Flexential Talty Data Center Campus

Talty, Texas, United StatesPreconstruction
Evidence
Planned / design
108 MW
Updated
Oct 28, 2026

Flexential Talty Data Center Campus is a 110-acre data center development in Talty, Kaufman County, southeast of Dallas-Fort Worth. Flexential purchased the land in July 2026. Current Dallas portfolio materials identify Dallas-Talty 1 as the first planned 375,000-square-foot building, with secured power supporting 36 MW of capacity. Two additional planned 36 MW buildings could expand the campus to a 108 MW design envelope. Site work is targeted for early 2027 and first customer availability for late 2028. The design includes closed-loop cooling, a zero-WUE target and confirmed fiber access. The 36 MW figure applies to the first planned building, while 108 MW describes the full-campus potential; neither represents achieved operating load.

Capacity

Reported capacity

Planned / design or future potential

108 MW

Source

Reported capacity

Planned / design or future potential

108 MW

Source

Phase1 capacity

Planned / design or future potential

36 MW

Source

Campus capacity potential

Planned / design or future potential

108 MW

Source

Operating IT capacity: Not established in published records

A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.

Development

Development programAnnounced or preconstruction

Project-wide phase for Flexential Talty Data Center Campus; capacity class is design.

Talty Phase 1Planned

1 building

375,000 ft² first building with secured power for 36 MW of source-described capacity.

Talty future campus buildoutPlanned

2 buildings

Two additional planned 36 MW buildings could bring the campus envelope to 108 MW.

Milestones (5)
Flexential Kaufman County Campus development disclosed

Jul 28, 2026 · Recorded actual event

Completed · Announced

Source not linked
Flexential announced purchase of the 110-acre Talty site

Jul 28, 2026 · Recorded actual event

Completed · Land acquired

Source not linked
Site work expected to begin in early 2027

2027 · Forecast / planned record

Forecast · Construction started

Source not linked
First customer availability targeted for late 2028

Dec 2028 · Forecast / planned record

Forecast · Forecast completion

Source not linked
Land acquired; Phase 1 planning underway

Date not disclosed · Forecast / planned record

Forecast · Forecast completion

Source not linked

Participants

Flexential

Developer · Operator · Owner

Sources by role

Site & development

Location context

Actual

Flexential campus | Talty | Kaufman County | Texas

Source

Location context

Actual

Flexential campus | Talty | Kaufman County | Texas

Source

Development scale

Actual

108 MW planned campus

Source

Development milestone

Actual

36 MW Phase 1

Source

Site configuration

Actual

Flexential campus | Talty | Kaufman County | Texas

Source

Site area

Actual

110 acres

Source

Phase1 building area

Design

375,000 sq. ft.

Source

Building count full build

Design

3 buildings

Source

Technical specifications

Power arrangement

Actual

110 Acres.

Source

Water usage effectiveness target

Forecast

0 WUE

Source

Additional project facts

Lifecycle status

Actual

Preconstruction

Source

Capacity basis

Actual

Flexential states a planned 108 MW campus.

Source

Lifecycle status

Actual

Preconstruction

Source

Capacity basis

Actual

Flexential states a planned 108 MW campus.

Source

Infrastructure & permits

Technical details (5)
Electric grid

Planned or represented

108 MW

Flexential states a planned 108 MW campus.

Site facility

Planned or represented

Phase 1 power secured for wholesale and high-density workloads.

Electric grid

Secured or contracted

36 MW

Power is secured for Phase 1 supporting 36 MW of source-described capacity.

Cooling system

Planned or represented

Closed-loop cooling architecture with a zero-WUE design target.

Fiber

Secured or contracted

The parcel has confirmed fiber access and is planned to connect to Flexential's nationwide private-network backbone.