Cartis diligence evidence schedule

G42 UAE–US AI Campus

PRJ-0591 · Site · Abu Dhabi, United Arab Emirates

Record last updated Oct 28, 2026

Scope and capacity

G42 is leading a consortium developing a planned 5 GW AI campus in Abu Dhabi across roughly ten square miles. The first phase is planned at 1 GW, with U.S. technology companies expected to operate facilities and nuclear, solar and gas resources proposed for supply. The campus remains a development program rather than an operating 5 GW facility.

Headline: 5,000 MW Planned / design

The 5 GW figure describes the full host-campus envelope. The planned Stargate cluster sits within it and must not be added to that figure.

Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.

Location context · Abu Dhabi, United Arab Emirates

Actual · G42 UAE–US AI Campus (Project)

Claim 53950 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. G42 to Lead Consortium of US Partners to Build 5GW UAE–US AI Campus

    G42 · Document date: Not stated · Primary

    Source reference: SRC-2918 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.g42.ai/resources/news/g42-lead-consortium-us-partners-build-5gw-uae-us-ai-campus

Lifecycle status · Preconstruction

Actual · G42 UAE–US AI Campus (Project)

Claim 53951 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. G42 to Lead Consortium of US Partners to Build 5GW UAE–US AI Campus

    G42 · Document date: Not stated · Primary

    Source reference: SRC-2918 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.g42.ai/resources/news/g42-lead-consortium-us-partners-build-5gw-uae-us-ai-campus

Reported capacity · 5,000 MW

Planned / design or future potential · G42 UAE–US AI Campus (Project)

Claim 53952 · Recorded claim type: Proposal · Review: Approved · Claim date: Not stated

Headline treatment: Separate claim, not added to the headline

  1. G42 to Lead Consortium of US Partners to Build 5GW UAE–US AI Campus

    G42 · Document date: Not stated · Primary

    Source reference: SRC-2918 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.g42.ai/resources/news/g42-lead-consortium-us-partners-build-5gw-uae-us-ai-campus

Capacity basis · Planned full build campus envelope

Actual · G42 UAE–US AI Campus (Project)

Claim 53953 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. G42 to Lead Consortium of US Partners to Build 5GW UAE–US AI Campus

    G42 · Document date: Not stated · Primary

    Source reference: SRC-2918 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.g42.ai/resources/news/g42-lead-consortium-us-partners-build-5gw-uae-us-ai-campus

Project identity · G42 UAE–US AI Campus

Actual · G42 UAE–US AI Campus (Project)

Claim 119494 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. UAE and U.S. presidents attend unveiling of Phase 1 of new 5 GW AI campus

    U.S. Department of Commerce · Document date: May 15, 2025 · Corroborating

    Source reference: SRC-6525 · Government record · Recorded authority: Official primary

    Source URL

    https://www.commerce.gov/news/press-releases/2025/05/uae-and-us-presidents-attend-unveiling-phase-1-new-5gw-ai-campus-abu

  2. G42 to Lead Consortium of US Partners to Build 5GW UAE–US AI Campus

    G42 · Document date: Not stated · Primary

    Source reference: SRC-2918 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.g42.ai/resources/news/g42-lead-consortium-us-partners-build-5gw-uae-us-ai-campus

Lifecycle status · Development program

Actual · G42 UAE–US AI Campus (Project)

Claim 119495 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. UAE and U.S. presidents attend unveiling of Phase 1 of new 5 GW AI campus

    U.S. Department of Commerce · Document date: May 15, 2025 · Corroborating

    Source reference: SRC-6525 · Government record · Recorded authority: Official primary

    Source URL

    https://www.commerce.gov/news/press-releases/2025/05/uae-and-us-presidents-attend-unveiling-phase-1-new-5gw-ai-campus-abu

  2. G42 to Lead Consortium of US Partners to Build 5GW UAE–US AI Campus

    G42 · Document date: Not stated · Primary

    Source reference: SRC-2918 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.g42.ai/resources/news/g42-lead-consortium-us-partners-build-5gw-uae-us-ai-campus

Location · Abu Dhabi, AE

Actual · G42 UAE–US AI Campus (Project)

Claim 119496 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. UAE and U.S. presidents attend unveiling of Phase 1 of new 5 GW AI campus

    U.S. Department of Commerce · Document date: May 15, 2025 · Corroborating

    Source reference: SRC-6525 · Government record · Recorded authority: Official primary

    Source URL

    https://www.commerce.gov/news/press-releases/2025/05/uae-and-us-presidents-attend-unveiling-phase-1-new-5gw-ai-campus-abu

  2. G42 to Lead Consortium of US Partners to Build 5GW UAE–US AI Campus

    G42 · Document date: Not stated · Primary

    Source reference: SRC-2918 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.g42.ai/resources/news/g42-lead-consortium-us-partners-build-5gw-uae-us-ai-campus

Participant roles · G42, Khazna Data Centers

Actual · G42 UAE–US AI Campus (Project)

Claim 119497 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. UAE and U.S. presidents attend unveiling of Phase 1 of new 5 GW AI campus

    U.S. Department of Commerce · Document date: May 15, 2025 · Corroborating

    Source reference: SRC-6525 · Government record · Recorded authority: Official primary

    Source URL

    https://www.commerce.gov/news/press-releases/2025/05/uae-and-us-presidents-attend-unveiling-phase-1-new-5gw-ai-campus-abu

  2. G42 to Lead Consortium of US Partners to Build 5GW UAE–US AI Campus

    G42 · Document date: Not stated · Primary

    Source reference: SRC-2918 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.g42.ai/resources/news/g42-lead-consortium-us-partners-build-5gw-uae-us-ai-campus

Capacity · 5,000 MW

Planned / design or future potential · G42 UAE–US AI Campus (Project)

Claim 119498 · Recorded claim type: Proposal · Review: Approved · Claim date: Not stated

Headline treatment: Selected headline

  1. UAE and U.S. presidents attend unveiling of Phase 1 of new 5 GW AI campus

    U.S. Department of Commerce · Document date: May 15, 2025 · Corroborating

    Source reference: SRC-6525 · Government record · Recorded authority: Official primary

    Source URL

    https://www.commerce.gov/news/press-releases/2025/05/uae-and-us-presidents-attend-unveiling-phase-1-new-5gw-ai-campus-abu

  2. G42 to Lead Consortium of US Partners to Build 5GW UAE–US AI Campus

    G42 · Document date: Not stated · Primary

    Source reference: SRC-2918 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.g42.ai/resources/news/g42-lead-consortium-us-partners-build-5gw-uae-us-ai-campus

Capacity basis · 5,000 MW planned full development campus envelope

Planned / design or future potential · G42 UAE–US AI Campus (Project)

Claim 119499 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

Headline treatment: Separate claim, not added to the headline

  1. UAE and U.S. presidents attend unveiling of Phase 1 of new 5 GW AI campus

    U.S. Department of Commerce · Document date: May 15, 2025 · Corroborating

    Source reference: SRC-6525 · Government record · Recorded authority: Official primary

    Source URL

    https://www.commerce.gov/news/press-releases/2025/05/uae-and-us-presidents-attend-unveiling-phase-1-new-5gw-ai-campus-abu

  2. G42 to Lead Consortium of US Partners to Build 5GW UAE–US AI Campus

    G42 · Document date: Not stated · Primary

    Source reference: SRC-2918 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.g42.ai/resources/news/g42-lead-consortium-us-partners-build-5gw-uae-us-ai-campus

Development scale · G42 is leading a consortium developing a planned 5 GW AI campus in Abu Dhabi across roughly ten square miles. The first phase is planned at 1 GW, with U.S

Actual · G42 UAE–US AI Campus (Project)

Claim 119500 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. UAE and U.S. presidents attend unveiling of Phase 1 of new 5 GW AI campus

    U.S. Department of Commerce · Document date: May 15, 2025 · Corroborating

    Source reference: SRC-6525 · Government record · Recorded authority: Official primary

    Source URL

    https://www.commerce.gov/news/press-releases/2025/05/uae-and-us-presidents-attend-unveiling-phase-1-new-5gw-ai-campus-abu

  2. G42 to Lead Consortium of US Partners to Build 5GW UAE–US AI Campus

    G42 · Document date: Not stated · Primary

    Source reference: SRC-2918 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.g42.ai/resources/news/g42-lead-consortium-us-partners-build-5gw-uae-us-ai-campus

Infrastructure · The campus remains a development program rather than an operating 5 GW facility.

Actual · G42 UAE–US AI Campus (Project)

Claim 119501 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated

  1. UAE and U.S. presidents attend unveiling of Phase 1 of new 5 GW AI campus

    U.S. Department of Commerce · Document date: May 15, 2025 · Corroborating

    Source reference: SRC-6525 · Government record · Recorded authority: Official primary

    Source URL

    https://www.commerce.gov/news/press-releases/2025/05/uae-and-us-presidents-attend-unveiling-phase-1-new-5gw-ai-campus-abu

  2. G42 to Lead Consortium of US Partners to Build 5GW UAE–US AI Campus

    G42 · Document date: Not stated · Primary

    Source reference: SRC-2918 · Company announcement · Recorded authority: Party primary

    Source URL

    https://www.g42.ai/resources/news/g42-lead-consortium-us-partners-build-5gw-uae-us-ai-campus

Counterparties and capital

G42 · Developer · CMP-0138

Khazna Data Centers · Operator · CMP-0137

This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.