Data center siteSite record

Google The Dalles Former Smelter Campus

The Dalles / former aluminum smelter site, Oregon, United StatesPartially operational
Capacity
No public figure
Lead participant
Google
Developer
Last updated
Aug 24, 2026
Most recent public record update

About Google The Dalles Former Smelter Campus

Google's third The Dalles campus redevelops former aluminum-smelter land with two planned buildings and new water and sewer infrastructure. Google The Dalles Former Smelter Campus is in The Dalles / former aluminum smelter site, OR, US and is a data center campus with partially operational status. Participants include Google LLC as developer, Design, LLC as owner. Development comprises Smelter campus building 1 (operational), Smelter campus building 2 (construction). Key milestones include First third-site building completed. (2025-12-31) and Second third-site building expected to complete. (2026-12-31). municipal water sewer and asr — 100 million_gallons_per_year: New water/sewer infrastructure plus ASR system and associated rights transferred to city; capacity is public-system benefit, not consumption. Incentives include strategic investment program (active) for 2021 SIP for up to two data centers with taxable portion, community service fee and GAP payments.

Program relationships

1 linked

Capacity

Operating capacityAn operating IT-capacity figure has not been publicly disclosed.

No additional capacity claims are published.

Development

2 phases · 4 milestones
Smelter campus building 1Operational

City/OPB report completion; exact service date remains open.

1 building

Smelter campus building 2Under Construction

Forecast pending primary completion confirmation.

1 building

Nov 1, 2021
SIP agreement established for up to two data centers
Completed
Oct 22, 2025
ASR and associated water rights transferred to city
Completed
Dec 31, 2025
First third-site building completed
Completed
Dec 31, 2026
Second third-site building expected to complete
Forecast

Infrastructure

Utility ServiceOperational

100 million gallons per year

New water/sewer infrastructure plus ASR system and associated rights transferred to city; capacity is public-system benefit, not consumption.

Project map

0 of 1 project point mapped
Infrastructure facts
1
Mapped records
1
Capacity figures
1

No map point available

Power & interconnection: 1

Facts & sources

Published claims and their source links.

5 facts
Building Completion Year
2025
Actual
Sip Building Scope
2 data center buildings
Fact
Sip Tax Abatement Term
15 years
Actual
Public Asr Capacity Added
100 million gallons per year
Fact
Ownership Transfer
Transferred to city with associated groundwater rights
Actual