Cartis diligence evidence schedule
Elea SPO2 São Bernardo do Campo
PRJ-0586 · Site · São Bernardo do Campo, SP, Brazil
Captured 2026-09-06T04:13:10.763Z · Record last updated 2026-08-26
SHA-256: 79b51c00304885069cc29f431f7b1e94679850c949fc55762e3785dd56ed469d
Save a diligence baseline
Download the public evidence as it appears now. Compare a previously saved snapshot to see added, removed and changed claims, counterparties, financing and milestones. Files are read in this browser and are not uploaded.
The fingerprint detects file changes; it is not a digital signature or a claim of independently verified authenticity. Keep your downloaded copy with the transaction file.
Scope and capacity
Elea operates SPO2 in São Bernardo do Campo and plans a major expansion. A 2025 public bid awarded Elea a 17-year, R$2.3 billion contract to build a 30 MVA Petrobras data center at the site.
Headline: 120 MW Planned / design
Numbers refer to their stated physical boundaries and are not added together. Source dates, claim dates and record updates have different meanings. Missing dates and locators are not inferred.
Claims and exhibit sources
Current Status · Operational and expanding
actual · Elea SPO2 São Bernardo do Campo (project)
Claim 53286 · Review: Approved · Claim date: Not published
- SPO2 São Bernardo do Campo
Elea Data Centers · Document date: Not published · Primary
https://eleadatacenters.com/en/datacenters/spo2-sao-bernardo-do-campo/
Acquired From · DXC Technology
transaction scope · Elea SPO2 São Bernardo do Campo (project)
Claim 53287 · Review: Approved · Claim date: 2024-07-16T00:00:00+00:00
- Elea Digital Data Centers announces 120MW footprint expansion in the Greater São Paulo area
Elea Data Centers · Document date: 2024-07-16 · Primary
https://eleadatacenters.com/en/2024/07/16/elea-digital-data-centers-announces-120mw-footprint-expansion-in-the-greater-sao-paulo-area/
Future Expansion Potential · 120 MW
Planned / design or future potential · Elea SPO2 São Bernardo do Campo (project)
Claim 53289 · Review: Approved · Claim date: Not published
Headline treatment: Selected headline
- SPO2 São Bernardo do Campo
Elea Data Centers · Document date: Not published · Primary
https://eleadatacenters.com/en/datacenters/spo2-sao-bernardo-do-campo/
Land Bank · Included in acquisition
actual · Elea SPO2 São Bernardo do Campo (project)
Claim 53291 · Review: Approved · Claim date: 2024-07-16T00:00:00+00:00
- Elea Digital Data Centers announces 120MW footprint expansion in the Greater São Paulo area
Elea Data Centers · Document date: 2024-07-16 · Primary
https://eleadatacenters.com/en/2024/07/16/elea-digital-data-centers-announces-120mw-footprint-expansion-in-the-greater-sao-paulo-area/
High Voltage Substation · Included in acquisition
actual · Elea SPO2 São Bernardo do Campo (project)
Claim 53292 · Review: Approved · Claim date: 2024-07-16T00:00:00+00:00
- Elea Digital Data Centers announces 120MW footprint expansion in the Greater São Paulo area
Elea Data Centers · Document date: 2024-07-16 · Primary
https://eleadatacenters.com/en/2024/07/16/elea-digital-data-centers-announces-120mw-footprint-expansion-in-the-greater-sao-paulo-area/
Petrobras Contract Value · 2,300,000,000 BRL
transaction scope · Elea SPO2 São Bernardo do Campo (project)
Claim 53293 · Review: Approved · Claim date: 2025-09-30T00:00:00+00:00
- Elea wins bid to build 30 MVA Petrobras data center in São Paulo
Elea Data Centers · Document date: 2025-09-30 · Primary
https://eleadatacenters.com/en/2025/09/30/elea-wins-bid-to-build-30-mva-petrobras-data-center-in-sao-paulo/
Petrobras Contract Term · 17 years
actual · Elea SPO2 São Bernardo do Campo (project)
Claim 53294 · Review: Approved · Claim date: 2025-09-30T00:00:00+00:00
- Elea wins bid to build 30 MVA Petrobras data center in São Paulo
Elea Data Centers · Document date: 2025-09-30 · Primary
https://eleadatacenters.com/en/2025/09/30/elea-wins-bid-to-build-30-mva-petrobras-data-center-in-sao-paulo/
Petrobras Build Capacity · 30 MVA
design · Elea SPO2 São Bernardo do Campo (project)
Claim 53295 · Review: Approved · Claim date: 2025-09-30T00:00:00+00:00
- Elea wins bid to build 30 MVA Petrobras data center in São Paulo
Elea Data Centers · Document date: 2025-09-30 · Primary
https://eleadatacenters.com/en/2025/09/30/elea-wins-bid-to-build-30-mva-petrobras-data-center-in-sao-paulo/
Certified Renewable Energy · Operator claim
actual · Elea SPO2 São Bernardo do Campo (project)
Claim 53297 · Review: Approved · Claim date: Not published
- SPO2 São Bernardo do Campo
Elea Data Centers · Document date: Not published · Primary
https://eleadatacenters.com/en/datacenters/spo2-sao-bernardo-do-campo/
Counterparties and capital
DXC Technology · Owner · CMP-1360
Elea Data Centers · Operator · CMP-1196
I Squared Capital · Investor · CMP-1255
Petróleo Brasileiro S.A. — Petrobras · Customer · CMP-1362
Piemonte Holding · Investor · CMP-1361
R$300,000,000 · 2024-07-08
Piemonte estimate across SPO2 and SPO3; not purchase price and not allocated by site.
Piemonte Holding (Other)
Financing record 169; claim-specific source links appear in the exhibit sources where published.
$1,000,000,000 · 2024-07-16
Combined SPO2/SPO3 acquisition and up-to-100 MW expansion program; no site allocation or financing close disclosed.
Elea Data Centers (Sponsor) · Piemonte Holding (Joint Venture Partner)
Financing record 168; claim-specific source links appear in the exhibit sources where published.
This schedule captures public Cartis research. It is not a title, lien or legal-opinion report. Document page/section locators and claim review timestamps are included only when published; this version has no separate locator or claim-review-time feed. Downloaded snapshots are retained by you; Cartis does not archive them automatically.