Galaxy Selene AI Data Center Campus

Texas, United StatesPreconstruction
Evidence
Planned / design
900 MW
Updated
Oct 28, 2026

Galaxy acquired the Texas site it calls Selene for AI and high-performance-computing development. Company reporting identifies approximately 900 MW of potential capacity, subject to ERCOT interconnection. Galaxy Digital is associated with the development in Undisclosed Texas county, TX, US. The disclosed development scope includes acquired Texas site; approximately 900 MW potential; ERCOT interconnection condition outstanding. Power and physical infrastructure include power remains subject to the ERCOT interconnection process. Galaxy states approximately 900 MW of potential capacity, subject to ERCOT interconnection.

Capacity

Reported capacity

Planned / design or future potential

900 MW

Source

Reported capacity

Planned / design or future potential

900 MW

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Development programAnnounced or preconstruction

Project-wide phase for Galaxy Selene AI Data Center Campus; capacity class is future potential.

Milestones (2)
Galaxy Selene Texas development disclosed

Aug 6, 2026 · Recorded actual event

Completed · Announced

Source not linked
Texas site acquired; interconnection process pending

Date not disclosed · Forecast / planned record

Forecast · Forecast completion

Source not linked

Participants

Galaxy Digital

Developer

Sources by role
Developer (1)

Site & development

Location context

Actual

Galaxy Selene site | Texas | precise boundary undisclosed

Source

Location context

Actual

Galaxy Selene site | Texas | precise boundary undisclosed

Source

Development scale

Actual

Acquired Texas site

Source

Development milestone

Actual

Approximately 900 MW potential

Source

Site configuration

Actual

Galaxy Selene site | Texas | precise boundary undisclosed

Source

Technical specifications

Power arrangement

Actual

ERCOT interconnection condition outstanding.

Source

Additional project facts

Lifecycle status

Actual

Preconstruction

Source

Capacity basis

Actual

Galaxy states approximately 900 MW of potential capacity, subject to ERCOT interconnection.

Source

Lifecycle status

Actual

Preconstruction

Source

Capacity basis

Actual

Galaxy states approximately 900 MW of potential capacity, subject to ERCOT interconnection.

Source

Infrastructure & permits

Technical details (2)
Electric grid

Planned or represented

900 MW

Galaxy states approximately 900 MW of potential capacity, subject to ERCOT interconnection.

Site facility

Planned or represented

Power remains subject to the ERCOT interconnection process.

Public-source research. Plans may change. See Evidence for sources and qualifications.

Related projects (3)
Galaxy Caspian AI Data Center Campus

Preconstruction · Texas, United States

Shared participant: Galaxy Digital · Same market: Texas, United States

Compare in a collection
Galaxy Helios Data Center Campus

Partially operational · Dickens County, Texas, United States

Shared participant: Galaxy Digital · Same market: Texas, United States

Compare in a collection
Galaxy Merlin AI Data Center Campus

Preconstruction · McGregor, Texas, United States

Shared participant: Galaxy Digital · Same market: Texas, United States

Compare in a collection