Entergy Project Laidley Power Program

Richland and St. Charles parishes, Louisiana, United StatesStatus Under Review
Capacity
See sites
2 constituent sites
Lead participant
Laidley LLC
Customer
Last updated
Aug 25, 2026
Most recent public record update

About Entergy Project Laidley Power Program

Approved utility-resource package serving the initial Meta/Laidley load, including three combined-cycle units, transmission and renewable procurement. Entergy Project Laidley Power Program is in Richland and St. Charles parishes, LA, US and is a program with under construction status. Participants include Entergy Louisiana as utility, Midcontinent Independent System Operator as grid operator, Laidley LLC as customer. Published specifications include 2250 MW onsite generation nameplate, 1500 MW onsite generation nameplate. Development comprises Regulatory approval and procurement (approved). Key milestones include Laidley application opened. (2024-12-01) and LPSC approved Laidley resource package. (2025-08-20). combined cycle generation portfolio — 2250 MW: Three approved units across Franklin Farms and Waterford; generation capacity is not Meta IT load. 500kv transmission — 60 miles: Mount Olive–Sarepta approximately 60-mile 500-kV line plus upgrades. Permitting includes certificate and resource approval for Project Laidley / Docket U-37425 (approved).

Constituent sites

2 linked

Projects sharing a market, utility, or organization.

1 related

Capacity

Operating capacityAn operating IT-capacity figure has not been publicly disclosed.
Onsite Generation2,250 MWFact · Entergy Project Laidley Power Program

Development

1 phases · 2 milestones
Regulatory approval and procurementAnnounced Or Preconstruction

LPSC-approved resource package.

Dec 1, 2024
Laidley application opened
Completed
Aug 20, 2025
LPSC approved Laidley resource package
Completed

Infrastructure

Electric GridUnder Construction

2,250 MW

Three approved units across Franklin Farms and Waterford; generation capacity is not Meta IT load.

Electric GridSecured Or Contracted

60 miles

Mount Olive–Sarepta approximately 60-mile 500-kV line plus upgrades.

Renewable Energy SupplySecured Or Contracted

1,500 MW

Authority to procure up to 1.5 GW solar; projects and delivery status not yet final.

Constituent-site map

0 of 2 constituent sites mapped
Child-site facts
0
Mapped child sites
0
Capacity figures
0

No map point available

Facts & sources

Published claims and their source links.

3 facts
Combined Cycle Generation Capacity
2,250 MW
Fact
Combined Cycle Unit Count
3 units
Actual
Authorized Solar Procurement Ceiling
1,500 MW
Fact