Scope and capacity
Global Switch Madrid 1 is the existing 14 MW operating facility. The adjacent 56 MW Madrid 2 construction program remains a separate project and does not change Madrid 1’s identity or capacity. Tenant utilization, contract pricing and undisclosed project financing remain outside the verified public record.
Headline: 14 MW Planned critical IT
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (17)
Location context · Global Switch Madrid 1 | Madrid | Community of Madrid | ES
Actual · Global Switch Madrid 1 (Project)
Claim 67324 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Global Switch Madrid 1 official profile
Global Switch · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3837 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.globalswitch.com/data-centres/madrid/
https://www.globalswitch.com/data-centres/madrid/
Lifecycle status · Operating
Actual · Global Switch Madrid 1 (Project)
Claim 67325 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Global Switch Madrid 1 official profile
Global Switch · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3837 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.globalswitch.com/data-centres/madrid/
https://www.globalswitch.com/data-centres/madrid/
Reported capacity · 14 MW
Design · Global Switch Madrid 1 (Project)
Claim 67326 · Recorded claim type: Design · Review: Approved · Claim date: Not stated
Headline treatment: Selected headline
- Global Switch Madrid 1 official profile
Global Switch · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3837 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.globalswitch.com/data-centres/madrid/
https://www.globalswitch.com/data-centres/madrid/
Capacity basis · Global Switch publishes 14 MW for this project boundary.
Actual · Global Switch Madrid 1 (Project)
Claim 67327 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Global Switch Madrid 1 official profile
Global Switch · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3837 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.globalswitch.com/data-centres/madrid/
https://www.globalswitch.com/data-centres/madrid/
Location context · Global Switch Madrid 1 | Madrid | Community of Madrid | ES
Actual · Global Switch Madrid 1 (Project)
Claim 85014 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Global Switch Madrid 1 official profile
Global Switch · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3837 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.globalswitch.com/data-centres/madrid/
https://www.globalswitch.com/data-centres/madrid/
Lifecycle status · Operating
Actual · Global Switch Madrid 1 (Project)
Claim 85015 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Global Switch Madrid 1 official profile
Global Switch · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3837 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.globalswitch.com/data-centres/madrid/
https://www.globalswitch.com/data-centres/madrid/
Reported capacity · 14 MW
Design · Global Switch Madrid 1 (Project)
Claim 85016 · Recorded claim type: Design · Review: Approved · Claim date: Not stated
Headline treatment: Separate claim, not added to the headline
- Global Switch Madrid 1 official profile
Global Switch · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3837 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.globalswitch.com/data-centres/madrid/
https://www.globalswitch.com/data-centres/madrid/
Capacity basis · 14 MW is the operator published facility IT-load boundary; it is not measured customer utilization.
Actual · Global Switch Madrid 1 (Project)
Claim 85017 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Global Switch Madrid 1 official profile
Global Switch · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3837 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.globalswitch.com/data-centres/madrid/
https://www.globalswitch.com/data-centres/madrid/
Operator confirmed · Global Switch
Actual · Global Switch Madrid 1 (Project)
Claim 85018 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Global Switch Madrid 1 official profile
Global Switch · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3837 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.globalswitch.com/data-centres/madrid/
https://www.globalswitch.com/data-centres/madrid/
Project location · Madrid, Community of Madrid, ES
Actual · Global Switch Madrid 1 (Project)
Claim 85019 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Global Switch Madrid 1 official profile
Global Switch · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3837 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.globalswitch.com/data-centres/madrid/
https://www.globalswitch.com/data-centres/madrid/
Current lifecycle · Operating
Actual · Global Switch Madrid 1 (Project)
Claim 85020 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Global Switch Madrid 1 official profile
Global Switch · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3837 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.globalswitch.com/data-centres/madrid/
https://www.globalswitch.com/data-centres/madrid/
Capacity classification · It load
Actual · Global Switch Madrid 1 (Project)
Claim 85021 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Global Switch Madrid 1 official profile
Global Switch · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3837 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.globalswitch.com/data-centres/madrid/
https://www.globalswitch.com/data-centres/madrid/
Capacity basis · 14 MW is the operator published facility IT-load boundary; it is not measured customer utilization.
Actual · Global Switch Madrid 1 (Project)
Claim 85022 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Global Switch Madrid 1 official profile
Global Switch · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3837 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.globalswitch.com/data-centres/madrid/
https://www.globalswitch.com/data-centres/madrid/
Customer utilization · Not publicly disclosed
Actual · Global Switch Madrid 1 (Project)
Claim 85023 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Global Switch Madrid 1 official profile
Global Switch · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3837 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.globalswitch.com/data-centres/madrid/
https://www.globalswitch.com/data-centres/madrid/
Identity boundary · This facility or named campus is tracked separately from adjacent buildings and broader operator portfolios
Actual · Global Switch Madrid 1 (Project)
Claim 85024 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Global Switch breaks ground on Madrid 2
Data Center Dynamics · Document date: Jun 18, 2026 · Primary
Source reference: SRC-4787 · News report · Recorded authority: Secondary
Source URL
https://www.datacenterdynamics.com/en/news/global-switch-breaks-ground-on-second-madrid-data-center/
https://www.datacenterdynamics.com/en/news/global-switch-breaks-ground-on-second-madrid-data-center/
Source refresh date · 2026-08-29
Actual · Global Switch Madrid 1 (Project)
Claim 85025 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Global Switch Madrid 1 official profile
Global Switch · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3837 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.globalswitch.com/data-centres/madrid/
https://www.globalswitch.com/data-centres/madrid/
Campus role · Operating first Madrid building
Actual · Global Switch Madrid 1 (Project)
Claim 85027 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Global Switch Madrid 1 official profile
Global Switch · Document date: Aug 28, 2026 · Primary
Source reference: SRC-3837 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.globalswitch.com/data-centres/madrid/
https://www.globalswitch.com/data-centres/madrid/
Counterparties and capital
Global Switch · Developer · CMP-1484
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.