Data center program / initiativeProgram record

Farmington Technology Park / Tract

Farmington, Minnesota, United StatesStatus Under Review
Capacity
See sites
0 constituent sites
Lead participant
MNLCO Farmington Two, LLC
Developer
Last updated
Aug 26, 2026
Most recent public record update

About Farmington Technology Park / Tract

Tract's Farmington Technology Park has completed major land-use, environmental-review and platting steps, and the city approved two updated additions and development contracts in April 2026. The approved Phase 1 is preliminary grading; future data center buildings still require site-plan review.

Capacity

Operating capacityAn operating IT-capacity figure has not been publicly disclosed.

No additional capacity claims are published.

Development

3 phases · 8 milestones
Environmental review and master-plan entitlementsPlanned

Land-use ceiling allows up to 12 data center buildings and two administrative buildings, but creates no vertical facility record.

12 buildings

Phase 1 preliminary gradingAnnounced Or Preconstruction

Phase 1 is site work at the developer's risk and excludes a data center building start.

Future vertical developmentPlanned

Any data center building requires later Planning Commission/City review and remains outside the current canonical record.

Nov 4, 2024
Farmington adopts final technology-park AUAR
Completed
Nov 4, 2024
City approves preliminary master-plan entitlements
Completed
Nov 18, 2024
City approves final plat and PUD
Completed
Nov 29, 2024
Coalition files challenge
Completed
Dec 2, 2024
City approves Tract development contract
Completed
May 14, 2025
Regional planning approval completed
Completed
Nov 13, 2025
Court allows legal proceedings to continue
In Progress
Apr 20, 2026
Two technology-park additions approved
Completed

Infrastructure

Electric GridPlanned Or Represented

Northwest portion of the southern lot is reserved for future electric utilities and identified as a potential substation location; no utility or capacity is disclosed.

Water SupplySecured Or Contracted

Updated development contracts revise infrastructure deadlines and cap annual municipal water usage, but the accessible memorandum does not state the numerical cap.

Constituent-site map

0 of 0 constituent sites mapped
Child-site facts
0
Mapped child sites
0
Capacity figures
0

No map point available

Facts & sources

Published claims and their source links.

18 facts
Auar Study Area
343 acres
Actual
Final Plat Area
338.35 acres
Actual
North Lot Area
150.74 acres
Actual
Utility Lot Area
2.07 acres
Actual
South Lot Area
185.54 acres
Actual
South Lot Floodplain
69 acres approx
Actual
Data Center Building Ceiling
12 buildings up to
Design
Administrative Building Ceiling
2 buildings up to
Design
North Data Center Floor Area Ceiling
1,600,400 square feet up to
Design
South Data Center Floor Area Ceiling
933,800 square feet up to
Design
Future Site Plan Requirement
Planning Commission approval required before any data center building or ancillary use construction
Forecast
Auar Legal Effect
Planning and environmental review tool; does not approve or deny a project
Actual
Final Plat And Pud Status
Approved
Permitted
Litigation Status
Legal proceedings continue after denial of City motion to dismiss
Actual
Specific Development Application Status
None received by the City at the November 2025 update
Actual
Split Addition Status
1St and 2nd Additions and updated development contracts approved
Actual
Phase Scope
Limited preliminary grading subject to City Engineer requirements and performed at developer risk
Actual
Later Phase Controls
Site plan approval and recorded Site Improvement/Performance Agreement required
Forecast