Cartis diligence evidence schedule
Galaxy Selene AI Data Center Campus
PRJ-0672 · Site · Texas, United States
Record last updated Oct 28, 2026
Scope and capacity
Galaxy acquired the Texas site it calls Selene for AI and high-performance-computing development. Company reporting identifies approximately 900 MW of potential capacity, subject to ERCOT interconnection. Galaxy Digital is associated with the development in Undisclosed Texas county, TX, US. The disclosed development scope includes acquired Texas site; approximately 900 MW potential; ERCOT interconnection condition outstanding. Power and physical infrastructure include power remains subject to the ERCOT interconnection process. Galaxy states approximately 900 MW of potential capacity, subject to ERCOT interconnection.
Headline: 900 MW Planned / design
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (12)
Location context · Galaxy Selene site | Texas | precise boundary undisclosed
Actual · Galaxy Selene AI Data Center Campus (Project)
Claim 57118 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Galaxy Q2 2026 financial results
Galaxy Digital · Document date: Aug 6, 2026 · Primary
Source reference: SRC-3102 · Fact sheet · Recorded authority: Party primary
Source URL
https://www.prnewswire.com/news-releases/galaxy-announces-second-quarter-2026-financial-results-302843529.html
https://www.prnewswire.com/news-releases/galaxy-announces-second-quarter-2026-financial-results-302843529.html
Lifecycle status · Preconstruction
Actual · Galaxy Selene AI Data Center Campus (Project)
Claim 57119 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Galaxy Q2 2026 financial results
Galaxy Digital · Document date: Aug 6, 2026 · Primary
Source reference: SRC-3102 · Fact sheet · Recorded authority: Party primary
Source URL
https://www.prnewswire.com/news-releases/galaxy-announces-second-quarter-2026-financial-results-302843529.html
https://www.prnewswire.com/news-releases/galaxy-announces-second-quarter-2026-financial-results-302843529.html
Reported capacity · 900 MW
Planned / design or future potential · Galaxy Selene AI Data Center Campus (Project)
Claim 57120 · Recorded claim type: Design · Review: Approved · Claim date: Not stated
Headline treatment: Separate claim, not added to the headline
- Galaxy Q2 2026 financial results
Galaxy Digital · Document date: Aug 6, 2026 · Primary
Source reference: SRC-3102 · Fact sheet · Recorded authority: Party primary
Source URL
https://www.prnewswire.com/news-releases/galaxy-announces-second-quarter-2026-financial-results-302843529.html
https://www.prnewswire.com/news-releases/galaxy-announces-second-quarter-2026-financial-results-302843529.html
Capacity basis · Galaxy states approximately 900 MW of potential capacity, subject to ERCOT interconnection.
Actual · Galaxy Selene AI Data Center Campus (Project)
Claim 57121 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Galaxy Q2 2026 financial results
Galaxy Digital · Document date: Aug 6, 2026 · Primary
Source reference: SRC-3102 · Fact sheet · Recorded authority: Party primary
Source URL
https://www.prnewswire.com/news-releases/galaxy-announces-second-quarter-2026-financial-results-302843529.html
https://www.prnewswire.com/news-releases/galaxy-announces-second-quarter-2026-financial-results-302843529.html
Location context · Galaxy Selene site | Texas | precise boundary undisclosed
Actual · Galaxy Selene AI Data Center Campus (Project)
Claim 111131 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Galaxy Q2 2026 financial results
Galaxy Digital · Document date: Aug 6, 2026 · Primary
Source reference: SRC-3102 · Fact sheet · Recorded authority: Party primary
Source URL
https://www.prnewswire.com/news-releases/galaxy-announces-second-quarter-2026-financial-results-302843529.html
https://www.prnewswire.com/news-releases/galaxy-announces-second-quarter-2026-financial-results-302843529.html
Lifecycle status · Preconstruction
Actual · Galaxy Selene AI Data Center Campus (Project)
Claim 111132 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Galaxy Q2 2026 financial results
Galaxy Digital · Document date: Aug 6, 2026 · Primary
Source reference: SRC-3102 · Fact sheet · Recorded authority: Party primary
Source URL
https://www.prnewswire.com/news-releases/galaxy-announces-second-quarter-2026-financial-results-302843529.html
https://www.prnewswire.com/news-releases/galaxy-announces-second-quarter-2026-financial-results-302843529.html
Reported capacity · 900 MW
Planned / design or future potential · Galaxy Selene AI Data Center Campus (Project)
Claim 111133 · Recorded claim type: Design · Review: Approved · Claim date: Not stated
Headline treatment: Selected headline
- Galaxy Q2 2026 financial results
Galaxy Digital · Document date: Aug 6, 2026 · Primary
Source reference: SRC-3102 · Fact sheet · Recorded authority: Party primary
Source URL
https://www.prnewswire.com/news-releases/galaxy-announces-second-quarter-2026-financial-results-302843529.html
https://www.prnewswire.com/news-releases/galaxy-announces-second-quarter-2026-financial-results-302843529.html
Capacity basis · Galaxy states approximately 900 MW of potential capacity, subject to ERCOT interconnection.
Actual · Galaxy Selene AI Data Center Campus (Project)
Claim 111134 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Galaxy Q2 2026 financial results
Galaxy Digital · Document date: Aug 6, 2026 · Primary
Source reference: SRC-3102 · Fact sheet · Recorded authority: Party primary
Source URL
https://www.prnewswire.com/news-releases/galaxy-announces-second-quarter-2026-financial-results-302843529.html
https://www.prnewswire.com/news-releases/galaxy-announces-second-quarter-2026-financial-results-302843529.html
Development scale · Acquired Texas site
Actual · Galaxy Selene AI Data Center Campus (Project)
Claim 111151 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Galaxy Q2 2026 financial results
Galaxy Digital · Document date: Aug 6, 2026 · Primary
Source reference: SRC-3102 · Fact sheet · Recorded authority: Party primary
Source URL
https://www.prnewswire.com/news-releases/galaxy-announces-second-quarter-2026-financial-results-302843529.html
https://www.prnewswire.com/news-releases/galaxy-announces-second-quarter-2026-financial-results-302843529.html
- Galaxy Q2 2026 Form 8-K and exhibits
Galaxy Digital · Document date: Aug 5, 2026 · Corroborating
Source reference: SRC-6189 · Regulatory record · Recorded authority: Official primary
Source URL
https://investor.galaxy.com/static-files/746675fd-4fa9-4c90-9421-81944d9d6377
https://investor.galaxy.com/static-files/746675fd-4fa9-4c90-9421-81944d9d6377
Development milestone · Approximately 900 MW potential
Actual · Galaxy Selene AI Data Center Campus (Project)
Claim 111152 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Galaxy Q2 2026 financial results
Galaxy Digital · Document date: Aug 6, 2026 · Primary
Source reference: SRC-3102 · Fact sheet · Recorded authority: Party primary
Source URL
https://www.prnewswire.com/news-releases/galaxy-announces-second-quarter-2026-financial-results-302843529.html
https://www.prnewswire.com/news-releases/galaxy-announces-second-quarter-2026-financial-results-302843529.html
- Galaxy Q2 2026 Form 8-K and exhibits
Galaxy Digital · Document date: Aug 5, 2026 · Corroborating
Source reference: SRC-6189 · Regulatory record · Recorded authority: Official primary
Source URL
https://investor.galaxy.com/static-files/746675fd-4fa9-4c90-9421-81944d9d6377
https://investor.galaxy.com/static-files/746675fd-4fa9-4c90-9421-81944d9d6377
Power arrangement · ERCOT interconnection condition outstanding.
Actual · Galaxy Selene AI Data Center Campus (Project)
Claim 111153 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Galaxy Q2 2026 financial results
Galaxy Digital · Document date: Aug 6, 2026 · Primary
Source reference: SRC-3102 · Fact sheet · Recorded authority: Party primary
Source URL
https://www.prnewswire.com/news-releases/galaxy-announces-second-quarter-2026-financial-results-302843529.html
https://www.prnewswire.com/news-releases/galaxy-announces-second-quarter-2026-financial-results-302843529.html
- Galaxy Q2 2026 Form 8-K and exhibits
Galaxy Digital · Document date: Aug 5, 2026 · Corroborating
Source reference: SRC-6189 · Regulatory record · Recorded authority: Official primary
Source URL
https://investor.galaxy.com/static-files/746675fd-4fa9-4c90-9421-81944d9d6377
https://investor.galaxy.com/static-files/746675fd-4fa9-4c90-9421-81944d9d6377
Site configuration · Galaxy Selene site | Texas | precise boundary undisclosed
Actual · Galaxy Selene AI Data Center Campus (Project)
Claim 111154 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Galaxy Q2 2026 financial results
Galaxy Digital · Document date: Aug 6, 2026 · Primary
Source reference: SRC-3102 · Fact sheet · Recorded authority: Party primary
Source URL
https://www.prnewswire.com/news-releases/galaxy-announces-second-quarter-2026-financial-results-302843529.html
https://www.prnewswire.com/news-releases/galaxy-announces-second-quarter-2026-financial-results-302843529.html
- Galaxy Q2 2026 Form 8-K and exhibits
Galaxy Digital · Document date: Aug 5, 2026 · Corroborating
Source reference: SRC-6189 · Regulatory record · Recorded authority: Official primary
Source URL
https://investor.galaxy.com/static-files/746675fd-4fa9-4c90-9421-81944d9d6377
https://investor.galaxy.com/static-files/746675fd-4fa9-4c90-9421-81944d9d6377
Counterparties and capital
Galaxy Digital · Developer · CMP-0381
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.