Cartis diligence evidence schedule
Flexential Talty Data Center Campus
PRJ-0682 · Site · Talty, Texas, United States
Record last updated Oct 28, 2026
Scope and capacity
Flexential Talty Data Center Campus is a 110-acre data-center development in Talty, Kaufman County, southeast of Dallas-Fort Worth. Flexential purchased the land in July 2026. Current Dallas portfolio materials identify Dallas-Talty 1 as the first planned 375,000-square-foot building, with secured power supporting 36 MW of capacity. Two additional planned 36 MW buildings could expand the campus to a 108 MW design envelope. Site work is targeted for early 2027 and first customer availability for late 2028. The design includes closed-loop cooling, a zero-WUE target and confirmed fiber access. The 36 MW figure applies to the first planned building, while 108 MW describes the full-campus potential; neither represents achieved operating load.
Headline: 108 MW Planned / design
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (18)
Location context · Flexential campus | Talty | Kaufman County | Texas
Actual · Flexential Talty Data Center Campus (Project)
Claim 57158 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Flexential to build new Dallas-area data center campus
Flexential · Document date: Jul 28, 2026 · Primary
Source reference: SRC-3114 · Company announcement · Recorded authority: Party primary
Source URL
https://www.prnewswire.com/news-releases/flexential-to-build-new-dallas-area-data-center-campus-on-110-acres-in-kaufman-county-302836104.html
https://www.prnewswire.com/news-releases/flexential-to-build-new-dallas-area-data-center-campus-on-110-acres-in-kaufman-county-302836104.html
Lifecycle status · Preconstruction
Actual · Flexential Talty Data Center Campus (Project)
Claim 57159 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Flexential to build new Dallas-area data center campus
Flexential · Document date: Jul 28, 2026 · Primary
Source reference: SRC-3114 · Company announcement · Recorded authority: Party primary
Source URL
https://www.prnewswire.com/news-releases/flexential-to-build-new-dallas-area-data-center-campus-on-110-acres-in-kaufman-county-302836104.html
https://www.prnewswire.com/news-releases/flexential-to-build-new-dallas-area-data-center-campus-on-110-acres-in-kaufman-county-302836104.html
Reported capacity · 108 MW
Planned / design or future potential · Flexential Talty Data Center Campus (Project)
Claim 57160 · Recorded claim type: Design · Review: Approved · Claim date: Not stated
Headline treatment: Separate claim, not added to the headline
- Flexential to build new Dallas-area data center campus
Flexential · Document date: Jul 28, 2026 · Primary
Source reference: SRC-3114 · Company announcement · Recorded authority: Party primary
Source URL
https://www.prnewswire.com/news-releases/flexential-to-build-new-dallas-area-data-center-campus-on-110-acres-in-kaufman-county-302836104.html
https://www.prnewswire.com/news-releases/flexential-to-build-new-dallas-area-data-center-campus-on-110-acres-in-kaufman-county-302836104.html
Capacity basis · Flexential states a planned 108 MW campus.
Actual · Flexential Talty Data Center Campus (Project)
Claim 57161 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Flexential to build new Dallas-area data center campus
Flexential · Document date: Jul 28, 2026 · Primary
Source reference: SRC-3114 · Company announcement · Recorded authority: Party primary
Source URL
https://www.prnewswire.com/news-releases/flexential-to-build-new-dallas-area-data-center-campus-on-110-acres-in-kaufman-county-302836104.html
https://www.prnewswire.com/news-releases/flexential-to-build-new-dallas-area-data-center-campus-on-110-acres-in-kaufman-county-302836104.html
Location context · Flexential campus | Talty | Kaufman County | Texas
Actual · Flexential Talty Data Center Campus (Project)
Claim 111211 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Flexential to build new Dallas-area data center campus
Flexential · Document date: Jul 28, 2026 · Primary
Source reference: SRC-3114 · Company announcement · Recorded authority: Party primary
Source URL
https://www.prnewswire.com/news-releases/flexential-to-build-new-dallas-area-data-center-campus-on-110-acres-in-kaufman-county-302836104.html
https://www.prnewswire.com/news-releases/flexential-to-build-new-dallas-area-data-center-campus-on-110-acres-in-kaufman-county-302836104.html
Lifecycle status · Preconstruction
Actual · Flexential Talty Data Center Campus (Project)
Claim 111212 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Flexential to build new Dallas-area data center campus
Flexential · Document date: Jul 28, 2026 · Primary
Source reference: SRC-3114 · Company announcement · Recorded authority: Party primary
Source URL
https://www.prnewswire.com/news-releases/flexential-to-build-new-dallas-area-data-center-campus-on-110-acres-in-kaufman-county-302836104.html
https://www.prnewswire.com/news-releases/flexential-to-build-new-dallas-area-data-center-campus-on-110-acres-in-kaufman-county-302836104.html
Reported capacity · 108 MW
Planned / design or future potential · Flexential Talty Data Center Campus (Project)
Claim 111213 · Recorded claim type: Design · Review: Approved · Claim date: Not stated
Headline treatment: Selected headline
- Flexential to build new Dallas-area data center campus
Flexential · Document date: Jul 28, 2026 · Primary
Source reference: SRC-3114 · Company announcement · Recorded authority: Party primary
Source URL
https://www.prnewswire.com/news-releases/flexential-to-build-new-dallas-area-data-center-campus-on-110-acres-in-kaufman-county-302836104.html
https://www.prnewswire.com/news-releases/flexential-to-build-new-dallas-area-data-center-campus-on-110-acres-in-kaufman-county-302836104.html
Capacity basis · Flexential states a planned 108 MW campus.
Actual · Flexential Talty Data Center Campus (Project)
Claim 111214 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Flexential to build new Dallas-area data center campus
Flexential · Document date: Jul 28, 2026 · Primary
Source reference: SRC-3114 · Company announcement · Recorded authority: Party primary
Source URL
https://www.prnewswire.com/news-releases/flexential-to-build-new-dallas-area-data-center-campus-on-110-acres-in-kaufman-county-302836104.html
https://www.prnewswire.com/news-releases/flexential-to-build-new-dallas-area-data-center-campus-on-110-acres-in-kaufman-county-302836104.html
Development scale · 108 MW planned campus
Actual · Flexential Talty Data Center Campus (Project)
Claim 111231 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Flexential to build new Dallas-area data center campus
Flexential · Document date: Jul 28, 2026 · Primary
Source reference: SRC-3114 · Company announcement · Recorded authority: Party primary
Source URL
https://www.prnewswire.com/news-releases/flexential-to-build-new-dallas-area-data-center-campus-on-110-acres-in-kaufman-county-302836104.html
https://www.prnewswire.com/news-releases/flexential-to-build-new-dallas-area-data-center-campus-on-110-acres-in-kaufman-county-302836104.html
- Talty campus announcement
Flexential · Document date: Jul 27, 2026 · Corroborating
Source reference: SRC-6209 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.flexential.com/resources/press-release/flexential-to-build-new-dallas-area-data-center-campus-on-110-acres-in-kaufman-county
https://www.flexential.com/resources/press-release/flexential-to-build-new-dallas-area-data-center-campus-on-110-acres-in-kaufman-county
Development milestone · 36 MW Phase 1
Actual · Flexential Talty Data Center Campus (Project)
Claim 111232 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Flexential to build new Dallas-area data center campus
Flexential · Document date: Jul 28, 2026 · Primary
Source reference: SRC-3114 · Company announcement · Recorded authority: Party primary
Source URL
https://www.prnewswire.com/news-releases/flexential-to-build-new-dallas-area-data-center-campus-on-110-acres-in-kaufman-county-302836104.html
https://www.prnewswire.com/news-releases/flexential-to-build-new-dallas-area-data-center-campus-on-110-acres-in-kaufman-county-302836104.html
- Talty campus announcement
Flexential · Document date: Jul 27, 2026 · Corroborating
Source reference: SRC-6209 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.flexential.com/resources/press-release/flexential-to-build-new-dallas-area-data-center-campus-on-110-acres-in-kaufman-county
https://www.flexential.com/resources/press-release/flexential-to-build-new-dallas-area-data-center-campus-on-110-acres-in-kaufman-county
Power arrangement · 110 Acres.
Actual · Flexential Talty Data Center Campus (Project)
Claim 111233 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Flexential to build new Dallas-area data center campus
Flexential · Document date: Jul 28, 2026 · Primary
Source reference: SRC-3114 · Company announcement · Recorded authority: Party primary
Source URL
https://www.prnewswire.com/news-releases/flexential-to-build-new-dallas-area-data-center-campus-on-110-acres-in-kaufman-county-302836104.html
https://www.prnewswire.com/news-releases/flexential-to-build-new-dallas-area-data-center-campus-on-110-acres-in-kaufman-county-302836104.html
- Talty campus announcement
Flexential · Document date: Jul 27, 2026 · Corroborating
Source reference: SRC-6209 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.flexential.com/resources/press-release/flexential-to-build-new-dallas-area-data-center-campus-on-110-acres-in-kaufman-county
https://www.flexential.com/resources/press-release/flexential-to-build-new-dallas-area-data-center-campus-on-110-acres-in-kaufman-county
Site configuration · Flexential campus | Talty | Kaufman County | Texas
Actual · Flexential Talty Data Center Campus (Project)
Claim 111234 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Flexential to build new Dallas-area data center campus
Flexential · Document date: Jul 28, 2026 · Primary
Source reference: SRC-3114 · Company announcement · Recorded authority: Party primary
Source URL
https://www.prnewswire.com/news-releases/flexential-to-build-new-dallas-area-data-center-campus-on-110-acres-in-kaufman-county-302836104.html
https://www.prnewswire.com/news-releases/flexential-to-build-new-dallas-area-data-center-campus-on-110-acres-in-kaufman-county-302836104.html
- Talty campus announcement
Flexential · Document date: Jul 27, 2026 · Corroborating
Source reference: SRC-6209 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.flexential.com/resources/press-release/flexential-to-build-new-dallas-area-data-center-campus-on-110-acres-in-kaufman-county
https://www.flexential.com/resources/press-release/flexential-to-build-new-dallas-area-data-center-campus-on-110-acres-in-kaufman-county
Site area · 110 acres
Actual · Flexential Talty Data Center Campus (Project)
Claim 158467 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Flexential to Build New Dallas-Area Data Center Campus on 110 Acres in Kaufman County
Flexential · Document date: Jul 28, 2026 · Primary
Source reference: SRC-7932 · Company announcement · Recorded authority: Party primary
Source URL
https://www.flexential.com/resources/press-release/flexential-build-new-dallas-area-data-center-campus-110-acres
https://www.flexential.com/resources/press-release/flexential-build-new-dallas-area-data-center-campus-110-acres
Phase1 building area · 375,000 sq. ft.
Design · Flexential Talty Data Center Campus (Project)
Claim 158468 · Recorded claim type: Design · Review: Approved · Claim date: Not stated
- Flexential to Build New Dallas-Area Data Center Campus on 110 Acres in Kaufman County
Flexential · Document date: Jul 28, 2026 · Primary
Source reference: SRC-7932 · Company announcement · Recorded authority: Party primary
Source URL
https://www.flexential.com/resources/press-release/flexential-build-new-dallas-area-data-center-campus-110-acres
https://www.flexential.com/resources/press-release/flexential-build-new-dallas-area-data-center-campus-110-acres
- Dallas, Texas data centers
Flexential · Document date: Not stated · Corroborating
Source reference: SRC-7933 · Fact sheet · Recorded authority: Party primary
Source URL
https://www.flexential.com/data-centers/tx/dallas
https://www.flexential.com/data-centers/tx/dallas
Phase1 capacity · 36 MW
Planned / design or future potential · Flexential Talty Data Center Campus (Project)
Claim 158469 · Recorded claim type: Design · Review: Approved · Claim date: Not stated
Headline treatment: Separate claim, not added to the headline
- Flexential to Build New Dallas-Area Data Center Campus on 110 Acres in Kaufman County
Flexential · Document date: Jul 28, 2026 · Primary
Source reference: SRC-7932 · Company announcement · Recorded authority: Party primary
Source URL
https://www.flexential.com/resources/press-release/flexential-build-new-dallas-area-data-center-campus-110-acres
https://www.flexential.com/resources/press-release/flexential-build-new-dallas-area-data-center-campus-110-acres
- Dallas, Texas data centers
Flexential · Document date: Not stated · Corroborating
Source reference: SRC-7933 · Fact sheet · Recorded authority: Party primary
Source URL
https://www.flexential.com/data-centers/tx/dallas
https://www.flexential.com/data-centers/tx/dallas
Campus capacity potential · 108 MW
Planned / design or future potential · Flexential Talty Data Center Campus (Project)
Claim 158470 · Recorded claim type: Design · Review: Approved · Claim date: Not stated
Headline treatment: Separate claim, not added to the headline
- Flexential to Build New Dallas-Area Data Center Campus on 110 Acres in Kaufman County
Flexential · Document date: Jul 28, 2026 · Primary
Source reference: SRC-7932 · Company announcement · Recorded authority: Party primary
Source URL
https://www.flexential.com/resources/press-release/flexential-build-new-dallas-area-data-center-campus-110-acres
https://www.flexential.com/resources/press-release/flexential-build-new-dallas-area-data-center-campus-110-acres
Building count full build · 3 buildings
Design · Flexential Talty Data Center Campus (Project)
Claim 158471 · Recorded claim type: Design · Review: Approved · Claim date: Not stated
- Flexential to Build New Dallas-Area Data Center Campus on 110 Acres in Kaufman County
Flexential · Document date: Jul 28, 2026 · Primary
Source reference: SRC-7932 · Company announcement · Recorded authority: Party primary
Source URL
https://www.flexential.com/resources/press-release/flexential-build-new-dallas-area-data-center-campus-110-acres
https://www.flexential.com/resources/press-release/flexential-build-new-dallas-area-data-center-campus-110-acres
Water usage effectiveness target · 0 WUE
Forecast · Flexential Talty Data Center Campus (Project)
Claim 158472 · Recorded claim type: Forecast · Review: Approved · Claim date: Not stated
- Flexential to Build New Dallas-Area Data Center Campus on 110 Acres in Kaufman County
Flexential · Document date: Jul 28, 2026 · Primary
Source reference: SRC-7932 · Company announcement · Recorded authority: Party primary
Source URL
https://www.flexential.com/resources/press-release/flexential-build-new-dallas-area-data-center-campus-110-acres
https://www.flexential.com/resources/press-release/flexential-build-new-dallas-area-data-center-campus-110-acres
Counterparties and capital
Flexential · Developer, Operator, Owner · CMP-1425
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.