Cartis diligence evidence schedule
Farmington Technology Park / Tract
PRJ-0554 · Program · Farmington, Minnesota, United States
Record last updated Oct 28, 2026
Scope and capacity
In a September 16, 2026 update, Farmington city said plaintiffs had filed dismissals in both legal matters involving the city and that final court directions were still awaited. This procedural development is not a final merits judgment or proof that every development approval is complete. Tract's Farmington Technology Park has completed major land-use, environmental-review and platting steps, and the city approved two updated additions and development contracts in April 2026. The approved Phase 1 is preliminary grading; future data-center buildings still require site-plan review.
Headline: See constituent sites
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (18)
Auar study area · 343 acres
Actual · Farmington Technology Park / Tract (Project)
Claim 50548 · Recorded claim type: Actual · Review: Approved · Claim date: Nov 4, 2024
- EQB Monitor — Farmington Technology Park AUAR
Minnesota Environmental Quality Board · Document date: Nov 12, 2024 · Corroborating
Source reference: SRC-6679 · Government record · Recorded authority: Official primary
Source URL
https://content.govdelivery.com/accounts/MNEQB/bulletins/3c06769
https://content.govdelivery.com/accounts/MNEQB/bulletins/3c06769
- Adoption of the Final AUAR — Farmington Technology Park
City of Farmington · Document date: Nov 4, 2024 · Primary
Source reference: SRC-2667 · Government record · Recorded authority: Official primary
Source URL
https://www.farmingtonmn.gov/DocumentCenter/View/1240
https://www.farmingtonmn.gov/DocumentCenter/View/1240
Final plat area · 338.35 acres
Actual · Farmington Technology Park / Tract (Project)
Claim 50549 · Recorded claim type: Actual · Review: Approved · Claim date: Nov 18, 2024
- Final Plat & Final Planned Unit Development — Farmington Technology Park
City of Farmington · Document date: Nov 18, 2024 · Primary
Source reference: SRC-2668 · Government record · Recorded authority: Official primary
Source URL
https://www.farmingtonmn.gov/DocumentCenter/View/1250
https://www.farmingtonmn.gov/DocumentCenter/View/1250
North lot area · 150.74 acres
Actual · Farmington Technology Park / Tract (Project)
Claim 50550 · Recorded claim type: Actual · Review: Approved · Claim date: Nov 18, 2024
- Final Plat & Final Planned Unit Development — Farmington Technology Park
City of Farmington · Document date: Nov 18, 2024 · Primary
Source reference: SRC-2668 · Government record · Recorded authority: Official primary
Source URL
https://www.farmingtonmn.gov/DocumentCenter/View/1250
https://www.farmingtonmn.gov/DocumentCenter/View/1250
Utility lot area · 2.07 acres
Actual · Farmington Technology Park / Tract (Project)
Claim 50551 · Recorded claim type: Actual · Review: Approved · Claim date: Nov 18, 2024
- Final Plat & Final Planned Unit Development — Farmington Technology Park
City of Farmington · Document date: Nov 18, 2024 · Primary
Source reference: SRC-2668 · Government record · Recorded authority: Official primary
Source URL
https://www.farmingtonmn.gov/DocumentCenter/View/1250
https://www.farmingtonmn.gov/DocumentCenter/View/1250
South lot area · 185.54 acres
Actual · Farmington Technology Park / Tract (Project)
Claim 50552 · Recorded claim type: Actual · Review: Approved · Claim date: Nov 18, 2024
- Final Plat & Final Planned Unit Development — Farmington Technology Park
City of Farmington · Document date: Nov 18, 2024 · Primary
Source reference: SRC-2668 · Government record · Recorded authority: Official primary
Source URL
https://www.farmingtonmn.gov/DocumentCenter/View/1250
https://www.farmingtonmn.gov/DocumentCenter/View/1250
South lot floodplain · 69 acres approx
Actual · Farmington Technology Park / Tract (Project)
Claim 50553 · Recorded claim type: Actual · Review: Approved · Claim date: Nov 18, 2024
- Final Plat & Final Planned Unit Development — Farmington Technology Park
City of Farmington · Document date: Nov 18, 2024 · Primary
Source reference: SRC-2668 · Government record · Recorded authority: Official primary
Source URL
https://www.farmingtonmn.gov/DocumentCenter/View/1250
https://www.farmingtonmn.gov/DocumentCenter/View/1250
Data center building ceiling · 12 buildings up to
Design · Farmington Technology Park / Tract (Project)
Claim 50554 · Recorded claim type: Design · Review: Approved · Claim date: Nov 18, 2024
- Final Plat & Final Planned Unit Development — Farmington Technology Park
City of Farmington · Document date: Nov 18, 2024 · Primary
Source reference: SRC-2668 · Government record · Recorded authority: Official primary
Source URL
https://www.farmingtonmn.gov/DocumentCenter/View/1250
https://www.farmingtonmn.gov/DocumentCenter/View/1250
Administrative building ceiling · 2 buildings up to
Design · Farmington Technology Park / Tract (Project)
Claim 50555 · Recorded claim type: Design · Review: Approved · Claim date: Nov 18, 2024
- Final Plat & Final Planned Unit Development — Farmington Technology Park
City of Farmington · Document date: Nov 18, 2024 · Primary
Source reference: SRC-2668 · Government record · Recorded authority: Official primary
Source URL
https://www.farmingtonmn.gov/DocumentCenter/View/1250
https://www.farmingtonmn.gov/DocumentCenter/View/1250
North data center floor area ceiling · 1,600,400 square feet up to
Design · Farmington Technology Park / Tract (Project)
Claim 50556 · Recorded claim type: Design · Review: Approved · Claim date: Nov 18, 2024
- Final Plat & Final Planned Unit Development — Farmington Technology Park
City of Farmington · Document date: Nov 18, 2024 · Primary
Source reference: SRC-2668 · Government record · Recorded authority: Official primary
Source URL
https://www.farmingtonmn.gov/DocumentCenter/View/1250
https://www.farmingtonmn.gov/DocumentCenter/View/1250
South data center floor area ceiling · 933,800 square feet up to
Design · Farmington Technology Park / Tract (Project)
Claim 50557 · Recorded claim type: Design · Review: Approved · Claim date: Nov 18, 2024
- Final Plat & Final Planned Unit Development — Farmington Technology Park
City of Farmington · Document date: Nov 18, 2024 · Primary
Source reference: SRC-2668 · Government record · Recorded authority: Official primary
Source URL
https://www.farmingtonmn.gov/DocumentCenter/View/1250
https://www.farmingtonmn.gov/DocumentCenter/View/1250
Future site plan requirement · Planning Commission approval required before any data center building or ancillary use construction
Forecast · Farmington Technology Park / Tract (Project)
Claim 50558 · Recorded claim type: Forecast · Review: Approved · Claim date: Nov 18, 2024
- Final Plat & Final Planned Unit Development — Farmington Technology Park
City of Farmington · Document date: Nov 18, 2024 · Primary
Source reference: SRC-2668 · Government record · Recorded authority: Official primary
Source URL
https://www.farmingtonmn.gov/DocumentCenter/View/1250
https://www.farmingtonmn.gov/DocumentCenter/View/1250
Auar legal effect · Planning and environmental review tool; does not approve or deny a project
Actual · Farmington Technology Park / Tract (Project)
Claim 50559 · Recorded claim type: Actual · Review: Approved · Claim date: Nov 4, 2024
- Adoption of the Final AUAR — Farmington Technology Park
City of Farmington · Document date: Nov 4, 2024 · Primary
Source reference: SRC-2667 · Government record · Recorded authority: Official primary
Source URL
https://www.farmingtonmn.gov/DocumentCenter/View/1240
https://www.farmingtonmn.gov/DocumentCenter/View/1240
Final plat and pud status · Approved
Permitted · Farmington Technology Park / Tract (Project)
Claim 50560 · Recorded claim type: Permitted · Review: Approved · Claim date: Nov 18, 2024
- Data Center (Farmington Technology Park)
City of Farmington · Document date: Apr 20, 2026 · Primary
Source reference: SRC-2666 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.farmingtonmn.gov/473/Data-Center-Farmington-Technology-Park
https://www.farmingtonmn.gov/473/Data-Center-Farmington-Technology-Park
- Final Plat & Final Planned Unit Development — Farmington Technology Park
City of Farmington · Document date: Nov 18, 2024 · Corroborating
Source reference: SRC-2668 · Government record · Recorded authority: Official primary
Source URL
https://www.farmingtonmn.gov/DocumentCenter/View/1250
https://www.farmingtonmn.gov/DocumentCenter/View/1250
Litigation status · Legal proceedings continue after denial of City motion to dismiss
Actual · Farmington Technology Park / Tract (Project)
Claim 50561 · Recorded claim type: Actual · Review: Approved · Claim date: Nov 13, 2025
- Data Center (Farmington Technology Park)
City of Farmington · Document date: Apr 20, 2026 · Primary
Source reference: SRC-2666 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.farmingtonmn.gov/473/Data-Center-Farmington-Technology-Park
https://www.farmingtonmn.gov/473/Data-Center-Farmington-Technology-Park
Specific development application status · None received by the City at the November 2025 update
Actual · Farmington Technology Park / Tract (Project)
Claim 50562 · Recorded claim type: Actual · Review: Approved · Claim date: Nov 13, 2025
- Data Center (Farmington Technology Park)
City of Farmington · Document date: Apr 20, 2026 · Primary
Source reference: SRC-2666 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.farmingtonmn.gov/473/Data-Center-Farmington-Technology-Park
https://www.farmingtonmn.gov/473/Data-Center-Farmington-Technology-Park
Split addition status · 1St and 2nd Additions and updated development contracts approved
Actual · Farmington Technology Park / Tract (Project)
Claim 50563 · Recorded claim type: Actual · Review: Approved · Claim date: Apr 20, 2026
- Data Center (Farmington Technology Park)
City of Farmington · Document date: Apr 20, 2026 · Primary
Source reference: SRC-2666 · Fact sheet · Recorded authority: Official primary
Source URL
https://www.farmingtonmn.gov/473/Data-Center-Farmington-Technology-Park
https://www.farmingtonmn.gov/473/Data-Center-Farmington-Technology-Park
- Final Plats — Farmington Technology Park 1st Addition and 2nd Addition
City of Farmington · Document date: Apr 20, 2026 · Corroborating
Source reference: SRC-2669 · Regulatory record · Recorded authority: Official primary
Source URL
https://www.farmingtonmn.gov/DocumentCenter/View/2119
https://www.farmingtonmn.gov/DocumentCenter/View/2119
Phase scope · Limited preliminary grading subject to City Engineer requirements and performed at developer risk
Actual · Phase 1 preliminary grading (Phase)
Claim 50564 · Recorded claim type: Actual · Review: Approved · Claim date: Apr 20, 2026
- Final Plats — Farmington Technology Park 1st Addition and 2nd Addition
City of Farmington · Document date: Apr 20, 2026 · Primary
Source reference: SRC-2669 · Regulatory record · Recorded authority: Official primary
Source URL
https://www.farmingtonmn.gov/DocumentCenter/View/2119
https://www.farmingtonmn.gov/DocumentCenter/View/2119
Later phase controls · Site plan approval and recorded Site Improvement/Performance Agreement required
Forecast · Future vertical development (Phase)
Claim 50565 · Recorded claim type: Forecast · Review: Approved · Claim date: Apr 20, 2026
- Final Plats — Farmington Technology Park 1st Addition and 2nd Addition
City of Farmington · Document date: Apr 20, 2026 · Primary
Source reference: SRC-2669 · Regulatory record · Recorded authority: Official primary
Source URL
https://www.farmingtonmn.gov/DocumentCenter/View/2119
https://www.farmingtonmn.gov/DocumentCenter/View/2119
Counterparties and capital
City of Farmington · Government authority · CMP-1272
Dakota County District Court · Government authority · CMP-1278
Metropolitan Council · Government authority · CMP-1277
MNLCO Farmington Two, LLC · Developer · CMP-1274
MNLCO Farmington, LLC · Developer · CMP-1273
Tract · Developer · CMP-1271
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.