Cartis diligence evidence schedule
Google Mayes County / Pryor Data Center
PRJ-0419 · Site · Pryor / MidAmerica Industrial Park, Oklahoma, United States
Record last updated Oct 28, 2026
Scope and capacity
Google's Mayes County campus has operated since 2011 and is again expanding under a wider Oklahoma investment program. Google Mayes County / Pryor Data Center is located in Pryor / MidAmerica Industrial Park, OK, US and is a data center campus in partially operational status.
Headline: Not established in published records
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (23)
Current status · Operating campus with active expansion
Actual · Google Mayes County / Pryor Data Center (Project)
Claim 39615 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Google is investing in infrastructure and an AI-ready workforce in Oklahoma
Google · Document date: Aug 13, 2025 · Corroborating
Source reference: SRC-2213 · Company announcement · Recorded authority: Party primary
Source URL
https://blog.google/company-news/inside-google/company-announcements/google-american-innovation-oklahoma/
https://blog.google/company-news/inside-google/company-announcements/google-american-innovation-oklahoma/
- Oklahoma data center location
Google Data Centers · Document date: Not stated · Primary
Source reference: SRC-2212 · Recorded authority: Party primary
Source URL
https://datacenters.google/locations/oklahoma/
https://datacenters.google/locations/oklahoma/
Campus announced year · 2007
Reported rounded · Google Mayes County / Pryor Data Center (Project)
Claim 39616 · Recorded claim type: Reported rounded · Review: Approved · Claim date: Not stated
- Oklahoma data center location
Google Data Centers · Document date: Not stated · Primary
Source reference: SRC-2212 · Recorded authority: Party primary
Source URL
https://datacenters.google/locations/oklahoma/
https://datacenters.google/locations/oklahoma/
Initial opening year · 2011
Reported rounded · Google Mayes County / Pryor Data Center (Project)
Claim 39617 · Recorded claim type: Reported rounded · Review: Approved · Claim date: Not stated
- Google data center opens in Pryor
The Journal Record · Document date: Sep 29, 2011 · Corroborating
Source reference: SRC-2219 · Recorded authority: Secondary
Source URL
https://journalrecord.com/2011/09/29/google-data-center-opens-in-pryor-real-estate/
https://journalrecord.com/2011/09/29/google-data-center-opens-in-pryor-real-estate/
- Oklahoma data center location
Google Data Centers · Document date: Not stated · Primary
Source reference: SRC-2212 · Recorded authority: Party primary
Source URL
https://datacenters.google/locations/oklahoma/
https://datacenters.google/locations/oklahoma/
Initial floor area · 130,000 square feet
Reported rounded · Google Mayes County / Pryor Data Center (Project)
Claim 39618 · Recorded claim type: Reported rounded · Review: Approved · Claim date: Not stated
- Google data center opens in Pryor
The Journal Record · Document date: Sep 29, 2011 · Primary
Source reference: SRC-2219 · Recorded authority: Secondary
Source URL
https://journalrecord.com/2011/09/29/google-data-center-opens-in-pryor-real-estate/
https://journalrecord.com/2011/09/29/google-data-center-opens-in-pryor-real-estate/
Initial investment · $600 million
Reported rounded · Google Mayes County / Pryor Data Center (Project)
Claim 39619 · Recorded claim type: Reported rounded · Review: Approved · Claim date: Not stated
- Google data center opens in Pryor
The Journal Record · Document date: Sep 29, 2011 · Primary
Source reference: SRC-2219 · Recorded authority: Secondary
Source URL
https://journalrecord.com/2011/09/29/google-data-center-opens-in-pryor-real-estate/
https://journalrecord.com/2011/09/29/google-data-center-opens-in-pryor-real-estate/
Initial employees · 106 employees
Reported rounded · Google Mayes County / Pryor Data Center (Project)
Claim 39620 · Recorded claim type: Reported rounded · Review: Approved · Claim date: Not stated
- Google data center opens in Pryor
The Journal Record · Document date: Sep 29, 2011 · Primary
Source reference: SRC-2219 · Recorded authority: Secondary
Source URL
https://journalrecord.com/2011/09/29/google-data-center-opens-in-pryor-real-estate/
https://journalrecord.com/2011/09/29/google-data-center-opens-in-pryor-real-estate/
Initial site area · 200 acres
Reported rounded · Google Mayes County / Pryor Data Center (Project)
Claim 39621 · Recorded claim type: Reported rounded · Review: Approved · Claim date: Not stated
- Google data center opens in Pryor
The Journal Record · Document date: Sep 29, 2011 · Primary
Source reference: SRC-2219 · Recorded authority: Secondary
Source URL
https://journalrecord.com/2011/09/29/google-data-center-opens-in-pryor-real-estate/
https://journalrecord.com/2011/09/29/google-data-center-opens-in-pryor-real-estate/
Expansion year · 2012
Reported rounded · Google Mayes County / Pryor Data Center (Project)
Claim 39622 · Recorded claim type: Reported rounded · Review: Approved · Claim date: Not stated
- Oklahoma data center location
Google Data Centers · Document date: Not stated · Primary
Source reference: SRC-2212 · Recorded authority: Party primary
Source URL
https://datacenters.google/locations/oklahoma/
https://datacenters.google/locations/oklahoma/
Expansion year · 2015
Reported rounded · Google Mayes County / Pryor Data Center (Project)
Claim 39623 · Recorded claim type: Reported rounded · Review: Approved · Claim date: Not stated
- Oklahoma data center location
Google Data Centers · Document date: Not stated · Primary
Source reference: SRC-2212 · Recorded authority: Party primary
Source URL
https://datacenters.google/locations/oklahoma/
https://datacenters.google/locations/oklahoma/
Facility opening year · 2016
Reported rounded · Google Mayes County / Pryor Data Center (Project)
Claim 39624 · Recorded claim type: Reported rounded · Review: Approved · Claim date: Not stated
- New Google facility opening brings Oklahoma investment to USD2 billion
Oklahoma Department of Commerce · Document date: Oct 13, 2016 · Primary
Source reference: SRC-2218 · Government record · Recorded authority: Official primary
Source URL
https://www.okcommerce.gov/new-google-facility-opening-brings-its-oklahoma-investment-to-2-billion/
https://www.okcommerce.gov/new-google-facility-opening-brings-its-oklahoma-investment-to-2-billion/
Cumulative investment 2016 · $2 billion
Reported rounded · Google Mayes County / Pryor Data Center (Project)
Claim 39625 · Recorded claim type: Reported rounded · Review: Approved · Claim date: Not stated
- New Google facility opening brings Oklahoma investment to USD2 billion
Oklahoma Department of Commerce · Document date: Oct 13, 2016 · Primary
Source reference: SRC-2218 · Government record · Recorded authority: Official primary
Source URL
https://www.okcommerce.gov/new-google-facility-opening-brings-its-oklahoma-investment-to-2-billion/
https://www.okcommerce.gov/new-google-facility-opening-brings-its-oklahoma-investment-to-2-billion/
2018 expansion investment · $600 million
Reported rounded · Google Mayes County / Pryor Data Center (Project)
Claim 39626 · Recorded claim type: Reported rounded · Review: Approved · Claim date: Not stated
- Google announces USD600 million expansion of Oklahoma data center
Oklahoma Department of Commerce · Document date: Feb 16, 2018 · Primary
Source reference: SRC-2216 · Government record · Recorded authority: Official primary
Source URL
https://www.okcommerce.gov/google-announces-expansion-of-oklahoma-data-center/
https://www.okcommerce.gov/google-announces-expansion-of-oklahoma-data-center/
2018 expansion form · Four story building
Actual · Google Mayes County / Pryor Data Center (Project)
Claim 39627 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Google announces USD600 million expansion of Oklahoma data center
Oklahoma Department of Commerce · Document date: Feb 16, 2018 · Primary
Source reference: SRC-2216 · Government record · Recorded authority: Official primary
Source URL
https://www.okcommerce.gov/google-announces-expansion-of-oklahoma-data-center/
https://www.okcommerce.gov/google-announces-expansion-of-oklahoma-data-center/
Cumulative investment 2018 · $2.50 billion plus
Reported rounded · Google Mayes County / Pryor Data Center (Project)
Claim 39628 · Recorded claim type: Reported rounded · Review: Approved · Claim date: Not stated
- Google announces USD600 million expansion of Oklahoma data center
Oklahoma Department of Commerce · Document date: Feb 16, 2018 · Primary
Source reference: SRC-2216 · Government record · Recorded authority: Official primary
Source URL
https://www.okcommerce.gov/google-announces-expansion-of-oklahoma-data-center/
https://www.okcommerce.gov/google-announces-expansion-of-oklahoma-data-center/
Jobs 2018 · 400 jobs plus
Reported rounded · Google Mayes County / Pryor Data Center (Project)
Claim 39629 · Recorded claim type: Reported rounded · Review: Approved · Claim date: Not stated
- Google announces USD600 million expansion of Oklahoma data center
Oklahoma Department of Commerce · Document date: Feb 16, 2018 · Primary
Source reference: SRC-2216 · Government record · Recorded authority: Official primary
Source URL
https://www.okcommerce.gov/google-announces-expansion-of-oklahoma-data-center/
https://www.okcommerce.gov/google-announces-expansion-of-oklahoma-data-center/
2019 expansion investment · $600 million
Reported rounded · Google Mayes County / Pryor Data Center (Project)
Claim 39630 · Recorded claim type: Reported rounded · Review: Approved · Claim date: Not stated
- Google investment in Pryor reaches USD3 billion
Oklahoma Department of Commerce · Document date: Jun 24, 2019 · Primary
Source reference: SRC-2217 · Government record · Recorded authority: Official primary
Source URL
https://www.okcommerce.gov/google-investment-in-pryor-okla-reaches-3-billion/
https://www.okcommerce.gov/google-investment-in-pryor-okla-reaches-3-billion/
Cumulative investment 2019 · $3 billion
Reported rounded · Google Mayes County / Pryor Data Center (Project)
Claim 39631 · Recorded claim type: Reported rounded · Review: Approved · Claim date: Not stated
- Google investment in Pryor reaches USD3 billion
Oklahoma Department of Commerce · Document date: Jun 24, 2019 · Primary
Source reference: SRC-2217 · Government record · Recorded authority: Official primary
Source URL
https://www.okcommerce.gov/google-investment-in-pryor-okla-reaches-3-billion/
https://www.okcommerce.gov/google-investment-in-pryor-okla-reaches-3-billion/
Expected jobs 2019 · 500 jobs plus
Reported rounded · Google Mayes County / Pryor Data Center (Project)
Claim 39632 · Recorded claim type: Reported rounded · Review: Approved · Claim date: Not stated
- Google investment in Pryor reaches USD3 billion
Oklahoma Department of Commerce · Document date: Jun 24, 2019 · Primary
Source reference: SRC-2217 · Government record · Recorded authority: Official primary
Source URL
https://www.okcommerce.gov/google-investment-in-pryor-okla-reaches-3-billion/
https://www.okcommerce.gov/google-investment-in-pryor-okla-reaches-3-billion/
Site area owned 2019 · 800 acres approximately
Reported rounded · Google Mayes County / Pryor Data Center (Project)
Claim 39633 · Recorded claim type: Reported rounded · Review: Approved · Claim date: Not stated
- Google planning another expansion for Pryor data center
Oklahoma Department of Commerce · Document date: Feb 22, 2019 · Primary
Source reference: SRC-2220 · Government record · Recorded authority: Official primary
Source URL
https://www.okcommerce.gov/google-planning-another-expansion-for-pryor-data-center/
https://www.okcommerce.gov/google-planning-another-expansion-for-pryor-data-center/
2025 expansion included · True
Actual · Google Mayes County / Pryor Data Center (Project)
Claim 39634 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Google is investing in infrastructure and an AI-ready workforce in Oklahoma
Google · Document date: Aug 13, 2025 · Primary
Source reference: SRC-2213 · Company announcement · Recorded authority: Party primary
Source URL
https://blog.google/company-news/inside-google/company-announcements/google-american-innovation-oklahoma/
https://blog.google/company-news/inside-google/company-announcements/google-american-innovation-oklahoma/
Oklahoma solar agreements · 700 MW generation plus
Reported rounded · Google Mayes County / Pryor Data Center (Project)
Claim 39637 · Recorded claim type: Reported rounded · Review: Approved · Claim date: Not stated
- Google is supporting new solar projects in Oklahoma
Google · Document date: Jan 16, 2025 · Primary
Source reference: SRC-2214 · Recorded authority: Party primary
Source URL
https://blog.google/feed/solar-energy-oklahoma/
https://blog.google/feed/solar-energy-oklahoma/
Campus IT capacity disclosed · False
Actual · Google Mayes County / Pryor Data Center (Project)
Claim 39640 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Google is investing in infrastructure and an AI-ready workforce in Oklahoma
Google · Document date: Aug 13, 2025 · Corroborating
Source reference: SRC-2213 · Company announcement · Recorded authority: Party primary
Source URL
https://blog.google/company-news/inside-google/company-announcements/google-american-innovation-oklahoma/
https://blog.google/company-news/inside-google/company-announcements/google-american-innovation-oklahoma/
- Oklahoma data center location
Google Data Centers · Document date: Not stated · Primary
Source reference: SRC-2212 · Recorded authority: Party primary
Source URL
https://datacenters.google/locations/oklahoma/
https://datacenters.google/locations/oklahoma/
Owner operator · Google
Actual · Google Mayes County / Pryor Data Center (Project)
Claim 39641 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Oklahoma data center location
Google Data Centers · Document date: Not stated · Primary
Source reference: SRC-2212 · Recorded authority: Party primary
Source URL
https://datacenters.google/locations/oklahoma/
https://datacenters.google/locations/oklahoma/
Counterparties and capital
Google · Operator, Owner · CMP-0112
Leeward Renewable Energy · Developer · CMP-1037
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.