Global Switch Madrid 2
PRJ-1001 · Site · Madrid, Community of Madrid, Spain
Record last updated Oct 28, 2026
Scope and capacity
Global Switch Madrid 2 is now under construction beside Madrid 1. Its 56 MW figure is a future full-build boundary, with first service targeted for 2029 and full completion targeted for 2032. Tenant utilization, contract pricing and undisclosed project financing remain outside the verified public record.
Headline: 56 MW Planned critical IT
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (18)
Location context · Global Switch Madrid 2 | Madrid | Community of Madrid | ES
Actual · Global Switch Madrid 2 (Project)
Claim 67276 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Global Switch Madrid 2 official profile
Global Switch · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3822 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.globalswitch.com/data-centres/madrid/
https://www.globalswitch.com/data-centres/madrid/
Lifecycle status · Preconstruction
Actual · Global Switch Madrid 2 (Project)
Claim 67277 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Global Switch Madrid 2 official profile
Global Switch · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3822 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.globalswitch.com/data-centres/madrid/
https://www.globalswitch.com/data-centres/madrid/
Reported capacity · 56 MW
Design · Global Switch Madrid 2 (Project)
Claim 67278 · Recorded claim type: Design · Review: Approved · Claim date: Not stated
Headline treatment: Selected headline
- Global Switch Madrid 2 official profile
Global Switch · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3822 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.globalswitch.com/data-centres/madrid/
https://www.globalswitch.com/data-centres/madrid/
Capacity basis · Global Switch publishes 56 MW for this project boundary.
Actual · Global Switch Madrid 2 (Project)
Claim 67279 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Global Switch Madrid 2 official profile
Global Switch · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3822 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.globalswitch.com/data-centres/madrid/
https://www.globalswitch.com/data-centres/madrid/
Location context · Global Switch Madrid 2 | Madrid | Community of Madrid | ES
Actual · Global Switch Madrid 2 (Project)
Claim 84844 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Global Switch Madrid 2 official profile
Global Switch · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3822 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.globalswitch.com/data-centres/madrid/
https://www.globalswitch.com/data-centres/madrid/
Lifecycle status · Construction
Actual · Global Switch Madrid 2 (Project)
Claim 84845 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Global Switch Madrid 2 official profile
Global Switch · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3822 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.globalswitch.com/data-centres/madrid/
https://www.globalswitch.com/data-centres/madrid/
Reported capacity · 56 MW
Planned / design or future potential · Global Switch Madrid 2 (Project)
Claim 84846 · Recorded claim type: Design · Review: Approved · Claim date: Not stated
Headline treatment: Separate claim, not added to the headline
- Global Switch Madrid 2 official profile
Global Switch · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3822 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.globalswitch.com/data-centres/madrid/
https://www.globalswitch.com/data-centres/madrid/
Capacity basis · 56 MW is the published future facility or full build IT boundary; it is not operating load.
Actual · Global Switch Madrid 2 (Project)
Claim 84847 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Global Switch Madrid 2 official profile
Global Switch · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3822 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.globalswitch.com/data-centres/madrid/
https://www.globalswitch.com/data-centres/madrid/
Operator confirmed · Global Switch
Actual · Global Switch Madrid 2 (Project)
Claim 84848 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Global Switch Madrid 2 official profile
Global Switch · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3822 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.globalswitch.com/data-centres/madrid/
https://www.globalswitch.com/data-centres/madrid/
Project location · Madrid, Community of Madrid, ES
Actual · Global Switch Madrid 2 (Project)
Claim 84849 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Global Switch Madrid 2 official profile
Global Switch · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3822 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.globalswitch.com/data-centres/madrid/
https://www.globalswitch.com/data-centres/madrid/
Current lifecycle · Under development
Actual · Global Switch Madrid 2 (Project)
Claim 84850 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Global Switch Madrid 2 official profile
Global Switch · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3822 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.globalswitch.com/data-centres/madrid/
https://www.globalswitch.com/data-centres/madrid/
Capacity classification · Future potential
Actual · Global Switch Madrid 2 (Project)
Claim 84851 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Global Switch Madrid 2 official profile
Global Switch · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3822 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.globalswitch.com/data-centres/madrid/
https://www.globalswitch.com/data-centres/madrid/
Capacity basis · 56 MW is the published future facility or full build IT boundary; it is not operating load.
Actual · Global Switch Madrid 2 (Project)
Claim 84852 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Global Switch Madrid 2 official profile
Global Switch · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3822 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.globalswitch.com/data-centres/madrid/
https://www.globalswitch.com/data-centres/madrid/
Customer utilization · Not publicly disclosed
Actual · Global Switch Madrid 2 (Project)
Claim 84853 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Global Switch Madrid 2 official profile
Global Switch · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3822 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.globalswitch.com/data-centres/madrid/
https://www.globalswitch.com/data-centres/madrid/
Identity boundary · This facility or named campus is tracked separately from adjacent buildings and broader operator portfolios
Actual · Global Switch Madrid 2 (Project)
Claim 84854 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Global Switch breaks ground on Madrid 2
Data Center Dynamics · Document date: Jun 18, 2026 · Primary
Source reference: SRC-4772 · News report · Recorded authority: Secondary
Source URL
https://www.datacenterdynamics.com/en/news/global-switch-breaks-ground-on-second-madrid-data-center/
https://www.datacenterdynamics.com/en/news/global-switch-breaks-ground-on-second-madrid-data-center/
Source refresh date · 2026-08-29
Actual · Global Switch Madrid 2 (Project)
Claim 84855 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Global Switch Madrid 2 official profile
Global Switch · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3822 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.globalswitch.com/data-centres/madrid/
https://www.globalswitch.com/data-centres/madrid/
Ready for service target · 2029
Forecast · Global Switch Madrid 2 (Project)
Claim 84857 · Recorded claim type: Forecast · Review: Approved · Claim date: Not stated
- Global Switch breaks ground on Madrid 2
Data Center Dynamics · Document date: Jun 18, 2026 · Primary
Source reference: SRC-4772 · News report · Recorded authority: Secondary
Source URL
https://www.datacenterdynamics.com/en/news/global-switch-breaks-ground-on-second-madrid-data-center/
https://www.datacenterdynamics.com/en/news/global-switch-breaks-ground-on-second-madrid-data-center/
Full completion target · 2032
Forecast · Global Switch Madrid 2 (Project)
Claim 84858 · Recorded claim type: Forecast · Review: Approved · Claim date: Not stated
- Global Switch breaks ground on Madrid 2
Data Center Dynamics · Document date: Jun 18, 2026 · Primary
Source reference: SRC-4772 · News report · Recorded authority: Secondary
Source URL
https://www.datacenterdynamics.com/en/news/global-switch-breaks-ground-on-second-madrid-data-center/
https://www.datacenterdynamics.com/en/news/global-switch-breaks-ground-on-second-madrid-data-center/
Counterparties and capital
Global Switch · Developer · CMP-1484
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.