Skip to content
← Return to profile

Cartis diligence evidence schedule

Google The Dalles Former Smelter Campus

PRJ-0121 · Site · The Dalles / former aluminum smelter site, Oregon, United States

Record last updated Oct 28, 2026

Scope and capacity

Google's third The Dalles campus redevelops former aluminum-smelter land with two planned buildings and new water and sewer infrastructure. Google The Dalles Former Smelter Campus is in The Dalles / former aluminum smelter site, OR, US and is a data center campus with partially operational status.

Headline: Not established in published records

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Building completion year · 2025

Actual · Smelter campus building 1 (Phase)

Claim 13795 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. As Google's water demands grow, The Dalles aims to pull more from Mount Hood forest

    Oregon Public Broadcasting · Document date: Jan 15, 2026 · Corroborating

    Source reference: SRC-0826 · News report · Recorded authority: Secondary

    Source URL

    https://www.opb.org/article/2026/01/15/as-googles-water-demands-grow-the-dalles-aims-to-pull-more-from-mount-hood-forest/

  2. Google and The Dalles complete water storage system

    Google · Document date: Oct 22, 2025 · Corroborating

    Source reference: SRC-0825 · Company announcement · Recorded authority: Party primary

    Source URL

    https://blog.google/company-news/outreach-and-initiatives/sustainability/the-dalles-oregon-water/

  3. The Dalles OKs Google data centers despite water worries

    KGW · Document date: Nov 9, 2021 · Corroborating

    Source reference: SRC-0829 · News report · Recorded authority: Secondary

    Source URL

    https://www.kgw.com/article/money/business/dalles-approves-google-data-centers-water-worries/283-622d713f-8db5-426d-a815-3ca66eaf0cab

  4. The Dalles, Oregon — Google Data Center Location

    Google · Document date: Not stated · Corroborating

    Source reference: SRC-0822 · Company announcement · Recorded authority: Party primary

    Source URL

    https://datacenters.google/locations/oregon/

  5. Google Data Centers in The Dalles

    City of The Dalles · Document date: Not stated · Primary

    Source reference: SRC-0823 · Government record · Recorded authority: Official primary

    Source URL

    https://www.thedalles.gov/business/google_data_centers/index.php

  6. Enterprise Zone and Strategic Investment Program Agreements with Google

    City of The Dalles · Document date: Not stated · Corroborating

    Source reference: SRC-0824 · Government record · Recorded authority: Official primary

    Source URL

    https://www.thedalles.gov/business/google_data_centers/ezandsipagreements.php

Sip building scope · 2 data center buildings

Source report · Google The Dalles Former Smelter Campus (Project)

Claim 13797 · Recorded claim type: Not stated · Review: Approved · Claim date: Not stated

  1. Enterprise Zone and Strategic Investment Program Agreements with Google

    City of The Dalles · Document date: Not stated · Primary

    Source reference: SRC-0824 · Government record · Recorded authority: Official primary

    Source URL

    https://www.thedalles.gov/business/google_data_centers/ezandsipagreements.php

Sip tax abatement term · 15 years

Actual · Google The Dalles Former Smelter Campus (Project)

Claim 13798 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. Enterprise Zone and Strategic Investment Program Agreements with Google

    City of The Dalles · Document date: Not stated · Primary

    Source reference: SRC-0824 · Government record · Recorded authority: Official primary

    Source URL

    https://www.thedalles.gov/business/google_data_centers/ezandsipagreements.php

Public asr capacity added · 100 million gallons per year

Source report · Google The Dalles Former Smelter Campus (Project)

Claim 13801 · Recorded claim type: Not stated · Review: Approved · Claim date: Oct 22, 2025

  1. Google and The Dalles complete water storage system

    Google · Document date: Oct 22, 2025 · Primary

    Source reference: SRC-0825 · Company announcement · Recorded authority: Party primary

    Source URL

    https://blog.google/company-news/outreach-and-initiatives/sustainability/the-dalles-oregon-water/

Ownership transfer · Transferred to city with associated groundwater rights

Actual · Google The Dalles Former Smelter Campus (Project)

Claim 13802 · Recorded claim type: Actual · Review: Approved · Claim date: Oct 22, 2025

  1. Google and The Dalles complete water storage system

    Google · Document date: Oct 22, 2025 · Primary

    Source reference: SRC-0825 · Company announcement · Recorded authority: Party primary

    Source URL

    https://blog.google/company-news/outreach-and-initiatives/sustainability/the-dalles-oregon-water/

Counterparties and capital

City of The Dalles · Government authority · CMP-0446

Design, LLC · Owner · CMP-0449

Google · Developer · CMP-0112

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.