Firmus Wesley Vale AI Factory
- Planned critical IT
- 46 MW
- Updated
- Oct 28, 2026
- Utility
- TasNetworks
Firmus's Wesley Vale AI Factory is a proposed facility at 226 Mill Road on part of the former Wesley Vale pulp-mill site in Tasmania. Firmus describes a two-stage build: approximately 26 MW of facility capacity with 23 MW critical IT initially, expanding to approximately 52 MW facility capacity and 46 MW critical IT. Application materials describe roughly 3,500 square metres of total building area and a 2,690-square-metre data hall, with 40 diesel backup generators. Firmus estimates average annual cooling-water use of 448 kL sourced from onsite rainwater. The development application remains under planning assessment; in September Latrobe Council requested state major-project review.
Capacity
Operating IT capacity: Not established in published records
A missing figure does not mean zero. Planned, utility and generation figures are not operating IT capacity.
Development
1 building
Initial approximately 26 MW facility capacity / 23 MW critical IT stage.
1 building
Maximum approximately 52 MW facility capacity / 46 MW critical IT.
Milestones (3)
Jun 15, 2026 · Recorded actual event
Completed · Permit filed
Sources (1)
- Firmus plans to truck water in and use rainwater to cool proposed Wesley Vale AI data centre · Aug 27, 2026 · Primary
Aug 27, 2026 · Recorded actual event
Completed · Status changed
Sources (1)
- Firmus plans to truck water in and use rainwater to cool proposed Wesley Vale AI data centre · Aug 27, 2026 · Primary
Sep 9, 2026 · Recorded actual event
Completed · Status changed
Sources (1)
- Latrobe council sends Firmus project to government · Sep 9, 2026 · Primary
Participants
Developer
Sources by role
Developer (1)
- Firmus proposes third data center project in Tasmania · Sep 3, 2026 · Corroborating
Developer (1)
- Wesley Vale AI Factory Project · Primary
Other participants (1)
Utility provider
Sources by role
Utility provider (1)
- Firmus proposes third data center project in Tasmania · Sep 3, 2026 · Primary
Site & development
Technical specifications
Additional project facts
Infrastructure & permits
Technical details (4)
Potential or planned
26 MW
Existing industrial electrical infrastructure supports an initial 26 MW connection concept; future substation upgrades would support the second stage. The connection remains planned.
Planned or represented
40 generators
Forty diesel backup generators are planned; generator MW is undisclosed.
Planned or represented
448 kiloliters per year
Firmus estimates 448 kL average annual cooling water, sourced from onsite rainwater; this is water consumption rather than thermal capacity.
Planned or represented
Firmus is recruiting network/fibre deployment roles for Wesley Vale; carrier count and completed fiber routes are not yet public.
Project map
Building · Under review
Wesley Vale AI Factory
Sources (3)
- Latrobe council sends Firmus project to government · Sep 9, 2026 · Corroborating
- Firmus plans to truck water in and use rainwater to cool proposed Wesley Vale AI data centre · Aug 27, 2026 · Corroborating
- Wesley Vale AI Factory Project · Primary
Public-source research. Plans may change. See Evidence for sources and qualifications.