · Recorded claim type: Forecast · Review: Approved · Claim date: Not stated

  1. Undheim data-center project information

    Green Mountain · Document date: Aug 30, 2026 · Primary

    Source reference: SRC-5608 · Fact sheet · Recorded authority: Official primary

    Source URL

    https://info.greenmountain.no/datasenter-pa-undheim/

Counterparties and capital

Green Mountain · Developer · CMP-1230