Captured 2026-09-06T04:12:18.168Z · Record last updated 2026-06-04

SHA-256: c2ca89f5269240c0c7b4e22459f6b089df38f6084fffe6b7bf93e275755a3493

Save a diligence baseline

Download the public evidence as it appears now. Compare a previously saved snapshot to see added, removed and changed claims, counterparties, financing and milestones. Files are read in this browser and are not uploaded.

The fingerprint detects file changes; it is not a digital signature or a claim of independently verified authenticity. Keep your downloaded copy with the transaction file.

Scope and capacity

Meitner is a Google data center under construction beside more than 1 GW of wind, solar and battery storage developed with Intersect in the Texas Panhandle. It uses air cooling and a minority share of on-site gas firming.

Headline:

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Claims and exhibit sources

Construction Announcement · 2026-06-04

actual · Google–Intersect Meitner Energy Center (project)

Claim AST-B2-021 · Review: Approved · Claim date: 2026-06-04

  1. Google and Intersect to build Meitner Energy Center in Texas

    Google · Document date: 2026-06-04 · Supports

    https://blog.google/innovation-and-ai/infrastructure-and-cloud/global-network/meitner-energy-center/

Co Located Clean Energy · 1+ GW

aggregate nameplate context · Google–Intersect Meitner Energy Center (project)

Claim AST-B2-022 · Review: Approved · Claim date: 2026-06-04

  1. Google and Intersect deepen Texas roots

    Intersect · Document date: 2026-06-04 · Supports

    https://www.intersect.com/news/google-and-intersect-deepen-texas-roots-with-new-data-center-and-energy-investments-in-gray-and-roberts-counties

Cooling System · Air cooling system

design · Google–Intersect Meitner Energy Center (project)

Claim AST-B2-023 · Review: Approved · Claim date: 2026-06-04

  1. Google and Intersect deepen Texas roots

    Intersect · Document date: 2026-06-04 · Supports

    https://www.intersect.com/news/google-and-intersect-deepen-texas-roots-with-new-data-center-and-energy-investments-in-gray-and-roberts-counties

Process Water Use · Domestic uses only scope

design company reported · Google–Intersect Meitner Energy Center (project)

Claim AST-B2-024 · Review: Approved · Claim date: 2026-06-04

  1. Google and Intersect deepen Texas roots

    Intersect · Document date: 2026-06-04 · Supports

    https://www.intersect.com/news/google-and-intersect-deepen-texas-roots-with-new-data-center-and-energy-investments-in-gray-and-roberts-counties

Day One Clean Energy Share · Majority share

planned · Google–Intersect Meitner Energy Center (project)

Claim AST-B2-025 · Review: Approved With Followup · Claim date: 2026-06-04

  1. Google and Intersect deepen Texas roots

    Intersect · Document date: 2026-06-04 · Supports

    https://www.intersect.com/news/google-and-intersect-deepen-texas-roots-with-new-data-center-and-energy-investments-in-gray-and-roberts-counties

On Site Gas Share · Minority share

planned firming · Google–Intersect Meitner Energy Center (project)

Claim AST-B2-026 · Review: Approved With Followup · Claim date: 2026-06-04

  1. Google and Intersect deepen Texas roots

    Intersect · Document date: 2026-06-04 · Supports

    https://www.intersect.com/news/google-and-intersect-deepen-texas-roots-with-new-data-center-and-energy-investments-in-gray-and-roberts-counties

Workforce Hub Area · 800 acres

planned · Google–Intersect Meitner Energy Center (project)

Claim AST-B2-027 · Review: Approved · Claim date: 2026-06-04

  1. Google and Intersect deepen Texas roots

    Intersect · Document date: 2026-06-04 · Supports

    https://www.intersect.com/news/google-and-intersect-deepen-texas-roots-with-new-data-center-and-energy-investments-in-gray-and-roberts-counties

Workforce Hub Capacity · 3,500 workers

planned · Google–Intersect Meitner Energy Center (project)

Claim AST-B2-028 · Review: Approved · Claim date: 2026-06-04

  1. Google and Intersect deepen Texas roots

    Intersect · Document date: 2026-06-04 · Supports

    https://www.intersect.com/news/google-and-intersect-deepen-texas-roots-with-new-data-center-and-energy-investments-in-gray-and-roberts-counties

Texas Water Fund · $10,000,000

company program not project capex · Google–Intersect Meitner Energy Center (project)

Claim AST-B2-029 · Review: Approved · Claim date: 2026-06-04

  1. Google and Intersect deepen Texas roots

    Intersect · Document date: 2026-06-04 · Supports

    https://www.intersect.com/news/google-and-intersect-deepen-texas-roots-with-new-data-center-and-energy-investments-in-gray-and-roberts-counties

Google Texas Investment Program · $40,000,000,000

statewide program context · Google–Intersect Meitner Energy Center (project)

Claim AST-B2-030 · Review: Approved · Claim date: 2025-11-14

  1. Google announces new $40 billion investment in Texas

    Google · Document date: 2025-11-14 · Supports

    https://blog.google/company-news/inside-google/company-announcements/google-american-innovation-texas/

Counterparties and capital

Google · Data Center Owner Operator And Offtaker · CMP-0112

Intersect · Energy And Site Developer

Gray County · Host Jurisdiction

Roberts County · Host Jurisdiction

Google Texas Investment Program

$40,000,000,000 · 2025-11-14

Financing record legacy-financing-AST-B2-030; claim-specific source links appear in the exhibit sources where published.

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed. Downloaded snapshots are retained by you; Cartis does not archive them automatically.