Google Mayes County / Pryor Data Center
- Headline capacity
- Not established in published records
- Updated
- Oct 28, 2026
Google's Mayes County campus has operated since 2011 and is again expanding under a wider Oklahoma investment program. Google Mayes County / Pryor Data Center is located in Pryor / MidAmerica Industrial Park, OK, US and is a data center campus in partially operational status.
Capacity
Operating IT capacity: Not established in published records
A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.
Development
1 building
Initial 130,000-square-foot facility on a then-200-acre site.
Campus expansions occurred in 2012 and 2015; a new facility opened in 2016. Exact current building geometry is unresolved.
Four-story building and later USD600 million expansion; no current site MW disclosed.
Part of a USD9 billion Oklahoma program also covering Stillwater and workforce initiatives; Pryor allocation undisclosed.
Milestones (8)
2007 · Recorded actual event
Completed · Announced
Source not linkedSep 29, 2011 · Recorded actual event
Completed · Event type not stated
Source not linked2012 · Recorded actual event
Completed · Event type not stated
Source not linked2015 · Recorded actual event
Completed · Event type not stated
Source not linkedOct 13, 2016 · Recorded actual event
Completed · Event type not stated
Source not linkedFeb 16, 2018 · Recorded actual event
Completed · Announced
Source not linkedJun 24, 2019 · Recorded actual event
Completed · Announced
Source not linkedAug 13, 2025 · Recorded actual event
Completed · Announced
Source not linkedParticipants
Operator · Owner
Sources by role
Operator / Owner (1)
- Oklahoma data center location · Primary
Owner (1)
- Google investment in Pryor reaches USD3 billion · Jun 24, 2019 · Corroborating
Developer
Sources by role
Developer (1)
- Google is supporting new solar projects in Oklahoma · Jan 16, 2025 · Primary
Capital & incentives
Capital claims
Site & development
Additional project facts
Infrastructure & permits
Technical details (2)
Secured or contracted
700 MW generation plus
Oklahoma solar agreements include a portfolio near Pryor but are not campus IT load.
Operational
1.4 billion gallons target
Seven-year statewide replenishment target; not an onsite water connection.
Project map
Public-source research. Plans may change. See Evidence for sources and qualifications.