Google Mayes County / Pryor Data Center

Pryor / MidAmerica Industrial Park, Oklahoma, United StatesPartially operational
Evidence
Headline capacity
Not established in published records
Updated
Oct 28, 2026

Google's Mayes County campus has operated since 2011 and is again expanding under a wider Oklahoma investment program. Google Mayes County / Pryor Data Center is located in Pryor / MidAmerica Industrial Park, OK, US and is a data center campus in partially operational status.

Capacity

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Initial Mayes County facilityOperational

1 building

Initial 130,000-square-foot facility on a then-200-acre site.

2012-2016 expansion cycleOperational

Campus expansions occurred in 2012 and 2015; a new facility opened in 2016. Exact current building geometry is unresolved.

2018-2019 expansion cycleOperational

Four-story building and later USD600 million expansion; no current site MW disclosed.

2025 Pryor expansionUnder construction

Part of a USD9 billion Oklahoma program also covering Stillwater and workforce initiatives; Pryor allocation undisclosed.

Milestones (8)
Google identifies 2007 as the Mayes County start milestone

2007 · Recorded actual event

Completed · Announced

Source not linked
Initial Pryor data center opens

Sep 29, 2011 · Recorded actual event

Completed · Event type not stated

Source not linked
Google timeline records a 2012 expansion

2012 · Recorded actual event

Completed · Event type not stated

Source not linked
Google timeline records a 2015 expansion

2015 · Recorded actual event

Completed · Event type not stated

Source not linked
New Pryor facility lifts cumulative investment to USD2 billion

Oct 13, 2016 · Recorded actual event

Completed · Event type not stated

Source not linked
Google announces a USD600 million four-story expansion

Feb 16, 2018 · Recorded actual event

Completed · Announced

Source not linked
Pryor cumulative investment reaches USD3 billion

Jun 24, 2019 · Recorded actual event

Completed · Announced

Source not linked
Google includes Pryor expansion in its two-year Oklahoma program

Aug 13, 2025 · Recorded actual event

Completed · Announced

Source not linked

Participants

Google

Operator · Owner

Sources by role
Operator / Owner (1)
Owner (1)
Leeward Renewable Energy

Developer

Sources by role
Developer (1)

Capital & incentives

Capital claims

Initial investment

Reported rounded

$600 million

Source

Cumulative investment 2016

Reported rounded

$2 billion

Source

2018 expansion investment

Reported rounded

$600 million

Source

Cumulative investment 2018

Reported rounded

$2.50 billion plus

Source

2019 expansion investment

Reported rounded

$600 million

Source

Cumulative investment 2019

Reported rounded

$3 billion

Source

Site & development

Initial floor area

Reported rounded

130,000 square feet

Source

Initial site area

Reported rounded

200 acres

Source

Site area owned 2019

Reported rounded

800 acres approximately

Source

Additional project facts

Current status

Actual

Operating campus with active expansion

Source

Campus announced year

Reported rounded

2007

Source

Initial opening year

Reported rounded

2011

Source

Initial employees

Reported rounded

106 employees

Source

Expansion year

Reported rounded

2012

Source

Expansion year

Reported rounded

2015

Source

Facility opening year

Reported rounded

2016

Source

2018 expansion form

Actual

Four story building

Source

Jobs 2018

Reported rounded

400 jobs plus

Source

Expected jobs 2019

Reported rounded

500 jobs plus

Source

2025 expansion included

Actual

True

Source

Oklahoma solar agreements

Reported rounded

700 MW generation plus

Source

Campus IT capacity disclosed

Actual

False

Source

Owner operator

Actual

Google

Source

Infrastructure & permits

Technical details (2)
Renewable energy supply

Secured or contracted

700 MW generation plus

Oklahoma solar agreements include a portfolio near Pryor but are not campus IT load.

Water supply

Operational

1.4 billion gallons target

Seven-year statewide replenishment target; not an onsite water connection.

Public-source research. Plans may change. See Evidence for sources and qualifications.