Cartis diligence evidence schedule
Energy Vault Snyder AI Data Center
PRJ-0701 · Site · Snyder, Texas, United States
Record last updated Oct 28, 2026
Scope and capacity
Energy Vault has begun construction of powered-shell infrastructure for Crusoe Spark modular data centers at its Snyder, Texas technology site. The first contracted phase is 8 MW, with a potential second phase to 25 MW and a separate long-range site concept of up to 500 MW. Energy Vault is associated with the development in Snyder, Scurry County, TX, US. The disclosed development scope includes 8 MW contracted initial powered-shell phase; commercial operation targeted in first half of 2027; potential 25 MW second phase; up to 500 MW long-range site plan. Power and physical infrastructure include modular powered-shell electrical and mechanical infrastructure will serve Crusoe Spark units at an existing Energy Vault site. The first contracted powered-shell phase is designed to deliver 8 MW.
Headline: 8 MW Contracted
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Jump to a claim (12)
Location context · Energy Vault data center site | Snyder | Scurry County | Texas
Actual · Energy Vault Snyder AI Data Center (Project)
Claim 57944 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Energy Vault Q2 2026 results
Energy Vault · Document date: Aug 6, 2026 · Primary
Source reference: SRC-3163 · Fact sheet · Recorded authority: Party primary
Source URL
https://investors.energyvault.com/overview/
https://investors.energyvault.com/overview/
Lifecycle status · Construction
Actual · Energy Vault Snyder AI Data Center (Project)
Claim 57945 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Energy Vault Q2 2026 results
Energy Vault · Document date: Aug 6, 2026 · Primary
Source reference: SRC-3163 · Fact sheet · Recorded authority: Party primary
Source URL
https://investors.energyvault.com/overview/
https://investors.energyvault.com/overview/
Reported capacity · 8 MW
Planned / design or future potential · Energy Vault Snyder AI Data Center (Project)
Claim 57946 · Recorded claim type: Design · Review: Approved · Claim date: Not stated
Headline treatment: Separate claim, not added to the headline
- Energy Vault Q2 2026 results
Energy Vault · Document date: Aug 6, 2026 · Primary
Source reference: SRC-3163 · Fact sheet · Recorded authority: Party primary
Source URL
https://investors.energyvault.com/overview/
https://investors.energyvault.com/overview/
Capacity basis · Energy Vault identifies 8 MW for the initial powered shell phase.
Actual · Energy Vault Snyder AI Data Center (Project)
Claim 57947 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Energy Vault Q2 2026 results
Energy Vault · Document date: Aug 6, 2026 · Primary
Source reference: SRC-3163 · Fact sheet · Recorded authority: Party primary
Source URL
https://investors.energyvault.com/overview/
https://investors.energyvault.com/overview/
Location context · Energy Vault data center site | Snyder | Scurry County | Texas
Actual · Energy Vault Snyder AI Data Center (Project)
Claim 111371 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Energy Vault Q2 2026 results
Energy Vault · Document date: Aug 6, 2026 · Primary
Source reference: SRC-3163 · Fact sheet · Recorded authority: Party primary
Source URL
https://investors.energyvault.com/overview/
https://investors.energyvault.com/overview/
Lifecycle status · Construction
Actual · Energy Vault Snyder AI Data Center (Project)
Claim 111372 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Energy Vault Q2 2026 results
Energy Vault · Document date: Aug 6, 2026 · Primary
Source reference: SRC-3163 · Fact sheet · Recorded authority: Party primary
Source URL
https://investors.energyvault.com/overview/
https://investors.energyvault.com/overview/
Reported capacity · 8 MW
Actual · Energy Vault Snyder AI Data Center (Project)
Claim 111373 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
Headline treatment: Selected headline
- Energy Vault Q2 2026 results
Energy Vault · Document date: Aug 6, 2026 · Primary
Source reference: SRC-3163 · Fact sheet · Recorded authority: Party primary
Source URL
https://investors.energyvault.com/overview/
https://investors.energyvault.com/overview/
Capacity basis · The first contracted powered shell phase is designed to deliver 8 MW.
Actual · Energy Vault Snyder AI Data Center (Project)
Claim 111374 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Energy Vault Q2 2026 results
Energy Vault · Document date: Aug 6, 2026 · Primary
Source reference: SRC-3163 · Fact sheet · Recorded authority: Party primary
Source URL
https://investors.energyvault.com/overview/
https://investors.energyvault.com/overview/
Development scale · 8 MW contracted initial powered shell phase
Actual · Energy Vault Snyder AI Data Center (Project)
Claim 111391 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Energy Vault Q2 2026 results
Energy Vault · Document date: Aug 11, 2026 · Corroborating
Source reference: SRC-6241 · Regulatory record · Recorded authority: Official primary
Source URL
https://www.sec.gov/Archives/edgar/data/1828536/000182853626000100/ex991_evpressreleasex2026q2.htm
https://www.sec.gov/Archives/edgar/data/1828536/000182853626000100/ex991_evpressreleasex2026q2.htm
- Energy Vault Q2 2026 results
Energy Vault · Document date: Aug 6, 2026 · Primary
Source reference: SRC-3163 · Fact sheet · Recorded authority: Party primary
Source URL
https://investors.energyvault.com/overview/
https://investors.energyvault.com/overview/
Development milestone · Commercial operation targeted in first half of 2027
Actual · Energy Vault Snyder AI Data Center (Project)
Claim 111392 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Energy Vault Q2 2026 results
Energy Vault · Document date: Aug 11, 2026 · Corroborating
Source reference: SRC-6241 · Regulatory record · Recorded authority: Official primary
Source URL
https://www.sec.gov/Archives/edgar/data/1828536/000182853626000100/ex991_evpressreleasex2026q2.htm
https://www.sec.gov/Archives/edgar/data/1828536/000182853626000100/ex991_evpressreleasex2026q2.htm
- Energy Vault Q2 2026 results
Energy Vault · Document date: Aug 6, 2026 · Primary
Source reference: SRC-3163 · Fact sheet · Recorded authority: Party primary
Source URL
https://investors.energyvault.com/overview/
https://investors.energyvault.com/overview/
Power arrangement · Potential 25 MW second phase
Actual · Energy Vault Snyder AI Data Center (Project)
Claim 111393 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Energy Vault Q2 2026 results
Energy Vault · Document date: Aug 11, 2026 · Corroborating
Source reference: SRC-6241 · Regulatory record · Recorded authority: Official primary
Source URL
https://www.sec.gov/Archives/edgar/data/1828536/000182853626000100/ex991_evpressreleasex2026q2.htm
https://www.sec.gov/Archives/edgar/data/1828536/000182853626000100/ex991_evpressreleasex2026q2.htm
- Energy Vault Q2 2026 results
Energy Vault · Document date: Aug 6, 2026 · Primary
Source reference: SRC-3163 · Fact sheet · Recorded authority: Party primary
Source URL
https://investors.energyvault.com/overview/
https://investors.energyvault.com/overview/
Site configuration · Up to 500 MW long range site plan.
Actual · Energy Vault Snyder AI Data Center (Project)
Claim 111394 · Recorded claim type: Actual · Review: Approved · Claim date: Not stated
- Energy Vault Q2 2026 results
Energy Vault · Document date: Aug 11, 2026 · Corroborating
Source reference: SRC-6241 · Regulatory record · Recorded authority: Official primary
Source URL
https://www.sec.gov/Archives/edgar/data/1828536/000182853626000100/ex991_evpressreleasex2026q2.htm
https://www.sec.gov/Archives/edgar/data/1828536/000182853626000100/ex991_evpressreleasex2026q2.htm
- Energy Vault Q2 2026 results
Energy Vault · Document date: Aug 6, 2026 · Primary
Source reference: SRC-3163 · Fact sheet · Recorded authority: Party primary
Source URL
https://investors.energyvault.com/overview/
https://investors.energyvault.com/overview/
Counterparties and capital
Energy Vault · Developer · CMP-1442
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed.